UNITED24 - Make a charitable donation in support of Ukraine!

Weapons of Mass Destruction (WMD)

Previous PageTable Of ContentsList Of TablesList Of FiguresNext Page

CHAPTER 2. PROPOSED ACTION AND ALTERNATIVES

This chapter describes alternatives for the stabilization of
plutonium solutions currently stored in the
F-Canyon (Figure 2-1).  Sections 2.1 through 2.5 describe the
following alternatives, which Chapter 4
evaluates in detail:
   - No Action
   - Processing to Plutonium Metal (preferred alternative)
   - Processing to Plutonium Oxide
   - Vitrification (Defense Waste Processing Facility)
   - Vitrification (F-Canyon)
Figure 2-2 shows the schedules for these alternatives.
Section 2.6 discusses other actions that would have the potential
to reduce the risk associated with the plutonium solutions but
that, standing alone, do not fulfill the identified purpose and
need for agency action.
Section 2.7 compares the environmental impacts associated with
each alternative, including the storage of plutonium in vaults 
or tanks, as analyzed in Chapter 4. Section 2.8 discusses other 
factors which DOE considers relevant and compares these factors 
to the alternatives. 
Appendix A describes the facilities involved in the alternatives
(i.e., F-Canyon, FB-Line, and associated support facilities).  The
appendix also describes the historic processing methods used in
these facilities (including F-Canyon, FB-Line, and the PUREX
process).  These descriptions might be helpful in understanding
the alternatives discussed below.  Figure 2-3 shows the PUREX
process in F-Canyon and indicates where DOE has stored plutonium
solutions in various stages.
Appendix B describes the potential accidents related to the
continued storage of plutonium solutions and to facility operations 
that would be necessary to implement the alternatives.
In relation to the stabilization alternatives described in this
chapter, and in support of United States nonproliferation policy,
DOE is exploring the possibility of making plutonium that is
surplus to the Nation's defense requirements available for
verification and inspection by the International Atomic Energy
Agency (IAea).
  Figure 2-1.  F-Canyon and surrounding area. 
  Figure 2-2.  Schedules for storage and stabilization 
             alternatives.
  Figure 2-3.  PUREX process in F-Canyon and location of plutonium solutions. 
With the shutdown of the Rocky Flats Plant near Denver, Colorado, 
DOE no longer has the capability to manufacture
plutonium weapon components for the U.S. stockpile.  DOE will
address the plutonium manufacturing capability in the
Programmatic eis on Stockpile Stewardship and Management, and
will address plutonium disposition in the Programmatic eis for
Disposition of Weapons-Usable Fissile Materials (see
Section 1.3).

2.1 No Action

Under the No-Action Alternative, DOE would continue to manage the
approximately 303,000 liters (80,000 gallons) of plutonium
solutions stored in stainless-steel tanks in the F-Canyon as it
has for approximately the past 2-1/2 years.  DOE would continue
to maintain the canyon facility in essentially a "warm standby"
mode of operation in which no additional nuclear materials would
be introduced into the canyons for chemical dissolution and
subsequent processing.  Existing plutonium solutions would not be
processed to produce another form of nuclear material.  DOE would
continue to monitor the storage tanks and would sample plutonium
solutions periodically to evaluate chemistry.  As evaporation of
a solution occurred or as chemical changes warranted, nitric acid
or other chemicals would be added to minimize the potential for
the precipitation of plutonium and the possibility of an
inadvertent criticality.  Solutions would be transferred within
F-Canyon only as required for sampling or to alleviate problems
with equipment (e.g., storage tanks).
The implementation of the No-Action Alternative would neither
reduce the risks associated with storage of the plutonium as a
liquid nor stabilize the solutions.  Further, the implementation
of the No-Action Alternative would not fulfill the need for
agency action.

2.2 Processing to Plutonium Metal

Under this alternative, DOE would use the existing PUREX process
in F-Canyon (see Appendix A) and equipment in FB-Line to convert the
plutonium solutions to metal (see Figure 2-4).  The FB-Line would
convert the solutions to a metal form, similar to that the
facility produced historically.  The metal would be a chemically
stable form of plutonium that DOE could produce without modifying
the existing equipment.  Because there is no need for additional
plutonium for weapons, DOE would not attempt to meet previous specifications or
chemical purities that were applicable for weapons production
(Reis 1994).  The plutonium metal would be packaged and stored,
similar to other plutonium metal already in the FB-Line vault.
  Figure 2-4. Plutonium to Metal Alternative 
After converting the plutonium solutions to a metal, and
packaging and storing, DOE would modify part of the FB-Line
facility.  New equipment would provide the capability to
repackage the plutonium metal into a configuration that meets the
DOE standard for long-term storage of plutonium (DOE 1994b).  DOE
estimates that it could accomplish this activity by late 1997 at
a cost of approximately $3 million.  The DOE standard establishes
criteria to ensure the safe storage of plutonium metal and oxide. 
The criteria are intended to reduce the generation of gas inside
the storage containers.  The generation of gas has the potential
to pressurize and subsequently damage containers.
Rather than modifying FB-Line, DOE could modify another vault
facility (Building 235-F) or construct a new repackaging and vault
facility in the F-Area.  DOE estimates this could cost between $70
and 150 million and that it could complete this work by 2001. 
Although repackaging of plutonium metal could occur in the FB-Line
at the completion of stabilization actions, the environmental
impacts are based on the assumption that the repackaging would
take place in a new vault facility.
The alternative of Processing to Metal would produce a solid form
of plutonium that would be safer and easier to store in the
shortest amount of time.  As a result, this is DOE's preferred
alternative.

2.3 Processing to Plutonium Oxide

DOE would use the existing PUREX process, including the second
plutonium cycle, in F-Canyon to prepare the solutions for
introduction into FB-Line.  Under this alternative, DOE would
modify the FB-Line to support conversion of the plutonium
solutions to a plutonium oxide and to package the material for
storage (see Figure 2-5).  DOE would produce a material form and
packaging configuration that meets the new DOE standard for
long-term storage of plutonium (DOE 1994b).
If the extent of the FB-Line modifications necessary to meet 
this standard were economically or physically impractical (i.e., 
too expensive or not enough space for the equipment required), 
DOE would perform the stabilization in two phases.  DOE would 
provide the capability to convert the material initially to 
an oxide form and package it in FB-Line.  At the same time, 
DOE would either modify an existing vault facility
(e.g., 235-F) or construct a new facility (the Repackaging and
Vault Facility; see Appendix A) to process, package, and store the
oxide in accordance with the new standard.  The oxide initially
produced in FB-Line would be stored in the existing FB-Line vault
until the new or modified facility could be completed.  The new
facility would be in the existing F-Area industrial complex.
  Figure 2-5. Plutonium to Oxide Alternative  
DOE estimates that the minimum required modifications to FB-Line
would cost $7 million and take 3 years to complete.  DOE would
operate the FB-Line for approximately 7 months to convert and
package the oxide for storage.
DOE estimates that modifications to an existing facility or a new
facility would cost between $70 and $150 million and could be
completed by 2001.  Heating and repackaging the oxide would take
approximately 3 months.

2.4 Vitrification (Defense Waste Processing Facility)

Under this alternative, DOE would transfer the plutonium
solutions to the SRS waste tank farm (see Figure 2-6).  
Before transfer, the solutions would be adjusted to ensure 
the safety of the material in the high-level waste tanks.  
DOE has identified several concepts for adjusting the 
solutions:  diluting the solutions with water and chemicals 
to achieve very low plutonium concentrations, diluting the
solutions with depleted uranium, or adding iron and manganese or
other neutron poisons such as gadolinium (DOE 1994a).  
DOE would operate portions of the PUREX process, as required, 
to make the necessary chemical adjustments. The addition of 
poisons or the dilution with depleted uranium would minimize 
the potential for inadvertent nuclear criticality
in the waste tanks.  This material would eventually be
transferred to the Defense Waste Processing Facility for proposed
vitrification.
To demonstrate the feasibility of this alternative, DOE would
have to address a number of issues: 
   - The potential for criticality if plutonium precipitated
  during and following transfer to the high-level waste tanks. 
  Detailed safety analysis would be required to address this
  concern and determine methods to reduce the potential for
  criticality.
   - The capability of the Defense Waste Processing Facility to
  process plutonium-bearing high-level waste (in other than
  trace quantities) has not been fully evaluated with respect
  to the effect that this material would have on the
  vitrification process.
   - Transfer of plutonium solutions to the high-level waste
  tanks has not been included in the High-Level Waste System
  Plan (WSRC 1994b).  The availability of sufficient tank
  space, given plans to remove waste from and retire old waste
  tanks, must be addressed.
  Figure 2-6. Vitrification (Defense Waste Processing Facility) Alternative 
DOE estimates it would take approximately 6 years to perform the
technical studies, training, and qualification efforts necessary 
to ensure safe operation for transferring the solutions and subsequent
vitrification using this stabilization alternative.  DOE has
estimated that evaluations for transferring the solutions to the
high-level waste tanks could be completed in approximately 3
years (WSRC 1994a).  However, the solutions would not be
transferred to these tanks until all studies for vitrification
were final.  After these studies were complete, DOE estimates
that it would take an additional 3 years to complete the process
of transferring all the plutonium solutions to the high-level
waste tanks because of the availability of tank space and
criticality concerns.  Under this alternative, DOE would continue
to store plutonium solutions in the F-Canyon, similar to the No-
Action Alternative, during the 6 years required to complete the
technical evaluations.  As a precursor to stabilization, DOE
would operate the second plutonium cycle.  The vitrification of
plutonium solutions would not begin within the 10-year period
evaluated in this eis.  As a result, this analysis does not inclu
de the impacts of vitrification.  However, if this alternative
were implemented, solutions would eventually be vitrified and the
environmental impacts associated with proposed Defense Waste Processing
Facility operation would occur.

2.5 Vitrification (F-Canyon)

Under this alternative, DOE would modify an existing portion of
F-Canyon, previously called the Multi-Purpose Processing Facility
and now called the F-Canyon Vitrification Facility.  The
modifications would include removal of equipment no longer
required and the installation of any new equipment required for
the vitrification process.  Appendix A contains a brief
description of the F-Canyon Vitrification Facility and a summary
of the modifications required.  DOE would operate portions of the
PUREX process in F-Canyon, as required, to prepare the solutions
for vitrification.  The vitrification process would involve
concentrating the plutonium solution in a small geometrically
favorable tank (i.e., the physical dimensions of the tank are
such that a nuclear criticality could not occur).  The solution
would be mixed with finely ground glass (frit) and fed to a small
melter.  Molten borosilicate glass would be produced and poured
into stainless-steel canisters.  The canisters would be stored in
existing vaults at the F-Canyon facility.  Figure 2-7 shows this
process.
The process relies on similar, large-scale technology developed
for proposed use in the Defense Waste Processing Facility. 
However, some process development work would be required due to
the amount of fissile material that would be vitrified.  DOE
estimates that approximately $27 million in capital costs would be
required to modify the F-Canyon to provide vitrification
capability.  In addition, DOE estimates that it could complete
the necessary process development work and physical
  Figure 2-7. Vitrification (F-Canyon) Alternative 
modifications by early 1999 and that it would take approximately
6 months to vitrify the plutonium solutions.

2.6 Other Activities for Reduction of Risk

DOE identified the following activities that would have the
potential to reduce the risks associated with the plutonium
solutions in F-Canyon:  the transportation of the solutions to
H-Canyon for stabilization, purification of the solutions by 
processing those that had the greatest criticality risk
through the second plutonium cycle in F-Canyon, those risk 
reduction activities identified in the DOE Assessment of Interim
Storage of Plutonium Solutions in F-Canyon and Mark-31 Targets in
L-Basin at the Savannah River Site (DOE 1994a), and shipment of the
solutions off the Site for stabilization.  These risk reduction 
activities would be in addition to those encompassed by the 
No-Action Alternative and already taken to reduce the risk, 
such as the addition of boron to selected tanks
and the periodic adjustments of tank chemistry and concentrations
to minimize the potential for precipitation of plutonium.
DOE evaluated the potential alternative of operating portions of
the PUREX process (e.g., the second plutonium cycle) in F-Canyon. 
Figure 2-3 shows the current storage locations of the solutions in
the various portions of the PUREX process.  As Figure 2-3 demonstrates,
only a small amount of the solutions [approximately 15,100 liters
(4,000 gallons)] have been through all the PUREX stages.
The initial stages of the PUREX process, head-end and first
cycle, remove fission products and some impurities.  In addition,
first cycle separates uranium and plutonium solutions from each
other.  The second cycle concentrates plutonium for introduction
to the FB-Line for conversion into a metal.
Before the preparation of this eis, DOE discussed the possibility
of operating only second cycle to process all the plutonium
solutions currently in F-Canyon to reduce the risk of continued
storage of plutonium (Fiori 1994).  Operational upgrades for that
portion of the F-Canyon were nearing completion, and the
performance operational readiness review was under way.  DOE
believed that the operation of second cycle as a purification
activity would reduce the risk of inadvertent criticality, which
could occur as a result of the current abnormal solution
chemistry.  Operation of the second cycle could also reduce the
chance of leakage by consolidating the solutions in fewer tanks. 
However, releases could still occur from accidents due to leaks,
spills, transfer errors, and other accidents associated with
storing plutonium in a liquid form.  These accident risks could
be eliminated only by converting the liquid form to a solid
form.
The use of the second cycle only would require changes to the process 
historically used to process plutonium solutions.  Rather than 
moving the solutions sequentially through each stage of the PUREX 
process, the revised process would transfer the solutions directly 
to the second cycle for the removal of fission products and the 
separation and concentration of plutonium and uranium.  The PUREX 
process has never been operated in this manner.  To do so would require
process development work and establishment of operating
parameters, which would take several months.  Nevertheless, even
if DOE could resolve the technical issues, there would be several
important issues associated with implementation of this potential
alternative.  For example, the operation of the second plutonium
cycle would result in unprecedented high levels of radiation in
the second cycle portion of the facility due to the presence of
fission products.  These fission products normally would have
been removed in the head end and first cycle portion of the
facility, which has shielding to reduce potential radiation
exposure to workers.  The portion of the facility housing the
second plutonium cycle is not as heavily shielded.  The chemistry
of the solutions produced would be within known technical
experience.  The risk associated with plutonium in solution
(e.g., inadvertent criticality) would remain until the plutonium
solutions were converted to a stabilized form.  Further, because
the second plutonium cycle functions to increase the
concentration of the plutonium, an inadvertent criticality would
result in a greater release of radioactivity.  Purification, like
the other risk reduction activities described in DOE (1994a),
would not fully mitigate the inherent risks of plutonium being
stored in liquid form.  As evaluated in this eis, however, purification of
the solutions utilizing the second plutonium cycle would be part
of the alternatives that would stabilize to a metal or an oxide.
DOE estimates that the impacts for normal operations and
accidents associated with PUREX-related operations are within the
impacts discussed in Chapters 4 and 5 of this eis.  PUREX
operations would be likely to generate slightly greater impacts
than the No-Action Alternative because operating the process would involve
transferring the material through equipment not used for No
Action.  However, the impacts would be well below those estimated
for the Processing to Metal or Processing to Oxide Alternative
because the operation of the PUREX process would be part of the
activities necessary to complete those stabilization
alternatives.  The increase in impacts above No Action would be
likely to occur primarily in the generation of high-level waste
and F-Canyon worker radiation exposure.
Finally, regarding the transportation of the plutonium solutions
in F-Canyon to H-Canyon for stabilization, the shipment, while
theoretically feasible, would involve all the risks associated
with the alternatives for stabilization plus the risks that would
be associated with the transport of radioactive liquids between
two facilities.  Further, the time required to accomplish this
alternative would be longer than that for any other alternative. 
The shipment of the plutonium solutions to another site for
stabilization would involve the additional risk and questionable
feasibility of shipping plutonium solutions over public
thoroughfares.

2.7 Comparison of Alternatives

Table 2-1 compares the environmental consequences for the five
alternatives based on the assessments contained in Chapter 4. 
The table summarizes how each alternative compares to the
others.

2.8 Other Factors

The selection of an alternative for stabilizing the F-Canyon
plutonium solutions depends in part on existing technology (or on
technology that DOE could develop quickly), the capabilities of
existing SRS facilities, and the extent to which the actions
would support long-term storage objectives.  Consistent with a
comprehensive review of long-term options for plutonium
disposition, DOE will consider the technical, nonproliferation, 
environmental, budgetary, and economic aspects of each alternative 
before it selects one alternative for implementation.  In addition to
comparing alternatives against the environmental criteria listed
in Table 2-1, DOE considered other factors related to the
  Table 2-1. Comparison of the potential environmental impacts of the alternatives.     
stabilization of nuclear materials.  These factors are
representative of issues addressed by the National Academy of
Science in its study of the management and disposition of
plutonium (NAS 1994), the Office of Technology Assessment
plutonium study (OTA 1993), and comments received during the eis
scoping period.  The following sections describe these factors.

2.8.1 NEW FACILITIES REQUIRED

This factor considers qualitative impacts on the number and size
of new facilities required, and the probable long-term
restoration requirements after their use.  The No-Action and
Vitrification Alternative using the Defense Waste Processing 
Facility would rely totally on existing facilities and, therefore, 
would be the most advantageous because they could be implemented 
immediately with no additional capital or environmental impact 
due to construction.  The Processing to Metal Alternative would 
require minor modifications to FB-Line to provide new repackaging 
capabilities for the metal produced.  The Processing to Oxide 
Alternative would involve more extensive modifications to FB-Line 
and potentially a new facility. Similarly, the Vitrification Alternative 
using F-Canyon would require extensive modifications to the facility.

2.8.2 SECURITY AND NONPROLIFERATION

This factor relates to how well each alternative supports
national security objectives and nonproliferation.  This issue is
being debated on the national and international level, and
consensus has yet to be reached.  However, DOE has qualitatively
evaluated the alternatives and rated them in comparison to one
another.
All the alternatives involve the use of facilities within
controlled industrial areas of the SRS, which are supported and
protected by an armed guard force.  However, the solutions or
stabilized forms of plutonium would have varying degrees of use
in potentially supporting or leading to the manufacture of a
nuclear weapon.  Methods could be used to further reduce this
potential.  For example, DOE considered the addition of fission
products to increase the radioactivity of the stabilized form of
material (e.g., metal).  The addition of fission products would
make the material essentially "self-protecting" from theft or
potential use in weapons because of high radiation levels. 
However, this method would result in increased exposures to
personnel performing processing and handling operations (e.g., at
FB-Line).  DOE does not consider such increased exposures to
personnel to be warranted based on the relatively small amount of
plutonium that these solutions represent in comparison to the
U.S. stockpile.  DOE has committed to prohibit the use of plutonium-239 and
weapons-usable highly enriched uranium separated or stabilized
during the phaseout, shutdown, and cleanout of weapons complex
facilities for nuclear explosive purposes (Reis and Grumbly 1994).  
Further, in support of United States nonproliferation policy, 
DOE is exploring the possibility of making plutonium that is surplus 
to the Nation's defense requirements available for verification and 
inspection by the International Atomic Energy Agency (IAea).
The Vitrification Alternatives would produce a material form that
would be least attractive for use in manufacturing or producing a
nuclear weapon.  Therefore, they represent the most advantageous
alternatives in this regard.  The Processing to Plutonium Metal
Alternative would result in a form that closely resembled that used 
in weapons production.  The No-Action and Processing to Plutonium
Oxide Alternatives would maintain or convert plutonium to forms
that would require increasing degrees of processing to produce 
a form suitable for weapons use. In either the Metal or Oxide alternative, 
large quantities of plutonium already exist in these forms; therefore,
processing this small increment of plutonium to either of these forms would
not impact decisions and alternatives for ultimate disposition.

2.8.3 IMPLEMENTATION SCHEDULE

Of the stabilization alternatives, the Processing to Metal
Alternative could be implemented in the shortest period of time. 
The Processing to Oxide Alternative could begin within
approximately 3 years.  The Vitrification Alternative using F-
Canyon could begin within approximately 5 years. 
Vitrification in the Defense Waste Processing Facility could not
be completed within 10 years, but initial actions to implement
that alternative could begin in approximately 6 years.  The
No-Action Alternative could be implemented immediately, but would
not satisfy the DOE purpose and need.

2.8.4 TECHNOLOGY AVAILABILITY AND TECHNICAL FEASIBILITY

This factor relates to the extent that technology development is
required and the likelihood of success.  Of the stabilization
alternatives, Processing to Plutonium Metal represents the most
technically proven; it would use existing technology and
equipment.  The Processing to Plutonium Oxide Alternative is also 
technically feasible, but would require technology development and new
equipment to accomplish stabilization.  Similarly, the Vitrification 
Alternatives appear to be technically feasible, but would require 
the most technology development.  The technical uncertainty would 
increase as the stabilized form differed from that historically produced.  
There would also be technical uncertainty associated with the continued
storage of the plutonium solutions under the No-Action Alternative
as a result of radiation and chemically induced changes in the
solution chemistry and form.

2.8.5 LABOR AVAILABILITY AND CORE COMPETENCY

There are differences between the level of personnel knowledge
and training required for each alternative.  In addition, there
would be impacts from providing the needed level of training. 
All the alternatives would require approximately the same amount of labor
to implement.  The No-Action and Processing to Plutonium Metal Alternatives 
would involve activities similar to those performed in the past; as a result,
facility personnel would have existing training and qualification
programs to maintain core competency.  The Processing to
Plutonium Oxide and Vitrification Alternatives would require
additional levels of training; the only impact anticipated from
such additional training would be the incremental funding
required.

2.8.6 AGING FACILITIES

All the alternatives involve the use of existing facilities, some
of which have been in operation for more than 40 years (e.g.,
F-Canyon).  The No-Action Alternative would require continued
storage of the material in the F-Canyon and is, therefore, the
least desirable or advantageous in this regard.
The Vitrification (Defense Waste Processing Facility) Alternative
would require maintenance of the solutions in F-Canyon for approximately 
6 to 9 years.  In addition, it would involve the transfer of
the plutonium solutions to the high-level waste tanks, some of
which have been in use since the 1950s.  Therefore, this
alternative has only a slight advantage over the No-Action
Alternative. 
The Vitrification (F-Canyon) Alternative would require maintenance
of the solutions in the canyon for approximately 5 years.  Even
though this alternative would use a substantial amount of new
equipment, the area that would be modified is in the F-Canyon, 
which is more than 40 years old.  The vitrified material would
be stored in an existing vault or the F-Canyon.  As with the
Vitrification (DWPF) Alternative, this alternative has only a
slight advantage over the No-Action Alternative.
The Processing to Plutonium Oxide Alternative could involve
limited use of the F-Canyon and FB-Line facilities.  It could use a
new or modified facility for conversion or repackaging of the
oxide and eventual storage.  If a new facility were required, it
would represent the minimum reliance on existing facilities.
While the Processing to Plutonium Metal Alternative would involve
limited use of the F-Canyon and FB-Line for stabilization, it
would involve continued storage of the metal in the FB-Line
vault.  Therefore, it represents some reliance on aging
facilities, but also represents an advantage over the No-Action
and Vitrification Alternatives.

2.8.7 MINIMUM CUSTODIAL CARE

The Vitrification Alternative would eventually result in a
stabilized form of material that would require a minimum of
custodial care.  However, continued custodial care of the
solutions would be required in F-Canyon or the high-level waste 
tanks until vitrification was accomplished.  Continued storage would 
involve maintaining a dispersible form of material for at least 5 
years in facilities with limited passive safety features, such as 
tanks that do not have a physical geometry that prevents the
possibility of a criticality.  Therefore, this alternative is
undesirable.  The No-Action Alternative would involve a similar level 
of custodial care and, therefore, is also undesirable.
The Processing to Plutonium Oxide Alternative would require
continued storage of the solutions for approximately 3 years.  
This material form would require continued surveillance on a 
frequent basis.  The alternative could use existing facilities 
that have limited passive safety features.   The new or
modified facility and eventual storage configuration could
incorporate the increased use of passive safety systems such as
specially designed and built racks that would prevent movement of
material during earthquakes.  (A passive safety system is one that
requires no action to function, such as a reinforced door panel 
for a vehicle.  An active safety system is one that requires an 
action, such as buckling a vehicle seatbelt.)
The Processing to Plutonium Metal Alternative would result in a
reduced level of custodial care after stabilization of the
solutions.  Although the passive safety systems of the storage
facility (FB-Line vault) are limited, plutonium metal is a
significantly less dispersible form than solutions or oxide.  As
a result, this alternative is the most advantageous in minimizing
custodial care.

Previous PageTable Of ContentsList Of TablesList Of FiguresNext Page



NEWSLETTER
Join the GlobalSecurity.org mailing list