Appendix C
C.1 Cost Methodology
This section describes the methodology used to determine
life-cycle costs for comparison of alternative treatment, storage,
and disposal facilities. Life-cycle costs include preliminary
planning, design, construction, operation, secondary waste disposal,
and post-operation decommissioning. These costs are distributed
along a timeline, and then converted to an equivalent cost in
terms of the current value of money. Major components of life-cycle
costs include building, equipment, operation and support manpower,
and secondary waste disposal costs. The purpose of the cost model
is to provide data that can differentiate between treatment options.
The cost model consistently applies the same assumptions, such
as labor cost rates, building square-footage costs, and others,
to the estimating process. Conceptual design estimates for planned
facilities and actual estimates for existing facilities are used
where possible. For the purpose of this environmental impact
statement (eis), the U.S. Department of Energy (DOE) developed
cost assumptions using Westinghouse Savannah River
Company standard estimating techniques. For appropriate comparison,
DOE assumed that treatment facilities that do not already exist
would be located onsite. Each facility estimate includes option-specific
costs for the major equipment, the number of man-hours per year
required to operate the facility, the facility start-up date,
the operating life of the facility, and the required design basis
throughput.
Projected facility costs and manpower requirements
differ between the draft and final eis. This is due to the following
factors: a refinement of the parameters that determine operating
manpower, building, and equipment costs; a correction to the scope
of no-action alternative costs to make them consistent with the
other alternative - waste forecast estimates; and new initiatives
in alternative B that lowered facility costs for this alternative.
In addition, the costing methodology bases construction manpower
requirements on building and equipment costs; therefore, both
operating and construction employment differ between draft and
final eis. This, in turn, affects projections of socioeconomic
and traffic impacts. Cost differences are shown in Table C-1.
The cost analysis was changed to be consistent with the Baseline
Environmental Management Report (DOE 1995) developed by DOE
to ensure consistent reporting on estimating future facility construction
and operation costs. This report is used to establish future
budgetary requirements for the DOE complex.
No action |
| ||
|
|
| |
|
|
| |
|
|
|
In most instances, the estimates are based on facilities
for which there has been little, if any, conceptual design. The
estimates were prepared only for the purpose of identifying salient
cost differences between technologies. These facility estimates
are not sufficiently mature to be used for budgeting purposes.
C.1.1 RELATIONSHIP TO SRS DRAFT SITE TReaTMENT PLAN COST METHODOLOGY
The cost model developed for the SRS Draft Site
Treatment Plan (DOE 1994a) was used as a basis for the eis
cost model. The major difference between the two models is the
difference in scope of the two efforts. The draft sit treatment
plan proposes specific treatments over the next 5 years for a
known mixed waste inventory. This eis examines
alternatives for treating, storing, and disposing of wastes that
would be generated over the next 30 years and investigates
the consequences of each alternative. The eis cost analyses consider
low-level, hazardous, mixed, and transuranic wastes;
the site treatment plan deals only with
mixed wastes. The uncertainties in this eis that affect the modelling
of costs include the waste forecasts (amounts of waste generated),
schedules (treatment need dates), and availability of funds.
C.1.2 APPLICATION OF COST METHODOLOGY FOR OPTIONS SELECTION
Process and materials descriptions were developed for full treatment, storage, and disposal options evaluated in the in-depth analysis in Section 2.3 of this eis. From these descriptions, a list of the required processing equipment, the sizes and types of buildings needed, and the necessary support equipment was developed. To provide equivalent comparisons of the options, it was initially assumed that 1,000 cubic meters (35,300 cubic feet) of waste would be processed per year by each facility. The costs for processing equipment, buildings, and support equipment were developed using Savannah River Site (SRS) experience and information from a waste management facilities cost report (Feizollahi and Shropshire 1992) prepared for the DOE Idaho National Engineering Laboratory. The manpower requirements were estimated with the COSTPRO (Hess 1994a) program used by Westinghouse Savannah River Company for estimating onsite work.
Because the in-depth options analysis evaluated individual
treatability groups, it was not sufficiently broad to identify
an integrated system of treatment, storage, and disposal facilities
for the entire SRS. The in-depth options analysis was supplemented
with a second analysis that considered the availability of excess
capacity in existing facilities and the environmental advantages
and economies of scale achieved by expanding planned facilities
to accommodate additional treatability groups that would otherwise
require other stand-alone treatment, storage, and disposal facilities.
The cost to dispose of secondary waste was developed from existing
SRS facilities and included in the cost model.
As an example, Table C2 (and Figure C-1)
illustrates the economies of scale for the non-alpha vitrification
facility. It displays the
total cost and the total and incremental cost per unit volume
of throughput. The calculation procedure is described in detail
in Section C.2. The table indicates that unit costs decreases
from approximately $7,700 to $2,000 per cubic meter when annual
throughput increases from 1,000 to 5,000 cubic meters.
Table C-2. Economies of scale for the non-alpha vitrification facility
(cubic meters) | ($ per cubic meter)c | Unit Cost ($ per cubic meter)c | ||
1,000 | 19,000 | 146,501 | 7,711 | 7,711 |
2,000 | 38,000 | 159,190 | 4,189 | 668 |
3,000 | 57,000 | 171,881 | 3,015 | 668 |
4,000 | 76,000 | 184,573 | 2,429 | 668 |
5,000 | 95,000 | 197,267 | 2,082 | 668 |
a. Source: Hess (1995).
b. To convert to cubic feet, multiply by 35.31.
c. To convert to $ per cubic feet, divide by 35.31.
C.1.3 APPLICATION OF COST METHODOLOGY FOR ALTERNATIVE TReaTMENT, STORAGE, AND DISPOSAL SCENARIOS
Facility costs vary with the amount of waste treated
per year. Therefore, the cost model used for this eis for equipment
and buildings based on a 1,000 cubic meter (35,300 cubic feet)
annual throughput was modified to account for the actual volume
of waste the facility would be required to treat annually. The
estimates from the Idaho National Engineering Laboratory facilities
cost report were used as the basis for this part of the model.
The equipment and facility descriptions in the Idaho National
Engineering Laboratory report were examined to see how closely
they matched the specifications of the treatments and processes
described in this eis. The Idaho National Engineering Laboratory
estimates were modified as required to match the specifications
in this eis. Linear and exponential curves were fit to the Idaho
National Engineering Laboratory costs versus capacity estimates.
The linear model closely matched the data, so it was used. For
further cost development, both equipment and building costs were
defined as the coefficient (cost per cubic meter of waste processed)
times the annual volume of waste plus a fixed cost. The coefficients
and fixed values come from calculations that determine those values
which provide the best fit between actual Idaho National Engineering
Laboratory data and the linear (straight line) approximation (i.e.,
cost = cost coefficient ÷
yearly volume + fixed cost ). The COSTPRO
model facility operating labor hours were also developed into
a linear model. (Annual labor = labor coefficient ÷
yearly volume + fixed labor; Tables C-3, C-4, and C-5 list the
fixed values and coefficients developed for equipment cost, building
cost, and labor, respectively.)
The costs for storage and disposal facilities, most
of which do not have equipment costs, were developed differently.
The labor hours on a per-cubic-meter basis were developed with
COSTPRO. The cost to build each facility was estimated by assuming
that new facilities would hold the same amount of waste as existing
facilities, dividing the waste that would need to be stored or
disposed of by the facility volume capacity, and multiplying the
resulting number of facilities needed by the cost of completed
existing facilities.
($1,000) | ($1,000/cubic meter/year)b | |
Off-site treatment and disposal | 11,257 | 0.0699 |
Containment building - macroencapsulationmacroencapsulation | 3,259 | 0.0385 |
Off-site smelter | 10,521 | 0.2597 |
Transuranic waste characterization/certification facility | 14,112 | 0.0396 |
Soil sort facility | 10,983 | 0.2101 |
Containment building - decontamination | 1,302 | 0.0035 |
Off-site low-level waste volume reduction | 4,981 | 0.0265 |
Non-alpha vitrification facility | 13,570 | 0.3361 |
Alpha vitrification facility | 25,102 | 0.0840 |
a. Source: Hess (1995).
b. To convert to $1,000 per cubic foot per year, divide by 35.31.
($1,000) | ($1,000/cubic meter/year)b | |
Off-site treatment and disposal | 3,259 | 0.0241 |
Containment building - macroencapsulation | 3,459 | 0.0243 |
Off-site smelter | 8,744 | 0.2824 |
Transuranic waste characterization/certification facility | 11,891 | 0.0396 |
Soil sort facility | 2,470 | 0.0611 |
Containment building - decontamination | 832 | 0.0120 |
Off-site low-level waste volume reduction | 1,776 | 0.0040 |
Non-alpha vitrification facility | 9,298 | 0.2403 |
Alpha vitrification facility | 23,683 | 0.1123 |
a. Source: Hess (1995).
b. To convert to $1,000 per cubic foot per year, divide by 35.31.
(manhours/year) | (manhours/year/ cubic meter)b | |
Off-site treatment and disposal | 21,145 | 0.0699 |
Containment building - macroencapsulation | 15,688 | 0.0385 |
Off-site smelter | 52,581 | 0.2597 |
Transuranic waste characterization/ certification facility | 42,332 | 0.0396 |
Soil sort facility | 14,196 | 0.2101 |
Containment building - decontamination | 27,996 | 0.0035 |
Supercompactor | 7,027 | 0.0265 |
Non-alpha vitrification facility | 31,796 | 0.3361 |
Alpha vitrification facility | 37,478 | 0.0840 |
a. Source: Hess (1995).
b. To convert to manhours per year per cubic foot, divide by 35.31.
C.1.4 SPECIAL CONSIDERATIONS FOR COST CALCULATIONS
DOE decided to assign costs to wastes with required
treatments differently than to wastes for which treatment was
optional. In the cost model, wastes with required treatments
were assigned both the fixed costs for treatment and the variable
costs associated with their specific volume (including equipment,
building, and labor costs). The wastes with optional treatments
were only assigned the variable costs associated with their additional
volume. This methodology assumed that these wastes would use
the excess capacity in facilities built to support required treatments.
It also burdened wastes with specified treatments more than wastes
with optional treatments.
A spreadsheet was developed for each alternative/forecast which listed the individual treatability groups and the options for treatment and disposal. The waste volume assigned to each option was entered along with the yearly fixed programmatic costs, the variable waste costs, and the volume reduction ratio achievable by that treatment option for the specific waste type. The variable waste costs included the cost to dispose of the secondary waste produced by the treatment. These inputs were summed and averaged over the 30year analysis period and put into a specific treatment cost model. The total waste to be processed was averaged over the operating period of the facility for the sizing, costing, and operating manpower calculations. Based on waste volume, fixed costs, variable costs, volume reduction ratio, the facility operating period, and the input dates for design start and operations start, the treatment cost model calculated the equipment and building costs, total operating manhours, the pre-project costs, the total estimated cost to build the facility, the costs to decommission and dispose of the facility after all the waste has been treated, and the secondary waste disposal costs. The various costs were distributed over the appropriate time periods. The costs were then escalated and discounted to get a life-cycle cost, the present worth cost for the treatment option, and a cost per cubic meter of input waste. Costs calculated in the treatment cost model were returned to the spreadsheet for summation, which yielded the total option cost. The specifics of how these calculations were performed are discussed in Section C.2.
Another spreadsheet calculated the manpower required
for each facility. Engineering, operation, and support manpower
were included over all phases of the life cycle. The life cycle
includes pre-project planning, design and construction operations,
and facility decontamination and decommissioning.
A master labor spreadsheet collected the individual facility
manpower calculations and generated totals for each treatment,
storage, and disposal alternative.
C.2 Typical Cost Estimate
This section describes the calculation procedure
for determining life-cycle cost. For illustration, each component
is explained and calculated for the non-alpha vitrification
facility (Hess 1994b, 1995).
Each component of the cost is calculated in units
of thousands of dollars and shown as a total dollar value in parenthesis.
The values have been rounded to the nearest thousand following
calculation; they do not always equal the sum or product of the
listed values.
C.2.1 TOTAL FACILITY COST
The total facility cost consists of pre-project costs,
design and construction costs, contingency costs, operating costs,
and post-operation costs. Escalation and discount rates are applied
to the costs as they are incurred to determine life-cycle costs.
Each step of the calculation is illustrated for a typical facility. The cost factors for the non-alpha vitrification facility are presented in Table C-6.
C.2.1.1 Assumptions
The cost estimates are based on the following assumptions:
- Annual manpower (manhours/year) is calculated
using the COSTPRO program and the assumption from the in-depth
options analysis that 1,000 cubic meters (35,300 cubic feet) per
year of waste would be processed through each facility.
- A uniform, fully burdened labor rate of $75/manhour in 1994 dollars is assumed for all workers for all activities, including design, construction, operation, and decontamination and decommissioning. The labor rate includes salary, benefits, and indirect expenditures (i.e., overhead).
- The year in which project planning and preconceptual
design start occurs is assumed for each facility to be 2 years
before the detailed design and construction start.
- The operation start is the year in which the
facility would begin operating.
- The operation period, in years, is the length of time the facility would be operating.
- The facility waste volume (throughput in cubic
meters per year) is calculated from the total volume to be treated
averaged over the operational period of the facility. Averaging
the waste volume defines a realistic design capacity for the equipment
and building, not the peak waste generation rates.
- The manner in which the treated waste would
ultimately be disposed is based on the disposal cost (calculated
in dollars per cubic meter; to convert to dollars per cubic foot,
divide by 35.31). The variable costs include the cost to build
and operate the final disposal facilities.
- A volume reduction ratio (x:1) is used for
each specific waste through each specific facility. The final
disposal volume (after volume reduction) is multiplied times the
disposal costs per unit volume of waste and added to the facility
costs as a portion of the facility life-cycle costs.
Table C-6. Total facility cost for the non-alpha vitrification facility
Throughput (cubic meters/year) | 3,063 |
Equipment cost (Table C-2) | |
Variable cost ($1,000/cubic meter/year) | 0.3361 |
Fixed cost ($1,000) | 13,570 |
Building cost (Table C-3) | |
Variable cost ($1,000/cubic meter/year) | 0.2403 |
Fixed cost ($1,000) | 9,298 |
Annual operating manpower (Table C-4) | |
Variable labor (manhours/cubic meter/year) | 0.3361 |
Fixed labor (manhours/year) | 31,796 |
Annual waste type support manpower (manhours/year)a | 38,848 |
Labor rate ($1,000/manhour) | 0.075 |
Is a RCRAb Part A Permit required? | No |
Is a RCRA Part B Permit required? | Yes |
Detailed design and construction start (year) | 2002 |
Operation start (year) | 2006 |
Operation period (years) | 19 |
Disposal cost ($1,000/cubic meter) | 7.636 |
Volume reduction ratio (x:1) | 7.43c |
a. Administrative and other support personnel.
b. Resource Conservation and Recovery Act.
c. A weighted average of volume reduction ratios for each waste type based upon experience with vitrification facilities.
C.2.1.2 Construction Costs
Construction costs consist of equipment costs, building costs, field indirect costs (e.g., auxiliary support personnel), field direct costs (e.g., temporary construction facilities), field and design engineering costs, construction management, and project management costs.
Equipment cost (EC) EC = | Cost coefficient Throughput Fixed cost | [0.3361] ÷ [3,063] + [13,570] = 14,600 (or $14,600,000) |
Building cost (BC) BC = | Cost coefficient Throughput Fixed Cost | [0.2403] ÷ [3,063] + [9,298] = 10,034 (or $10,034,000) |
Field indirect cost (FIC) FIC = | 8 percent Equipment cost | [0,08] ÷ [14,600] = 1,168 (or $1,168,000) |
Field direct cost (FDC) FDC = | 14 percent Building cost | [0.14] ÷ [10,034] = 1,405 (or $1,405,000) |
Engineering cost (ENGC) ENGC = | 22 percent Equipment and building cost | [0.22] ÷ [14,600 + 10,034] = 5,419 (or $5,419,000) |
Construction management cost (CMC) CMC = | 7 percent Equipment and building cost | [0.07] ÷ [14,600 + 10,034] = 1,724 (or $1,724,000) |
Project management cost (PMC)
PMC = |
9 percent Equipment and building cost | [0.09] ÷ [14,600 + 10,034] = 2,217 (or $2,217,000) |
Total construction cost (TCC) TCC = |
Equipment cost Building cost Field indirect cost Field direct cost Engineering cost Construction management cost Project management cost | [14,600] + [10,034] + [1,168] + [1,405] + [5,419] + [1,724] + [2,217] = 36,567 (or $36,567,000) |
C.2.1.3 Total Estimated Cost (TEC)
Total estimated cost is construction cost plus contingency
(C). The contingency is the funding required to give an 80-percent
confidence level that the project will be completed within the
estimated funding and schedule. Estimates done at the conceptual
planning level are typically + 40 percent. For this effort
a contingency of 35 percent of the construction cost was used.
Contingency (C) C = | 35 percent total construction cost | [0.35] ÷ [36,567] = 12,799 (or $12,799,000) |
Total estimated cost (TEC) TEC = |
Construction cost Contingency | [36,567] + [12,799] = 49,366 (or $49,366,000) |
C.2.1.4 Pre-Project Costs
Based on experience with projects at SRS, the planning
costs for project definition and implementation of DOE Order 4700,
"Project Management System" requirements were estimated
as 5 percent of the total estimated cost, as calculated above,
and preconceptual design costs were estimated as 10 percent
of the total estimated cost.
Planning cost (PLANC) PLANC = | 5 percent Total estimated cost |
[0.05] ÷ [49,366] = 2,468 (or $2,468,000) |
Preconceptual design cost (PDC) PDC = | 10 percent Total estimated cost | [0.10] ÷ [49,366] = 4,937 (or $4,937,000) |
The permitting costs are based on an estimate of
the need for new permits or required modifications to existing
permits. A Resource Conservation and Recovery Act (RCRA) Part
A permit or modification is estimated to cost $150,000. A RCRA
Part B permit is estimated to cost $1,500,000.
Permitting cost (PC) PC = | Resource Conservation and Recovery Act Part B permit | 1,500 (or $1,500,000) |
Costs associated with preparation for operations (e.g., a procedure
document) are estimated to be $150,000.
Preparation for operations costs (POC) POC = | 150 (or $150,000) | |
Pre-project cost (PPC) PPC = | Planning cost Preconceptual design cost Permitting cost Preparation for operation cost | [2,468] + [4,937] + [1,500] + [150 ] = 9,055 (or $9,055,000) |
C.2.1.5 Facility Operating Costs
Two types of manpower requirements are considered.
Operating manpower consists of personnel who actually operate
the facility as estimated by the linear model developed from the
COSTPRO program. Waste type support manpower includes administrative
and other support personnel based on a distribution of these requirements
to each waste type as reported in FY 1993 SRS Waste Cost Analysis
(Taylor, McDonnel, and Harley 1993).
Annual operating manpower (AOM) AOM = | Labor coefficient Throughput Fixed labor | [0.3361] ÷ [3,063] + [31,796] = 32,826 (manhours per year) |
Operating manpower cost (OMC) OMC = |
Annual operating manpower Labor rate in $1,000/hour Facility operation period | [32.826] ÷ [0.075] ÷ [19] = 46,777 (or $46,777,000) |
Annual waste type support manpower (AWTSM) AWTSM = | Fixed amount | [38,848] = 38,848 (manhours per year) |
Waste type support manpower cost (WTSMC) WTSMC = | Annual waste type support manpower Labor rate in $1,000/hour Facility operation period | [38,848] ÷ [0.075] ÷ [19] = 55,358 (or $55,358,000) |
Utilities costs vary from 4 percent to 20 percent
of the operating manpower cost. The variance is the following
function of the equipment cost: F = 1 + 4 ÷
equipment cost ÷
maximum equipment cost. The maximum equipment
cost of the facilities identified in this eis is 14,882 (or $14,882,000).
Utilities cost (UC) UC = | 4 percent Equipment cost factor Operating manpower cost | [0.04] [1+4 ÷ 14,600 ÷ 14,882] ÷ [46,777] = 9,214 (or $9,214,000) |
Material requirements cost (MRC) MRC = | 60 percent Operating manpower cost | [0.60]÷ [46,777] = 28,066 (or $28,066,000) |
Maintenance cost (MC) MC = | 36 percent Operating manpower cost | [0.36] ÷ [46,777] = 16,839 (or $16,839,000) |
Secondary waste disposal cost (SWDC) SWDC = | Throughput Operating period Disposal cost Volume reduction ratio | [3,063] ÷ [19] ÷ [7.636] ÷ [7.43] = 59,810 (or $59,810,000) |
Total facility operating cost (TFOC) TFOC = | Operating manpower cost Waste type support manpower cost Utilities cost Material requirements cost Maintenance cost Secondary waste disposal cost | [46,777] + [55,358] + [9,214] + [28,066] + [16,839] + [59,810] = 216,064 (or $216,064,000) |
C.2.1.6 Post-Operation Costs
The cost of decontamination and decommissioning the facility following its useful life is estimated as 80 percent of the initial equipment and building costs.
Post-operation cost (POC) POC = | 80 percent Equipment and building cost | [0.80] ÷ [14,600 + 10,034] = 19,707 (or $19,707,000) |
C.2.1.7 Total Unescalated Costs
Total unescalated cost (TUC) | Pre-project costs Construction costs Contingency costs Facility operation costs Post-operations costs | [9,055] + [36,567] + [12,799] + [216,064] + [19,707] = 294,192 (or $294,192,000) |
C.2.2 COST DISTRIBUTION
Annual pre-project cost (APPC) APPC = | Pre-project cost Years prior to detailed design and construction start | [9,055] ÷ [2] = 4,527 (or $4,527,000) for each year, 2000 and 2001 |
Annual total estimated cost (ATEC) ATEC = | Total estimated cost Period from detailed design and construction start to operation start | [49,366] ÷ [4] = 12,341 (or $12,341,000) for each year, 2002 through 2005 |
Annual facility operation cost (AFOC) AFOC = | Facility operation cost Period of operation | [216,064] ÷ [19] = 11,371 (or $11,371,000) for each year, 2006 through 2024 |
Annual post-operation cost (APOC) APOC = | Post-operation cost Years following operations | [19,707] ÷ [3] = 6,569 (or $6,569,000) for each year, 2025 through 2027 |
Unescalated costs (based on the value of money in
1994), escalated costs, and discounted costs are listed by year
in Table C-7.
C.2.3 ESCALATION
The escalation rates were taken from the DOE guidelines
(DOE 1994b) for future-year estimating. The escalation rates
are typically 3 percent, with the exception of 2.9 percent and
3.1 percent for fiscal year 1995 and fiscal year 1998, respectively.
Escalation factors are calculated as the previous
year's escalation factor compounded by the appropriate escalation
rate. For example, the escalation rate in 2000 is 3 percent.
Therefore, the 2001 escalation factor is the 2000 factor (1.194)
times 1.03 or 1.230. The escalated costs are the product of the
unescalated cost and the corresponding escalation factor (Table
C-7).
Table C-7. Cost distribution for the non-alpha vitrification facility
factor | |||||
1.000 | 1.000 | ||||
1.029 | 0.943 | ||||
1.06 | 0.890 | ||||
1.092 | 0.840 | ||||
1.126 | 0.792 | ||||
1.159 | 0.747 | ||||
4,527 | 1.194 | 5,046 | 0.705 | 3,811 | |
4,527 | 1.230 | 5,568 | 0.665 | 3,703 | |
12,341 | 1.267 | 15,634 | 0.627 | 9,809 | |
12,341 | 1.305 | 16,103 | 0.592 | 9,531 | |
12,341 | 1.344 | 16,586 | 0.558 | 9,261 | |
12,341 | 1.384 | 17,083 | 0.527 | 8,999 | |
11,371 | 1.426 | 16,212 | 0.497 | 8,057 | |
11,371 | 1.469 | 16,699 | 0.469 | 7,829 | |
11,371 | 1.513 | 17,200 | 0.442 | 7,607 | |
11,371 | 1.558 | 17,716 | 0.417 | 7,392 | |
11,371 | 1.605 | 18,247 | 0.394 | 7,183 | |
11,371 | 1.653 | 18,795 | 0.371 | 6,980 | |
11,371 | 1.702 | 19,359 | 0.350 | 6,782 | |
11,371 | 1.754 | 19,939 | 0.331 | 6,590 | |
11,371 | 1.806 | 20,537 | 0.312 | 6,404 | |
11,371 | 1.86 | 21,154 | 0.294 | 6,222 | |
11,371 | 1.916 | 21,788 | 0.278 | 6,046 | |
11,371 | 1.974 | 22,442 | 0.262 | 5,875 | |
11,371 | 2.033 | 23,115 | 0.247 | 5,709 | |
11,371 | 2.094 | 23,809 | 0.233 | 5,547 | |
11,371 | 2.157 | 24,523 | 0.220 | 5,390 | |
11,371 | 2.221 | 25,259 | 0.207 | 5,238 | |
11,371 | 2.288 | 26,016 | 0.196 | 5,090 | |
11,371 | 2.357 | 26,797 | 0.185 | 4,946 | |
11,371 | 2.427 | 27,601 | 0.174 | 4,806 | |
6,569 | 2.500 | 16,423 | 0.164 | 2,698 | |
6,569 | 2.575 | 16,916 | 0.155 | 2,621 | |
6,569 | 2.652 | 17,423 | 0.146 | 2,547 | |
294,192 | 534,348 | 172,674 |
C.2.4 DISCOUNTING
Discounting is the determination of the present cost of future payments. The present cost is less than the future payment because the money could be invested with some rate of return and be worth more later. The rate of return is assumed to remain constant at 6 percent per year; this rate is judged to be consistent with current prime lending rates and long-term rates of return.
Discounting is calculated in a manner similar to
escalation; the previous factor is discounted by the appropriate
discount rate. For example, the discount factor for 2001 is the
2000 factor (0.705) divided by 1.06 or 0.665. Discounted costs
are the product of the escalated cost and the discount factor
(Table C7). Figure C-2 presents a graphic representation
of the discounted, unescalated, and escalated costs.
C.3 Cost of Facilities
Costs for proposed facilities are presented for each
alternative and waste forecast (Table C-8). The costs include
those for pre-project, design and construction (except for existing
facilities, which have already incurred design/construction costs),
operation and maintenance, secondary waste disposal and facility
decontamination and decommissioning.
They are expressed as present 1994 costs and are based on draft
site treatment plan escalation (approximately
3 percent) and a 6percent discount rate.
Table C-8. Cost of facilities in the SRS Waste Management eis ($ million).
Forecast | ||||
Waste soil sort (new) | Minimum | 52.6 | 54.0 | 53.6 |
Expected | 56.2 | 58.2 | 58.1 | |
Maximum
| 73.8 | 113.7 | 103.4 | |
Offsite low-level waste volume | Minimum | b | 57.1 | |
reduction | Expected | 58.4 | ||
Maximum
| 62.0 | |||
Offsite treatment and disposal | Minimum | 2,462.3 | 2,350.6 | 2,009.7 |
Expected | 4,637.3 | 4,419.3 | 2,418.6 | |
Maximum
| 7,404.7 | 7,109.6 | 2,798.6 | |
Non-alpha vitrificationvitrification (new) | Minimum | 194.7 | ||
Expected | 172.7 | 299.6 | ||
Maximum
| 565.6 | 660.6 | ||
Alpha vitrificationvitrification (new) | Minimum | 246.0 | 248.3 | |
Expected | 246.8 | 250.2 | ||
Maximum
| 359.3 | 416.4 | ||
Transuranic wasteTransuranic waste characterization/ | Minimum | 121.9 | 121.9 | 121.9 |
certification (new) | Expected | 120.7 | 120.7 | 120.7 |
Maximum
| 129.0 | 129.0 | 129.0 | |
Consolidated IncinerationIncineration | Minimum | 125.9 | 296.9 | 115.7 |
Facility | Expected | 206.9 | 353.6 | 143.1 |
Maximum
| 691.5 | 525.2 | 249.2 | |
Low-activity waste vaults | Minimum | 264.4 | 21.5 | 83.4 |
(periodic requirements) | Expected | 340.8 | 32.5 | 103.1 |
Maximum
| 848.2 | 105.1 | 197.8 | |
Intermediate-level vaults | Minimum | 144.0 | 117.6 | 33.6 |
(periodic requirement) | Expected | 192.2 | 192.3 | 77.4 |
Maximum
| 684.1 | 436.7 | 100.1 | |
Low-level waste non-vault disposal | Minimum | 62.9 | 58.9 | 62.3 |
(periodic requirement) | Expected | 78.3 | 62.3 | 86.7 |
Maximum
| 294.6 | 92.8 | 317.4 | |
Long-lived storage | Minimum | 33.0 | 33.0 | 33.1 |
(periodic requirement) | Expected | 33.8 | 33.8 | 33.8 |
Maximum
| 34.2 | 34.3 | 34.3 | |
Transuranic wasteTransuranic waste storage (periodic | Minimum | 39.4 | 16.5 | 25.1 |
requirement) | Expected | 105.4 | 106.0 | 107.2 |
Maximum | 5,900.0 | 5,898.2 | 5,816.7 |
Table C-8. (continued).
Forecast | |||||
Offsite smeltersmelter | Minimum | 214.2 | 214.1 | ||
Expected | 214.6 | 214.3 | |||
Maximum
| 216.4 | 215.1 | |||
Offsite lead decontamination | Minimum | 117.3 | 117.3 | 117.0 | |
Expected | 210.7 | 210.7 | 210.7 | ||
Maximum
| 472.2 | 472.2 | 472.2 | ||
Waste Isolation Pilot PlantWaste Isolation Pilot Plant | Minimum | 276.7 | 127.1 | 72.6 | |
Expected | 357.1 | 152.3 | 77.0 | ||
Maximum
| 4,287.5 | 1,896.7 | 496.1 | ||
RCRA-permitted disposal vaults | Minimum | 81.4 | 98.0 | 264.0 | |
Expected | 92.6 | 121.0 | 1,128.6 | ||
Maximum
| 1,405.9 | 562.5 | 4,448.1 | ||
CompactorsCompactors | Minimum | 117.1 | 24.0 | 31.3 | |
Expected | 117.1 | 24.0 | 33.4 | ||
Maximum
| 50.9 | 22.5 | 32.4 | ||
M-Area air stripper | Minimum | 0.003 | 0.003 | 0.003 | |
Expected | 0.016 | 0.016 | 0.016 | ||
Maximum
| 0.017 | 0.017 | 0.017 | ||
Containment building (new)Containment building | Minimum | 145.0 | 134.4 | 49.1 | |
Expected | 177.2 | 159.1 | 49.2 | ||
Maximum
| 336.4 | 254.1 | 49.3 | ||
Mixed waste storage
(periodic requirement) | Minimum Expected Maximum | 125.0 208.8 1,826.6 | 112.8 208.8 1,583.9 | 111.7 208.9 1,574.1 | |
Total | Minimum | 4,168.9 | 4,201.7 | 3,841.0 | |
Expected | 6,935.3 | 6,947.2 | 5,620.7 | ||
Maximum | 24,439.6 | 20,439.9 | 18,110.9 |
a. Source: Hess (1995).
b. Shaded areas indicate the alternatives that do not use the facility.
C.4 References
DOE (U.S. Department of Energy), 1994a, SRS Draft
Site Treatment Plan, Savannah River Operations
Office, Savannah River Site, Aiken, South Carolina.
DOE (U.S. Department of Energy), 1994b, Draft
Site Treatment Plan Cost Guidance, (Revision 1), Office of
Field Management, Washington, D.C.
DOE (U.S. Department of Energy), 1995, Baseline
Environmental Management Report, Office of Environmental Management,
Washington, D.C., March.
Feizollahi, F., and D. Shropshire, 1992, Waste
Management Facilities Cost Information Report, EGGWTD-10443,
EG&G, Idaho Falls, Idaho.
Hess, M. L., 1994a, Westinghouse Savannah River Company, Aiken, South Carolina, Interoffice Memorandum to H. L. Pope, U.S. Department of Energy Savannah River Operations Office, Aiken, South Carolina, "Synopsis of Estimating Models," ESH-NEP-94-0194, October 14.
Hess, M. L., 1994b, Westinghouse Savannah River Company,
Aiken, South Carolina, Interoffice Memorandum to H. L. Pope, U.S.
Department of Energy Savannah River Operations Office, Aiken,
South Carolina, "Draft In-Depth Option Analysis for Review
and Comments," ESHNEP940099, July 29.
Hess, M. L., 1995, Westinghouse Savannah River Company,
Aiken, South Carolina, Interoffice Memorandum to H. L. Pope, U.S.
Department of Energy Savannah River Operations Office, Aiken,
South Carolina, "WSRC Data Transmittal-Complete Copy of Cost
Model for WMeis," ESH-NEP-95-0078, May 5.
Taylor, B. K., W. R. McDonnel, and D. P. Harley,
1993, FY 1993 SRS Waste Cost Analysis, WSRCRP93-942,
Westinghouse Savannah River Company, Aiken, South Carolina, July
31.
NEWSLETTER
|
Join the GlobalSecurity.org mailing list |
|
|