UNITED24 - Make a charitable donation in support of Ukraine!

Weapons of Mass Destruction (WMD)

Previous PageTable Of ContentsList Of FiguresList Of TablesNext Page

APPENDIX F ACCIDENTS CONSIDERED DURING INTERIM ACTIVITIES

TABLE OF CONTENTS

ACCIDENTS CONSIDERED DURING INTERIM ACTIVITIES                                F-1
F.1    RETRIEVAL AND STORAGE                                                  F-4
                 F.1.1 MITIGATION MIXER PUMPS                                 F-5
                 F.1.2 INITIAL TANK RETRIEVAL SYSTEM                          F-5
                             F.1.2.1 Unfiltered Riser Release                 F-6
                             F.1.2.2 Waste Spill From Contaminated Pump       F-8
                             F.1.2.3 Transfer Pipe Break                      F-8
                             F.1.2.4 Pressurized Spray Release                F-10
                             F.1.2.5 Toxic Gas Release                        F-11
                 F.1.3 NEW TANK FACILITIES                                    F-12
                             F.1.3.1 Pressurized Spray Releases               F-13
                             F.1.3.2 Transfer Pipe Leaks                      F-15
                             F.1.3.3 Leaks From Failures of the Waste Tank    F-16
                             F.1.3.4 Leaks From Waste Misrouting              F-18
                             F.1.3.5 Pressurization of a Contaminated Process Pit F-18
                             F.1.3.6 Nuclear Criticality                      F-19
                             F.1.3.7 Flammable Gas Burn                       F-19
                             F.1.3.8 Tank Bumps                               F-20
                             F.1.3.9 Overheating of a Waste Tank              F-20
                             F.1.3.10 Gaseous Release of Toxic Material       F-21
                             F.1.3.11 Release of Materials From a Pressurized Tank  
                            Dome                                              F-21
                             F.1.3.12 Chemical Reactions Due to Waste Misrouting F-22
                             F.1.3.13 Aircraft Crash                          F-23
                 F.1.4 PAST PRACTICES SLUICING SYSTEM                         F-23
                             F.1.4.1 Transfer Pipe Breaks                     F-24
                             F.1.4.2 Pressurized Spray Leaks                  F-25
        F.2 INTERIM STABILIZATION OF SINGLE SHELL TANKS                       F-26
                 F.2.1 SALT WELL TRANSFER PIPING LEAKS                        F-27
                 F.2.2 SALT WELL SYSTEM SPRAY LEAKS                           F-30
                             F.2.2.1 Spray Leak During SST to DCRT Transfer   F-30
                             F.2.2.2 Spray Leak During DCRT To DST Transfer   F-31
        F.3 UNDERGROUND CROSS-SITE TRANSFER                                   F-32
                 F.3.1 EXISTING CROSS-SITE TRANSFER SYSTEM                    F-33
                             F.3.1.1 Waste Transfer Line Leak                 F-35
                             F.3.1.2 Overflow of The 241-EW-151 Vent Station
                            Catch Tank                                        F-36
                             F.3.1.3 Rupture of the Encasement and Pipeline   F-36
                             F.3.1.4 Spray Release From a Diversion Box With
                            Cover Blocks Installed                            F-37
                             F.3.1.5 Spray Release From a Diversion Box With
                            Cover Blocks Not Installed                        F-38
                 F.3.2 REPLACEMENT CROSS-SITE TRANSFER SYSTEM                 F-38
                             F.3.2.1 Transfer Line Breaks                     F-40
                             F.3.2.2 Spray Releases                           F-42
        F.4 ABOVE-GROUND CROSS-SITE TRANSFER                                  F-45
                 F.4.1 TANKER TRAILER TRUCKS                                  F-45
                             F.4.1.1 In-Transit Punctures                     F-46
                             F.4.1.2 Fire Induced Breaching                   F-47
                             F.4.1.3 Collisions and Rollovers                 F-47
                             F.4.1.4 Criticality                              F-49
                 F.4.2 RAIL TANK CARS                                         F-51
                             F.4.2.1 In-Transit Punctures                     F-52
                             F.4.2.2 Fire-Induced Breaches                    F-52
                             F.4.2.3 Collisions and Derailments               F-52
                             F.4.2.4 Criticality                              F-53
                 F.4.3  LOAD AND UNLOAD FACILITIES                            F-54
                             F.4.3.1 Spills                                   F-56
                             F.4.3.2 Spray Releases                           F-57
                             F.4.3.3 Fires                                    F-58
        APPENDIX F REFERENCES                                                 F-59
                                LIST OF TABLES
        F-1 Accident Frequency Categories                                     F-1
        F-2 Summary of ITRS Accident Releases                                 F-7
        F-3 Summary of NTF Accident Releases                                  F-14
        F-4 Summary of PPSS Accident Releases                                 F-25
        F-5 Estimated Frequencies and Maximum Volumes for Salt Well Transfer
       Line Leaks                                                             F-28
        F-6 Summary of Accident Releases During Pumping and Transfer of SWL   F-29
        F-7 Summary of ECSTS Accident Releases                                F-34
        F-8 Summary of RCSTS Accident Releases                                F-40
        F-9 Accident Frequencies for Trucks at the Hanford Site               F-48
        F-10 Fractional Release Frequencies for Rail Accidents                F-49
        F-11 Summary of Maximum Accident Releases from Transport Vehicles
       During Cross-Site Transfers                                            F-50
        F-12 Summary of Accident Releases for the HLW Load and Unload
       Facilities                                                             F-56

APPENDIX F ACCIDENTS CONSIDERED DURING INTERIM ACTIVITIES

This appendix discusses potential accidents which could occur during
implementation of the proposed alternatives.  The discussion includes
estimates of the frequency of occurrence of the accident scenarios and the
quantity of hazardous materials released during each accident.  Design
features and institutional and organizational controls which can prevent or
mitigate potential accidents are also discussed.  This appendix is organized
by the systems which would be utilized by one or more alternatives identified
in Section 3.
Accidents can be initiated by operational events, natural phenomena, and
external events and may be categorized according to their frequency of
occurrence, as shown in Table F-1.
Table F-1
Accident Frequency Categories
 
                                Annual Frequency     
Accident Description            (yr-1)              Category 
Anticipated - May occur more    1                    
than once during the lifetime                        
of the facility                                      
                                                     
                                                    Reasonably 
                                                    Foreseeable 
                                10-1                 
                                10-2                 
Unlikely - May occur at some    10-3                 
time during the lifetime of 
the facility
                                10-4                 
Extremely Unlikely - Probably   10-5                 
will not occur during the 
lifetime of the facility
                                10-6                 
Incredible - Not credible       10-7                 
during the lifetime of the 
facility
                                < 10-7              Not Reasonably 
                                                    Foreseeable
It is important to distinguish between the frequency of the event that
initiates the sequence of events and the frequency of the accidental release
of hazardous materials expected to result from the sequence of events. 
Equipment or component failures or human errors are common initiators of
accidents and often have frequencies in the anticipated and unlikely ranges. 
Natural phenomena can also initiate accident sequences.  The frequencies of
occurrence of natural events such as earthquakes exceeding Uniform Building
Code levels, 100-year floods, and maximum wind gusts are usually within the
unlikely range.  Natural phenomena such as severe earthquakes, tornados, and
lightning strikes are usually in the extremely unlikely range.  The frequency
of the accidental release of hazardous materials is the product of the
frequency of each event in the sequence leading to the event. 
DOE orders establish a design process for nuclear facilities that ensures that
there is an inverse relationship between the frequency of occurrence of an
accident and its consequences.  DOE Order 5480.23, Nuclear Safety Analysis
Reports, defines hazard categories and Section 1300-3 of DOE Order 6430.1A,
General Design Criteria, establishes a safety classification system for
structures, systems, and components.  Risk acceptance guidelines used in the
design process at Hanford are defined in WHC-CM-4-46, Nonreactor Facility
Safety Analysis Manual (WHC 1988).  The purpose of the risk acceptance
guidelines is to determine whether additional mitigative features need to be
incorporated into the design of a structure, system, or component and not to
define any particular level of risk as acceptable.
The principal actions to be accomplished during the interim period, 1995
through 2000, assessed by this EIS are:
.      Continued removal of SWL from SSTs
.      Provision of a capability for cross-site transfer of waste from the 200
       West Area to the 200 East Area via a system that complies with
       applicable rules and regulations
.      Provision of adequate tank waste storage capacity for wastes associated
       with tank farm operations and other Hanford facility operations during
       the interim period
.      Mitigation of flammable gas buildup in Watchlist Tank 101-SY.
Actions considered to continue mitigation of flammable gas buildup in Tank
101-SY are active mitigation using mixer pumps and passive mitigation by
retrieval and dilution of tank contents.  Accidents associated with the mixer
pumps and with facilities to retrieve, dilute, and store the contents of Tank
101-SY are discussed in Section F.1.
SST interim stabilization is accomplished by removing drainable liquids from
SST salt wells using submersible pumps or jet pumps.  The liquids removed are
collected in DCRTs and transferred to designated DSTs.  The shielding piping
used during these operations is old and some is above ground.  Accidents
associated with salt well pumping are discussed in Section F.2.
Eventually, the liquids removed from the SST salt wells and Tank 101-SY could
be processed through Evaporator 242-A in the 200 East Area to reduce the waste
volume.  The SY Tank Farm and several million gallons of SWL are in the 200
West Area.  Both below-ground and above-ground alternatives are considered for
the cross-site transfer of these wastes.  Accidents associated with
underground transfers are discussed in Section F.3 and those associated with
above-ground transfers are discussed in Section F.4.
The primary pathway for exposure of workers and the general public as the
result of accidents associated with the actions considered here is inhalation
of tank waste released as aerosols and vapors during potential accidents.  To
support the evaluation of health effects using the methods discussed in
Appendix E, discussion of each accident includes an estimate of the
"respirable volume" at the point of release.  Hanford safety assessment
documents generally assume that material released as vapors and as droplets
with diameters of 50 -m (0.002 in) or less are respirable.  Droplets with
diameters of greater than 50 -m (0.002 in) are assumed to condense and settle
and those smaller than 50 -m (0.002 in) are assumed to remain airborne and
evaporate to a respirable size.  Calculation of airborne concentrations of
hazardous materials at downwind locations occupied by workers and members of
the general public is discussed in Appendix E.

F.1 RETRIEVAL AND STORAGE

Prior to the initiation of full-scale retrieval of tank wastes under the TWRS
program, it may be necessary to retrieve and store wastes now stored in Tanks
101-SY and 102-SY.
Tank 101-SY is currently designated as a hydrogen Watchlist tank as the result
of GREs that have occurred in the past.  In the absence of mitigative
measures, concentrations of flammable gases such as hydrogen and NOx increase
in the tank vapor space during GREs.  If concentrations approach the LFL for
the gas mixture, combustion could occur and lead to the release of hazardous
materials.  Flammable gas buildup is considered to be mitigated by actions
which limit the concentration of flammable gases in the tank vapor space to no
more the 25 percent of the LFL.  The LFL is defined as 3 percent hydrogen by
volume in a NOx atmosphere (PNL 1994a). 
Section F.1.1 discusses an active approach to mitigating the buildup of
flammable gases.  The active approach relies on a mixer pump to keep the waste
mixed so that stratification cannot occur.  Although flammable gases are still
generated in the waste, they are released gradually thereby preventing the
short-duration increases in gas concentrations in the tank vapor space
associated with GREs.  A passive approach to mitigation is to dilute the waste
to dissolve the components of the sludge layer that trap gases.  This can be
accomplished by retrieving, diluting, and storing the waste.  Accidents
associated with the tank retrieval using the ITRS are discussed in Sections
F.1.2 and those associated with storage are discussed in Section F.1.3. 
Accidents associated with PPSS, an ITRS alternative, are discussed in Section
F.1.4.  If storage tanks for the diluted waste are located in the 200 East
Area, cross-site transfer will be necessary.  Accidents associated with such
transfer are discussed separately in Section F.3.1.
The waste currently stored in Tank 102-SY presents a different problem.  This
tank is the only non-Watchlist tank in the SY Tank Farm and is used for
storage of SWL and facility wastes generated in the 200 West Area. It is also
used as the staging tank for cross-site transfers.  Tank 102-SY currently
contains 269,000 L (71,000 gal) of sludge that is classified as TRU waste.
Some of the SWL contains complexing agents that could dissolve this sludge if
added to Tank 102-SY.  Dissolution of the sludge could result in an increase
in the volume of TRU waste.  This could be avoided by retrieving the sludge
prior to the introduction of complexed SWL.  Retrieval options considered are
the ITRS and PPSS.  Accidents associated with retrieval using the ITRS are
discussed in Section F.1.2 and those associated with retrieval using the PPSS
are discussed in Section F.1.4.

F.1.1 MITIGATION MIXER PUMPS

Accidents involving operation of the mitigation mixer pump installed in Tank
101-SY were evaluated in Environmental Assessment for Proposed Mixing
Operations to Mitigate Episodic Gas Releases in Tank 241-SY-101, (DOE 1992a)
and found not to result in any significant impact.  The evaluation included
removal of the existing slurry distributor, and installation, operation, and
removal of the mitigation jet mixer pump.  The pump was assumed to be operated
for four hours per day, seven days per week.
A spare 150-hp mixer pump from the Hanford Grout Program was modified and
installed in Tank 101-SY on July 3, 1993.  The ability of this pump to
mitigate flammable gas buildup has been demonstrated on Tank 101-SY during
approximately 1 year of testing (PNL 1994b, KEHC 1993).  Based on these tests,
it was concluded (PNL 1994a) that the jet mixer pump is capable of maintaining
mitigation indefinitely and a long-term pump operations plan was developed for
Tank 101-SY.  The plan calls for operation of the pump from 5 minutes to 180
minutes per day 3 days per week.  Since this is well within the operating
conditions evaluated in the EA, no additional accident analysis has been
performed.

F.1.2 INITIAL TANK RETRIEVAL SYSTEM

The ITRS is designed to retrieve both solids and liquids from selected DSTs. 
The selected DSTs include hydrogen Watchlist tanks, proposed process feed
tanks, and tanks selected for retrieval to provide additional liquid waste
storage space.  The selected tanks include Tank 101-SY but not Tank 102-SY. 
The Safety Assessment, Initial Tank Retrieval Systems. Project W-211 (WHC
1995a) considers a range of accidents that could occur during ITRS retrieval
of these tanks.  The hazards identified in this SA are considered to be
generally applicable to retrieval of DSTs, including Tank 102-SY.
The SA included quantitative estimates of the following five accident
scenarios involving both radioactive materials and toxic chemicals:
.      Unfiltered riser release
.      Waste spill from contaminated pump
.      Transfer pipe break
.      Pressurized spray release
.      Toxic gas release.
The SA also evaluated a release of toxic gases from the tank ventilation
system during tank drawdown.
Accident frequencies and quantities of respirable radioactive materials
released and release rates of "flash" gases derived from the safety assessment
(WHC 1995a) are summarized in Table F-2 and discussed in the following
sections.
F.1.2.1 Unfiltered Riser Release
 - This accident scenario is identical to
that described in A Safety Assessment for Proposed Pump Mixing Operations to
Mitigate Episodic Gas Release in Tank 241-SY-101, Rev. 8 (LANL 1994).  It is
assumed that the primary tank ventilation system fails while a riser is open
for installation of a pump.  In this scenario, natural convection flow
patterns are established due to the heating of the dome gas from the hotter
waste surface.  Based on the prior safety assessment, 327 g (0.72 lb) of
suspended waste is convected to the environment in 1 hour at ground level (DOE
1992b).  Based on a density of 1.4 g/ml (11.7 lb/gal) (WHC 1993a), this is
equivalent to a release of 0.023 L (0.006 gal) of respirable material.  The
release is categorized as extremely unlikely (WHC 1995a). 
There are several mitigating factors that would be expected to reduce the
duration and consequences of an unfiltered release from a riser.  These
factors include use of temporary enclosures, use of protective equipment by
workers, monitoring of direct radiation and airborne radioactivity by HP 
Technicians, and use of work procedures specific to the task.
Table F-2
Summary of ITRS Accident Releases
 
Accident                            Frequency           Exposure Duration   Respirable Volume 
Scenario                            (yr-1)              (hr)                (L) 
Unfiltered Riser                    Extremely           On-site   1         0.023 
Release                             Unlikely 
                                                        Off-site  1         0.023 
Spill from                                              On-site   1         0.00262 
Contaminated Pump                   Unlikely                      7         0.00165 
                                                                            0.00427 
                                                        Off-site  1         0.00262 
                                                                  2         0.00542 
                                                                  3         0.00804 
Unmitigated Pipe                                        On-site   1         1.0203 
Break (Seismic)                     Incredible                    7         0.6428 
                                                                            1.66 
                                                        Off-site  1         1.0203 
                                                                  7         0.6428 
                                                                            1.66 
Mitigated Pipe Break                                    On-site   1         0.2559 
(Seismic)                           Unlikely                      7         0.1612 
                                                                            0.417 
                                                        Off-site  1         0.2559 
                                                                  7         0.1612 
                                                                            0.417 
Unmitigated Pipe                                        On-site   1         0.384 
Break (Excavation)                  Incredible                    7         0.242 
                                                                            0.625 
                                                        Off-site  1         0.384 
                                                                  7         0.242 
                                                                            0.625 
Mitigated Pipe Break                                    On-site   1         0.0122 
(Excavation)                        Unlikely                      7         0.0077 
                                                                            0.0198 
                                                        Off-site  1         0.0122 
                                                                  7         0.0077 
                                                                            0.0198 
Unmitigated Spray                   Extremely           On-site   8         4,550 
Release                             Unlikely to 
                                    Incredible 
                                                        Off-site  8         4,550 
Mitigated Spray                     Anticipated to      On-site   8         0.00033 
Release                             Unlikely 
                                                        Off-site  8         0.00033 
Toxic Gas Release                   Anticipated         Not Applicable      0.236 m3/s or  
84.7 mg/s
F.1.2.2 Waste Spill From Contaminated Pump
 - This accident scenario is
similar to that described in A Safety Assessment for Proposed Pump Mixing
Operations to Mitigate Episodic Gas Release in Tank 241-SY-101, Rev. 8 (LANL
1994).  The accident scenario assumes that the pump installation is
unsuccessful and that the pump is removed from the tank after it becomes
contaminated with waste material.  Following removal of the pump, waste
trapped in the pump inlet is spilled on the ground surface.  The accident
scenario does not take credit for the fact that the pump assembly will be
drained and bagged in plastic as it is removed from the riser.  An SA for a
similar event estimated that 654 L (173 gal), assuming a density of 1.4 g/ml
(11.6 lbs/gal) of waste would be spilled and that 0.18 kg (0.4 lbs) would be
expected to become airborne (LANL 1994). 
For consistency with treatment of spills in more recent SAs, the quantity of
airborne respirable material is calculated using ARRs from Mishima (DOE 1993)
and exposure times adjusted.  The spill of 654 L (173 gal) of waste is assumed
to form a pool on the surface for one hour and then soak into the ground
causing the soil to remain saturated with waste for 23 hours.  While waste is
pooled on the surface, respirable material is released at a rate of 4.0 x 10-6
of the pool volume per hour (DOE 1993).  Respirable material is released from
the saturated ground at a rate of 3.6 x 10-7 of the liquid volume per hour
(DOE 1993).  Workers are assumed to be exposed for 8 hours and the general
public for 24 hours.  The resultant volumes of respirable material are shown
in Table F-2.
Mitigating factors that would reduce the consequences of a spill from a
contaminated pump include high pressure flush rings for rinsing and bagging
the pump as it is removed from the riser, use of protective equipment such as
respirators, and quickly covering the spill area to prevent subsequent
airborne release.
F.1.2.3 Transfer Pipe Break
 - Transfer pipe breaks could be caused by
excavation accidents or BDBE.  The ITRS safety assessment developed different
accident scenarios for each initiating event (WHC 1995a).  Each of these two
accidents are described in the following paragraphs. 
.      Excavation Accident - This accident scenario assumes that excavation
       equipment causes a breach of the primary transfer pipe and its
       secondary containment in the interval between leak testing and
       initiation of pumping.  Pumping then begins at the rate of 530 L/min
       (140 gpm) and causes a pool of waste to form on the ground surface. 
       Pumping would continue until the leak is detected.  Once pumping is
       stopped, waste in the ruptured line is assumed drain back into the pool
       390 L (103 gal).  The ITRS safety assessment assumed that pumping would
       be terminated after 3 hours and that 390 L (103 gal) would drain back.
       The unmitigated case assumes (WHC 1995a) that the leak is detected by
       the first material balance performed after pumping begins.  Considering
       the time to fill the transfer line, this corresponds to a 4-hour leak. 
       The mitigated case assumes that the leak detection system shuts down
       the pump within 5 minutes.  Both cases assume a 0.5:1 dilution
       (diluent:waste) of the waste spilled and that the spilled waste is
       available for resuspension for 8 hours.  For consistency with pipe
       break scenarios for similar systems, this EIS assumes an 8-hour leak
       for the unmitigated case and a 2-hour leak for the mitigated case. 
       Since dilution is performed in-line, the transfer line would initially
       contain undiluted waste.  With these assumptions, the unmitigated leak
       volume would be 255,000 L (67,300 gal) and the mitigated leak volume
       would be 64,000 L (16,900 gal).
       The quantity of respirable material released in 8 hours is estimated by
       assuming (WHC 1995a) that the pool remains on the surface for 1 hour
       and then saturates the ground for the remaining 7 hours.  An airborne
       release rate of 4.0 x 10-6/hr is assumed for the pool and of 3.6 x
       10-7/hr for the saturated soil.  The quantities of respirable material
       released during each phase are shown in Table F-2.
       The ITRS SA (WHC 1995a) classifies both the unmitigated and mitigated
       excavation accidents as incredible based on the analysis used to
       estimate the frequency of RCSTS excavation accidents (WHC 1995b) but
       assumes somewhat different event trees.  For this EIS, the unmitigated
       accident is assumed to be incredible and the mitigated accident to be
       unlikely.
.      Seismic Accident - The seismic transfer pipe break accident is
       initiated by a beyond design basis accident and causes rupture of the
       primary transfer pipe and its encasement.  The ITRS SA (WHC 1995a)
       assumes that the unmitigated leak continues for 8 hours at 530 L/s (140
       gal/s).  This is considered to be an incredible event.  The quantity of
       respirable material released is estimated by assuming that the pool
       remains on the surface for 1 hour and then saturates the ground for the
       remaining 7 hours.  An airborne release rate of 4.0 x 10-6/hr is
       assumed for the pool and of 3.6 x 10-7/hr for the saturated soil.  The
       quantities of respirable material released during each phase, assuming
       undiluted waste is spilled, are shown in Table F-2.
       The ITRS SA treats the mitigated case as an impossible event on the
       basis that the system is designed to withstand a design basis
       earthquake.  For this EIS, the mitigated case is treated as a 2-hour
       leak that remains available for resuspension for 8 hours and is
       considered an unlikely event.  The quantity of respirable material
       released is estimated by assuming that the pool remains on the surface
       for 1 hour and then saturates the ground for the remaining 7 hours.  An
       airborne release rate of 4.0 x 10-6/hr is assumed for the pool and of
       3.6 x 10-7/hr for the saturated soil.  The quantities of respirable
       material released during each phase, assuming undiluted waste is
       spilled, are shown in Table F-2. 
F.1.2.4 Pressurized Spray Release
 - Spray releases may be defined as a
pressurized release of a liquid from a hole/opening such that droplets and
mists are formed.  Some of the droplets and mists remain airborne and are
released to the environment.  Unmitigated and mitigated accident scenarios
have been evaluated for pressurized spray releases.
.      Unmitigated Spray Release - This accident scenario involves a spray
       release in a pump pit, which is advertently left uncovered during the
       transfer operations (WHC 1995a).  Equipment in a pump pit includes
       piping, motor-operated three-way valves, and pumps.  Valves are welded
       and are provided with double stem packing.  Even though the system will
       have been hydrostatically tested, it is postulated that a leak develops
       through the stem packing.  The length of the opening is assumed to be
       5 cm (2 in), the typical circumference of a 8 cm (3 in) valve stem and
       the width is assumed to be 0.1 mm (0.004 in) (WHC 1995a).  These
       dimensions maximize the fraction of respirable material in the spray. 
       The pressure of the transfer system is assumed to be 28 kg/cm2 (400
       psig).  The resulting total flow of 0.190 L/s (0.05 gal/s) through the
       opening.  Based on a respirable fraction of 0.8, respirable material
       would be released at the rate of 0.158 L/s (0.04 gal/s).  The spray
       release continues for 8 hours releasing in the release of 4,500 L
       (1,200 gal) of respirable waste.
       The frequency of this unmitigated spray release is considered to be
       extremely unlikely to incredible.  The most significant factor
       controlling the consequences of this accident is that it assumes that
       the pit cover blocks are not in place.  The frequency of the
       unmitigated seismic pipe break is assumed to incredible.  The frequency
       of the mitigated case is assumed to be extremely unlikely.
.      Mitigated Spray Release - This accident scenario is similar to the
       unmitigated spray scenario, with the exception that the pump pit covers
       are assumed to be in place during system operation.  The leak paths for
       dispersing aerosols from the pump pit into the environment would be
       through openings around the cover blocks.  The volume of waste released
       is calculated using the assumptions that the pump pit drain is plugged
       and that the leak detection system fails to detect accumulating liquid. 
       It is further assumed that escaping spray will saturate the pit volume.
       Saturated air will hold 100 mg/m3 [1.0 x 10-4 ounces (oz)/ft3] of
       respirable liquid aerosol particles.  This saturated air is assumed to
       be forced from the pit at the volumetric flow rate of the leak, 1.58 x
       10-4 m3/s (5.58 x 10-3 ft3/s) (WHC 1995a).  The leak is assumed to
       continue for 8 hours resulting in the release of 3.3 x 10-4 L (9.7 x
       10-5 gal) of respirable waste.
F.1.2.5 Toxic Gas Release
 - The ITRS safety assessment (WHC 1995a) evaluated
a release of toxic gases from the tank ventilation system as the level of
waste in the tank was reduced during a waste transfer. Gases are released as
the hydrostatic pressure on the liquid decreases.  The release of ammonia
(NH3) and N20 were modeled using a process simulator.  A drop of 92.9 cm/d
(36.6 in/d) was assumed in the waste level.  The simulation included release
of gases already in the waste and additional gases generated by radiolysis
during the drawdown period.  The initial NH3 concentration was 11.3 g/L (1.5
oz/gal) and the initial average hydrostatic pressure was 1.80 atmosphere.  The
initial concentration of N20 was not specified.  Ventilation rates of 14 and
28 m3/min (500 and 1,000 ft3/min) were considered.  Concentrations of the
gases were found to be greatest at the lower ventilation rate.  The peak
concentrations were 103 mg/m3 (1.0 x 10-4 oz/ft3) for NH3 and 256 mg/m3 (2.6 x
10-4 oz/ft3) for N20.  The total gas release rate was 0.236 m3/s (8.3 ft3/s) or
84.7 mg/s (2.99 x 10-3 oz/s).

F.1.3 NEW TANK FACILITIES

New HLW tank facilities would be required to support mitigation of flammable
gas potential by dilution.  These facilities would be designed and constructed
to current DOE high safety standards.  These standards apply to the high-
integrity DSTs, and require monitoring and control systems, ventilation
system, double containment, and rigorous OSRs.
Two new tanks and support facilities would be constructed in either the 200
West Area or at one of two potential sites in the 200 East Area.  To allow
maximum flexibility in the use of the new tanks, they would be connected to
the RCSTS.  The RCSTS is described in Section F.3.2
The operation of these new tanks would be similar to past and continuing tank
farm operations on the Hanford Site.  No new or unique accident scenarios
would be anticipated.  With new construction using current technology and
lessons learned from past operations, it is anticipated that the probability
of abnormal events and accidents would be lower than for similar existing
facilities.  It is also anticipated that the consequences, because of better
instrumentation and control, would be less severe.  
The section discusses accidents that could occur if the NTF were constructed. 
The information presented is based primarily on Multi-Function Waste Tank
Facility - Preliminary Safety Analysis Report, Rev. A, Vol. II, (WHC 1994a)
and additional analysis related to the multi-function waste tank facility (WHC
1994b).  These documents evaluated the frequency of occurrence and
consequences of a large number of accident categories.  These categories
include:
.      Pressurized Spray Releases
.      Transfer Pipe Leaks
.      Leaks from Failures of the Waste Tank
.      Leaks from Waste Misrouting
.      Pressurization of a Contaminated Process Pit
.      Nuclear Criticality
.      Flammable Gas Burn
.      Tank Bump
.      Overheating of a Waste Tank
.      Gaseous Release of Toxic Material
.      Release of Materials from a Pressurized Tank Dome
.      Chemical Reactions due to Misrouting
.      Aircraft Crash.
These accidents are discussed in the following sections.  The frequencies,
durations, and source terms (respirable volume released) of selected accidents
are summarized in Table F-3.  These accidents have been selected to show the
full range of frequencies and consequences for the NTF.
F.1.3.1 Pressurized Spray Releases
 - Spray releases may be defined as a
pressurized release of a liquid from a hole/opening such that droplets and
mists are formed.  Some of the droplets and mists remain airborne and are
released to the environment.  
The NTF would use pumps to move radioactive liquid waste to and from the waste
tanks in a system of underground transfer pipes and pump and valve pits. 
Although constructed, tested, and controlled to high standards some leaks
would be anticipated.
Spray release accidents could be initiated by events such as valve failures
and cracking of pipes.  These initiating events are in the anticipated to
unlikely range.  Seismic events could also initiate spray releases.  The
resulting spray release can have severe consequences but can be easily
mitigated by requiring the pit cover blocks to be in place.  For this reason, 
Table F-3
Summary of NTF Accident Releases
 
                                                             Exposure            Respirable 
Accident                            Single Event Frequency   Duration            Volume 
Scenario                            (yr-1)                   (hr)                (L) 
Pressurized Spray                   5 x 10-4 to 1 x 10-5     On-site  31.4       0.00304 
Release                             Unlikely to Extremely 
(Mitigated)                         Unlikely 
                                                             Off-site 94         0.0091 
Pressurized Spray                   2 x 10-7 to 8 x 10-8     On-site  8          625 
Release                             Incredible to Not 
(Unmitigated)                       Reasonably Foreseeable 
                                                             Off-site 8          625 
Tank Leak (BDBE)                    7 x 10-6 to 8 x 10-8     On-site  1          1.76 
                                    Extremely Unlikely to              7         1.11 
                                    Not Reasonably                               2.87 
                                    Foreseeable  
                                                             Off-site 1          1.76 
                                                                       23        3.63 
                                                                                 5.39 
Misrouting Leak                     2 x 10-4 to 4 x 10-6     On-site  1          1.45 
                                    Unlikely to Extremely              7         0.915 
                                    Unlikely                                     2.36 
                                                             Off-site 1          1.45 
                                                                       23        3.01 
                                                                                 4.46 
Pressurization of                   3 x 10-3 to 1 x 10-4     On-site  2          4.5 x 10-4 
Contaminated Pit                    Unlikely 
(Unmitigated)
                                                             Off-site 2          4.5 x 10-4 
Tank Overheating                    5 x 10-5 to 5 x 10-7     On-site  8          0.80 
(Unmitigated)                       Extremely Unlikely to 
                                    Incredible 
                                                             Off-site 24         2.39
pit cover blocks are designed to Safety Class 1S and are required to be in
place (WHC 1994a).  The confinement provided by the pit structure also
prevents the direct release of leakage to the soil column.
A large range of pressurized spray leaks has been evaluated by Muhlestein
using a quantified event tree approach (WHC 1994b).  Spray leaks initiated by
human error or equipment failure were found to be more likely than those
initiated by seismic events (WHC 1994b).  Regardless of the initiating event,
spray leaks were found to be in the unlikely to extremely unlikely category
and result in small releases when cover blocks are in place.  This section
considers a spray leak in a process pit with cover blocks in place when most
other safety systems have failed.  Section F.1.3.2 considers a similar spray
leak in transfer piping in a pit when the cover blocks are not in place.
The accident frequency and release quantity correspond to a spray leak in a
NTF valve pit during a waste transfer.  The cover blocks are in place but the
ventilation system is inoperative, the pit drain is blocked, and the pit leak
detection is inoperative.  This sequence of events has an estimated frequency
of 5 x 10-4 to 1 x 10-5/yr (WHC 1994b).  Under these conditions, the air inside
the pit is assumed to become saturated with vapor from the spray and to be
forced out through small spaces around the cover blocks.  The release is
terminated when liquid begins to overflow to the ground surface around the
pit.  This is estimated (WHC 1994a) to require 94 hours and to result in the
release of a total of 0.0091 L (0.0024 gal) of respirable liquid.  If the
release begins at the start of a worker's shift, the worker could be exposed
for 31.4 of the 94-hour release.  It is conservatively assumed that the off-
site individual is exposed for the entire 94 hours.
F.1.3.2 Transfer Pipe Leaks
 - The waste to be stored in the NTF would be
transferred into, out of, and among the tanks via encased underground transfer
pipes.  If the NTF is constructed in the 200 West Area, encased transfer
piping would connect the NTF transfer pit to RCSTS Diversion Box 1.  If the
NTF is constructed at either of the two sites in the 200 East Area, encased
transfer piping would connect the NTF transfer pit to an RCSTS Diversion Box 2
that would be added for this purpose.  It is anticipated that the distance
between transfer pit and diversion box would be greater for an NTF in the 200
East Area.
As discussed in Section F.1.3.1, transfer pipe leaks can be considered as a
type of pressurized spray leak.  Some of these events result in no release,
some in release to the soil column, some in release of aerosols, and some in
both soil column and aerosol releases.  To bound the entire category, this
section considers an unmitigated spray release from a leak detection riser in
a transfer pit.  The event is assumed to be initiated by a seismic event
during a waste transfer when the pit cover blocks are not installed.  The
earthquake causes rupture of the primary transfer pipe but leaves the
secondary encasement pipe intact.  This creates the potential for
pressurization of the transfer pipe leak detection system and a large spray
release directly to the atmosphere.  The release is maximized by assuming that
the following events also occur:
.     Leak detection fails in the transfer pipe
.     Transfer pit drain is blocked
.     Leak detection in the diversion box fails
.     Transfer pipe leak detection riser flange is not tight
.     Leak detection riser is pressurized.
The estimated frequency for the sequence of events is 2 x 10-7 to 8 x 10-8/yr
(WHC 1994b).  Based on adjustment of the size of the opening in the riser
flange to optimize the production of respirable aerosol, a release rate of
0.0217 L/s (0.006 gal/s) was calculated (WHC 1994a).  Leach (WHC 1994a)
assumed workers were exposed to this aerosol for 8 hours and the public for 24
hours.  Since a spray of this magnitude would be visible at some distance, it
is assumed for this evaluation that the spray release is detected and
terminated in 8 hours.  Workers and the public would then be exposed to 625 L
(165 gal) of respirable aerosol.
The accident scenario developed by Muhlestein (WHC 1994b) postulates a BDBE as
the initiating event but reduces the frequency of occurrence by assuming
independent failure of design features such as pipe and pit leak detection
systems.  Because a BDBE is assumed, no design feature can be assumed to
function.  The leak detection riser would not be pressurized unless the
primary pipe ruptured but the secondary pipe remained intact.  Although no
quantitative estimate is available, it is anticipated that this reasoning
would yield an accident frequency in the range of extremely unlikely to
incredible.
F.1.3.3 Leaks From Failures of the Waste Tank
 - The NTF would be constructed
utilizing the best current technology and lessons learned for DSTs and
instrumentation.  However, it is assumed that leaks from failure of the
primary waste tank could occur either through corrosion or a seismic event. 
The following features may mitigate an HLW tank leak:
.     Level indication
.     Secondary (annulus) tank containment
.     Liquid detection system in the annulus
.     Ventilation flow in the annulus 
.     Annulus ventilation continuous monitor
.     Annulus HEPA filter system.
If all of these systems should fail, the entire contents of the tank could be
released to the soil column.  Some of the waste could reach the surface and be
released to the atmosphere, particularly if there were large cracks in the
primary and secondary tank shells.  A BDBE is considered to be the only
credible initiating event.  Muhlestein (WHC 1994b) estimated the frequency of
a BDBE initiated simultaneous failure of all of these systems at 7 x 10-6 to 8
x 10-8/yr.  
To estimate the consequences of the loss of the entire contents 4.39 million L
(1.16 million gal) of a new DST, Leach assumed (WHC 1994a) that 10 percent of
the volume formed a pool on the ground surface and was released to the
atmosphere at a rate of 10-10 per second.  The release was assumed to occur
for 24 hours.  For consistency with more recent SAs (WHC 1995c), modeling of
release to the atmosphere has been changed for this evaluation.  The very
conservative assumption that 10 percent of the tank volume reaches the surface
is retained.  The pool is assumed to be present for 1 hour and the ground is
assumed to remain saturated with waste liquid for an additional 23 hours.  A
release rate of 4 x 10-4/hr is assumed for the pool and 3.6 x 10-7/hr for the
saturated ground.  Using these assumptions, a respirable volume of 2.87 L
(0.76 gal) would be released during 8 hours and of 5.39 L (1.42 gal) during 24
hours, the assumed exposure time of worker and the public, respectively.
The method used to estimate the accident frequency assumes a BDBE but also
assumes that the failure of each design feature remains independent of the
others.  It could be argued that the occurrence of a DBE would cause
simultaneous failure of all design safety systems and, in this case, the
frequency of the accident would be equal to the frequency of the earthquake,
1.44 x 10-5/yr.
F.1.3.4 Leaks From Waste Misrouting
 - Misrouting during waste transfers could
result in transfer of liquid waste to an open pipe in a process pit.  This
misrouting could result in either an overflow of the process pit or structural
damage to or overflowing of the tank to which the process pit drains.  The
following features serve to mitigate the consequences of such a misrouting:
.     Level indication differences between withdrawal and receiving tanks
.     Pit drain 
.     Liquid detection system in the process pit.
The frequency of a waste misrouting event in conjunction with failure of the
potentially mitigating features is estimated between 2 x 10-4/yr and 4 x 10-6
per year (WHC 1994b).  If the process pit drain is blocked and the pit liquid
detection system does not operate, liquid would fill the pit and leak out,
forming a pool at grade.  The transfer pump pit could be filled in less than 1
hour at a transfer rate of 6.31 L per second (100 gpm).  Since material
balances are performed at approximately 2-hour intervals the transfer pit
could overflow.  Leach assumed (WHC 1994a) that the overflow was detected
after 16 hours and that an additional 8 hours was required to cover the spill. 
Using a combination of pool and saturated soil release rates (WHC 1995c), 2.36
L (0.62 gal) of respirable material would be released in 8 hours and 4.46 L
(1.18 gal) in 24 hours.
If the pit drain is open and the pit liquid detection system does not operate,
the tank might be damaged from overfilling.  However, the soil release
consequences would be less than from a process pit, because the tank free
space at the maximum liquid level is greater than the volume of the process
pits.  If a tank failure was caused by overfilling, the consequences would be
bounded by the postulated full tank leak accident discussed in Section
F.1.3.3.
F.1.3.5 Pressurization of a Contaminated Process Pit
 - During long-term
operation, process pits would become contaminated with dried waste solutions
resulting from spills or leaks.  Contamination is normally confined by the
induced flow HEPA filter system.
An accident involving pressurization of a process pit might be caused by the
inadvertent transfer of incompatible materials from a process pit resulting in
failure of a test port during a pneumatic testing of the pipe encasement.  Air
leaking from the test port could resuspend contamination and transport it from
the process pit, either via the pit ventilation system or around the cover
blocks.  Features that may mitigate the consequences of such an event include
the process pit cover block(s), the ventilation flow path from the process
pit, and the ventilation system filters.  Although the frequency of this
accident has been estimated (WHC 1994b) at 3 x 10-3 to 1 x 10-4/yr, its
consequences are very small, even without filtration of the release (WHC
1994a).  Leach estimated a release of 4.5 x 10-4 L (1.2 x 10-4/gal) of
respirable material.
F.1.3.6 Nuclear Criticality
 - A criticality SA of Hanford Site HLW tanks has
concluded that the waste is highly subcritical (WHC 1994c).  The subcritical
nature of the waste in the waste tanks was demonstrated by evaluating the two
independent criticality parameters.  The first criticality parameter is the
concentration of Pu in the waste.  If the Pu concentration in the waste is
less than critical Pu concentration, the waste is subcritical.  The safe
critical Pu concentration is 2.6 g/L (0.02 lbs/gal).  The highest measured Pu
concentration in the HLW solids was 0.35 g/L (0.003 lbs/gal).  The second
criticality parameter is the relative amounts of neutron absorbers and Pu in
the waste.  If the ratio of the mass of neutron absorbers to Pu mass is less
than the minimum subcritical ratio for any neutron absorber present, the waste
is subcritical.  Analysis has shown that each solid waste sample contained
sufficient neutron absorbers to be subcritical.  Because the waste in the NTF
waste tanks would be highly subcritical, no facility-specific criticality
accident scenarios were developed for the NTF.
F.1.3.7 Flammable Gas Burn
 - A major function of the NTF would be to provide
mitigation for an accident involving a flammable gas burn event.  The NTF
would be constructed and operated to provide state-of-the-art protection from
this event.  The NTF's key prevention measures are:  Reliable ventilation to
prevent high gas concentrations in the tank vapor space and good mixing to
prevent gas accumulation in the waste.
In addition to the accumulation of a flammable gas mixture, there must be an
initiating source to cause a burn.  Factors such as electrical sources,
sparks, and lighting have been considered in assessing this risk.  It has been
concluded that the frequency of flammable gas burn is in the range of 1 x 10-6
to 1 x 10-7/yr (WHC 1993b).  A more recent review, using a quantified event
tree approach, estimated the frequency of a flammable gas burn in NTF tank
without primary tank or riser failure at extremely unlikely to incredible (WHC
1994b). 
Evaluation of the results of mitigation mixer pump test data from Tank 101-SY
led to the conclusion that the mixer pump can mitigate flammable gas buildup
indefinitely in this tank (PNL 1994a). 
F.1.3.8 Tank Bumps
 - A tank bump is a sudden release of vapor resulting from
the loss of circulation in the waste and resultant buildup of temperature
gradients in a waste tank.  Tank bumps occurred at the Hanford Site between
1954 and 1968 in HLW tanks containing waste with a high radioactive heat load. 
Existing high-heat load waste tanks are equipped with airlift circulators to
prevent buildup of temperature gradients.  The NTF storage tanks would be
equipped with mixing pumps that can serve the same purpose.  
Tank bumps are considered to be bounded by the tank overheating scenario
described in Section F.1.3.9.
F.1.3.9 Overheating of a Waste Tank
 - The temperature of HLW in the NTF would
be controlled by two parallel ventilation systems.  These ventilation systems
would be designed to prevent thermal damage to the tank and to prevent boiling
of the waste.  If the waste in the tanks boils, excessive quantities of vapor
could enter the ventilation train and result in the loss of filtration.
Overheating could be caused by addition of incompatible wastes or process
chemicals resulting in an exothermic reaction.  The heat generated would be in 
addition to the radioactive decay heat of the waste and the heat produced by
the operation of the mixing pump.  If one of the tank ventilation systems
fails and the mixing pump continues to run, the heat production rate could
exceed the remaining cooling capacity.  A longer term failure could result in
partial crystallization of the waste.  This is considered to be an operational
problem.  For a relatively large airborne release to occur, the filtration on
the once-through ventilation system must also be ineffective.
Because the existing tank waste and transfer criteria are not completely
defined, it is not possible to calculate the possible heat production due to
adverse reactions.  Leach evaluated (WHC 1994a) a scenario that assumes that
the tank contains waste with the design-basis radioactive-decay heat-load,
that no ventilation is operating, that there is no filtration on the once-
through ventilation system, and that the mixer pump continues to operate for
24 hours under these conditions.  It was assumed that all the heat from mixer
pump operation was used to boil off waste.  The frequency of this sequence of
events was estimated (WHC 1994b) at 5 x 10-5 to 5 x 10-7/yr.  Leach estimated
that 0.80 L (0.211 gal) of respirable liquid would be released in 8 hours and
2.39 L (0.63 gal) in 24 hours.
F.1.3.10 Gaseous Release of Toxic Material
 - Leach (WHC 1994a) chose two
scenarios to evaluate gaseous release of toxic materials from the NTF.  The
first scenario assumes a sudden increase in ammonia release resulting from a
rollover (burp) or sudden mixing of the contents of the waste tank.  The
second scenario assumes an increase in ammonia release rate due to elevated
temperature in the tank.  It was assumed that the off-gas condenser was
inoperable and that no other device in the ventilation system was effective in
reducing ammonia release.  The ammonia release rate for the burp scenario is
4,200 mg/s and 229 mg/s for the high-temperature scenario.  Muhlestein
estimated (WHC 1994b) the frequency of both the these scenarios at 1 x 10-2 to
3 x 10-4/yr.
F.1.3.11 Release of Materials From a Pressurized Tank Dome
 - A loss of the
heat removal capability of both ventilation systems combined with continued
full-power operation of both mixing pumps and the maximum radioactive heat
load is not sufficient to pressurize the tank dome space.  The adiabatic boil-
off rate is less than the design volumetric flow for the NTF once-through
ventilation system (Cloud 1993).  Chemical reactions and unregulated high-
volumetric steam flow into the tank dome space may lead to pressurization of
the tank dome space.  These postulated events and their consequences are
considered to be bounded by other accident scenarios.  
F.1.3.12 Chemical Reactions Due to Waste Misrouting
 - Section F.1.3.4
considered spills resulting from misrouting of waste transfers to open pipes
and overfull tanks.  This section discusses accidents due to chemical
reactions where waste is transferred to a tank containing incompatible waste.
There are chemical reactions, other that those that generate hydrogen gas,
that are of potential concern to the NTF.  These reactions do not necessarily
require incompatible waste mixing to occur.  Chemical reactions have been
studied for existing tank waste (WHC 1993b) and are briefly summarized as
follows.
.     Nitrated Organics - Organic compounds used at the Hanford Site are
      present in the waste as salts and are mixed with nitrates.  There are
      two types of reactions to consider; first an exothermic reaction between
      nitrates or nitrites and organic compounds, and second exothermic
      reactions involving nitrate and organic compounds in the presence of
      uranium, sometimes called a "red oil" reaction.  A "red oil" formation
      requires a high temperature, exceeding 135yC (275y F) and cannot be
      formed in the alkaline wastes stored in the Hanford Site waste tanks.  
      To produce a nitrate or nitrite salt reaction with organic compounds,
      the following four conditions are necessary:
      -    High concentration of organic material (ARH 1976) 
      -    An optimum near-stoichiometric mixture 
      -    High temperature, greater than 200yC (392y F) (ARH 1977) 
      -    Water content less than 20 percent by weight (ARH 1976).  
.     Organic Materials - Organic materials identified in this section could
      also produce flammable gases by radiolytic decomposition.  This is
      essentially the same mechanism as the hydrogen burn described in Section
      F.1.3.7 and is limited and controlled by the same mitigation effects.
.     Ammonium Nitrate - Ammonium nitrate is stable at standard temperature
      and pressure (i.e., normal tank conditions).  However, the aqueous
      alkaline environment of the waste tanks could drive the equilibrium
      toward ammonia which could be released to the tank vapor space.  If
      ammonia gas and nitrogen oxides exist together, then ammonia could
      combine with nitrogen dioxide to form ammonium nitrate.  
.     Ferrocyanide Reactions - Early studies (DOE 1987) suggested that a
      ferrocyanide reaction could cause an explosion within the tank.  This
      scenario was subsequently deemed not Reasonably Foreseeable (WHC 1994d).
F.1.3.13 Aircraft Crash
- The airspace above the Hanford Site is used by many types of aircraft, typically on a limited basis. The Hanford Site airspace is used by commercial air carriers, air taxis, general aviation, military aviation, contracted pesticide and herbicide aerial applicator aircraft, and Hanford Site bioscience surveillance aircraft. Commercial aircraft are considered to present the most threat to the NTF on the basis that they are the largest aircraft to routinely overfly the Hanford Site. Muhlestein estimated a frequency of approximately 8 x 10-8/yr for airplane crashes at the Hanford site. Based on this frequency, accidents involving airplane crashes are not reasonably foreseeable.

F.1.4 PAST PRACTICES SLUICING SYSTEM

A PPSS is being designed to retrieve the contents of Tank 106-C.  Tank 106-C
is a SST with a capacity of 2,000,000 L (530,000 gal) and now contains
approximately 746,000 L (197,000 gal) of sludge.  Because of decay heat from
the large quantity of 90Sr in the sludge, approximately 23,000 L/mo (6,000
gal/mo) of water are added to the tank to prevent drying of the sludge.  An EA
and FONSI have been issued for PPSS retrieval of Tank 106-C (DOE 1995).
For this EIS, it is assumed that PPSS design can be adapted for retrieval of
the 269,000 L (71,000 gal) of sludge in Tank 102-SY.  To evaluate accidents
that could be associated with this application of the PPSS, scenarios and
source terms taken from Preliminary Safety Evaluation for 241-C-106 Waste
Retrieval, Project W-320 (WHC 1994e) have been modified for better consistency
with safety analyses for other systems considered in this EIS.  Two types of
accident scenarios have been evaluated, Transfer Pipe Breaks, Section F.1.4.1,
and Pressurized Spray Leaks, Section F.1.4.2.
F.1.4.1 Transfer Pipe Breaks
 - Transfer pipe breaks could occur as the result
of BDBEs, excavation accidents, and operational failure such as corrosion or
blockage of the pipe.  If secondary containment is also breached, waste would
be released to the environment.  The spill would include waste pumped prior to
recognition of the accident and shutdown of the pump as well as drainback of
waste in the pipeline.  The PPSS for Tank 106-C has a pumping rate of 350 gpm
and includes 610 m (2,000 ft) of piping to allow circulation of sluicing fluid
between Tanks 106-C and 102-AY.  There is no design for a PPSS for Tank 102-
SY; pipe runs would be expected to be much shorter and drainback is considered
to be negligible.
A seismic event would be the most likely event to rupture both pipes; however,
when drainback is ignored, the volume spilled would be the same whether one or
both pipelines were ruptured.  The PSE for Tank 106-C (WHC 1994e) assumed a 2-
hour unmitigated leak and a 10-second mitigated leak for the seismic event. 
The duration of the unmitigated leak is not based on any particular design or
administrative control.  The duration of the mitigated leak is based on the
activation of a seismic cutoff switch.  Based on pumping rate alone, a 2-hour
leak would spill 159,000 L (42,000 gal) and a 10-second leak would spill 221 L
(58 gal).  It was assumed that 10 percent of the leak reaches the surface
where it becomes resuspended at a rate of 1 x 10-5/hr.  These assumptions
result in smaller releases of respirable material than obtained using
assumptions that are more consistent with recent safety assessments for other
systems considered in this EIS.
More recent accident analyses assume an 8-hour unmitigated pipe leak and a 2-
hour mitigated pipe leak.  These times assume detection of the leak during a
work shift change and by periodic material balance, respectively.  The entire
volume of the spill is assumed to remain on the surface for 1 hour and to
maintain saturation of surface soil for the remainder of the accident.  These
assumptions yield leak volumes of 636,000 L (168,000 gal) for the unmitigated
leak and 159,000 L (42,000 gal) for the mitigated leak.  The resuspension rate
of the liquid pool is 4.0 x 10-6/hr and 3.6 x 10-7/hr for the saturated soil. 
The quantities of respirable materials that would be released under both sets
of assumptions are shown in Table F-4.
Table F-4
Summary of PPSS Accident Releases
Accident                            Frequency                Exposure Duration   Respirable Volume 
Scenario                            (yr-1)                   (hr)                (L) 
Unmitigated Pipe                    Incredible               On-site 1           2.54 
Break                                                                7           1.60 
                                                                                 4.14 
                                                             Off-site    1       2.54 
                                                                     23          5.27 
                                                                                 7.81 
Mitigated Pipe                      Unlikely                 On-site 1           0.636 
Break                                                                7           0.401 
                                                                                 1.04 
                                                             Off-site    1       0.636 
                                                                     23          1.32 
                                                                                 1.96 
Unmitigated Spray                   Extremely                On-site 2           831 
Release                             Unlikely to 
                                    Incredible 
                                                             Off-site    2       831 
Unmitigated Spray                   Extremely                On-site 8           3,312 
Release                             Unlikely to 
                                    Incredible 
                                                             Off-site    8       3,312 
Mitigated Spray                     Anticipated to           On-site 8           0.0000438 
Release                             Unlikely 
                                                             Off-site    8       0.0000438
The PSE for the Tank 106-C PPSS estimated accident frequencies were based on
the frequency of the initiating event and did not consider whether the system
was in use at the time of the accident.  Using this approach, the unmitigated
seismic transfer pipe break has a frequency of unlikely (7.0 x 10-4/yr) and
the operational accident has a frequency of anticipated (1.7 x 10-2/yr).  No
frequency was given for the excavation accident.  This is a more conservative
approach than used to estimate accident frequencies for other systems
considered in this EIS.  The unmitigated 8-hour leak is considered to
incredible and the 2-hour mitigated leak is considered to be unlikely.
F.1.4.2 Pressurized Spray Leaks
 - Pressurized spray leaks could occur in
valve and transfer pits due to misaligned or failed jumpers.  For the
unmitigated case (i.e., pit cover blocks off), the PSE (WHC 1994e) assumed a
5-cm long (2-in) 0.1-mm (0.004-in) wide crack in a valve stem operating at a
pressure of 180 psig and estimated a respirable material release rate of 0.114
L/s (0.03 gal/s).  As indicated in Table F-4, a 2-hour leak would result in
release to the atmosphere of 831 L (220 gal) of respirable material and an 8-
hour leak in the release of 3,312 L (875 gal).
The PSE (WHC 1994e) estimated the quantity of respirable material released to
the atmosphere for a mitigated spray leak based on the displacement of vapor-
laden air from the pit as it filled with liquid emerging from a broken or
disconnected jumper.  An aerosol loading of 10 mg/m3 (6 x 10-7 lbs/ft3) was
assumed for the vapor.  The displacement rate of 0.062 m3/s (2.2 ft3/s) was
based on 180 psig through a 5-cm (2-in) diameter, squared-edged orifice. 
Under these conditions, 4.38 x 10-5 L for respirable waste would be released
to the atmosphere in 8 hours.
Based on analogy to the ITRS system and consideration of the limited operating
time of the PPSS, the unmitigated spray release frequency is considered to be
extremely unlikely to incredible and the mitigated spray release frequency to
be anticipated to unlikely.

F.2 INTERIM STABILIZATION OF SINGLE SHELL TANKS

This section describes the activities involved in interim stabilization and
characterizes the potential accidents which could result.  
Interim stabilization of SSTs is accomplished by saltwell jet pumping.  Jet
pumps are used to remove interstitial liquids from saltcake and sludge in the
SSTs.  Pumping rates vary from approximately 0.19 to 19 L/min (0.05 to 5.0
gpm).  The interstitial liquids are routed to DCRTs through transfer piping
and valve pits.  Depending on the location of the SST and the DCRT, transfer
piping may be double-encased in concrete or another steel pipe or single-
encased (direct buried).  Existing salt well transfer piping is beyond its
design life and is pressure tested every 6 months to minimize leaks.  Transfer
valve pits are equipped with cover leak detection interlocked to the
appropriate pumps and covered by heavy shield blocks.  The valve pits are
designed to allow several SSTs to be pumped simultaneously to a common DCRT.
DCRTs are housed in underground reinforced concrete vaults.  The steel tanks
have capacities of either 76,000 L (20,000 gal) for Tank 244-S or 95,000 L
(25,000 gal) for Tanks 244-TX and 244-U.  The DCRT vaults include HEPA
ventilation systems, interlocked leak detection systems, and tank sluicing
systems.  Permanent neutron detectors are installed in DCRT 244-TX and
portable detectors can be used in steel Tank 244-S.  There are no provisions
for neutron monitoring in DCRT 244-U.  SWL accumulated in DCRTs in the 200
West Area is presently transferred to Tank 102-SY.  SWL can be transferred
through the ECSTS.
A number of reports have evaluated accidents associated with salt well pumping
activities.  Safety Study of Interim Stabilization of Nonwatchlist Single-
Shell Tanks (WHC 1992) evaluated spray leaks, equipment fires, hydrogen fires,
waste stability, and transfer pipe leaks.  Environmental Assessment, Waste
Tank Safety Program (DOE 1994) focused on issues associated with interim
stabilization of Watchlist SSTs.  A FONSI was issued for these activities on
February 25, 1994.  A more recent report, Safety Analysis; Tank Farms Waste
Transfer System Leaks, Breaks, and Spray Releases (WHC 1994f), is generally
applicable to interim stabilization of SSTs.  This more recent report is used
as the basis for evaluating accidents during interim stabilization of SSTs. 
The accidents evaluated are:
.     Salt Well Transfer Piping Leaks
.     Salt Well System Spray Leaks.

F.2.1 SALT WELL TRANSFER PIPING LEAKS

Salt well transfer piping includes both double-encased and single-encased
steel piping.  More than 80 percent of the salt well transfer piping is
single-encased pipe which is 2.5 cm to 8 cm (1 to 3 in) in diameter and
shielded by 0.9 m (3 ft) of soil.  The pipe may be either buried or bermed on
the ground surface.  All of this piping is beyond its 10-year design life. 
Stahl (WHC 1994f) estimated a failure frequency of 3.0 x 10-7/hr-ft based on
the Hanford Site soil conditions and the age of the pipe.  This failure
frequency was then used with pipe lengths and assumptions regarding pumping
rates to estimate transfer piping leak frequencies and maximum leak volumes
for salt well jet pumping of individual tank farms.  The maximum leak volumes
are based on maximum rather than nominal transfer pump rates and assume 16-
hour releases.  The results are shown in Table F-5.
Table F-5
Estimated Frequencies and Maximum Volumes
for Salt Well Transfer Line Leaksa
                                    Frequency           Volume (L) 
Farm     Tanks 
                                    200 East Area 
A & AX   A-101, AX-101              2.6/yr              36,300 
                                    Anticipated 
BX       BX-106                     4.2 x 10-2/yr       18,200 
                                    Anticipated 
BY       BY-102, BY-103, BY-105,    3.1/durationb       72,700 
         BY-106, BY-109             Anticipated 
C        C-102, C-103, C-105,       0.34/duration       72,700 
         C-106, C-107, C-110        Anticipated 
                                    200 West Area 
S        S-101, S-102, S-103,       0.85/yr             90,800 
         S-106, S-107, S-108,       Anticipated 
         S-109, S-110, S-111, 
         S-112 
SX       SX-101, SX-102, SX-103,    2.0/duration        54,500 
         SX-104, SX-106             Anticipated 
T        T-104, T-107,T-110,T-111   4.7/yr              54,500 
                                    Anticipated 
U        U-102, U-103, U-105,       0.46/duration       72,700
         U-106, U-107, U-108,       Anticipated 
         U-109, U-111 
Source:  WHC 1994f 
      aFrequencies are based on pipe failure only and do not include operator
error or failure of other systems such as leak detection.
      bSalt well pumping expected to take less than 1 year.
The maximum leak volumes are based on the assumptions that leak detection does
not function and that the leak is not discovered for 16 hours.  Based on prior
experience with similar piping, it was assumed that the entire volume reaches
the ground surface where it forms a pool for 1 hour and keeps the soil
saturated thereafter.  The quantity of respirable radioactive material
released was estimated using an ARR of 4 x 10-6/hr for pools for the first
hour and an ARR of 3.6 x 10-7/hr for saturated soil for the remainder of the
accident.  Workers were assumed to be exposed for 8 hours and members of the
public for 24 hours.  The volumes of respirable material released are shown in
Table F-6.
Table F-6
Summary of Accident Releases During Pumping and Transfer of SWL
                                                               Exposure            Respirable 
Accident                            Frequency                  Duration            Volume 
Scenario                            (yr-1)                     (hr)                (L) 
Unmitigated Transfer                2.3 x 10-3 to              On-site 1           0.363 
Piping Leak (90,800 L)              1.0 x 10-2                  15                 0.490 
                                    Unlikely                                       0.853 
                                                               Off-site 1          0.363 
                                                                23                 0.752 
                                                                                   1.11 
Mitigated Transfer                  0.46 to 2.0                On-site 1           0.0727 
Piping Leak (18,200 L)              Anticipated                 7                  0.0458 
                                                                                   0.118 
                                                               Off-site 1          0.0727 
                                                                15                 0.981 
                                                                                   0.171 
Unmitigated DCRT Spray              1.1 x 10-5                 On-site 8           28.5 
Leak (207 psig)                     Extremely Unlikely 
                                                               Off-site 24         85.5 
Mitigated DCRT Spray                1.1 x 10-2                 On-site 8           3.03 x 10-5 
Leak (207 psig)                     Anticipated 
                                                               Off-site 24         9.09 x 10-5 
Unmitigated Salt Well               1.1 x 10-4                 On-site 8           7.31 
Spray Leak (80 psig)                Unlikely 
                                                               Off-site 24         21.9 
Mitigated Salt Well                 0.11                       On-site 8           1.92 x 10-5 
Spray Leak (80 psig)                Anticipated 
                                                               Off-site 24         5.76 x 10-5
Source:  WHC 1994f 
The frequencies shown in Table F-5 are based on current interim OSRs.  It was
estimated that the frequency of salt well transfer piping leaks could be
reduced by a factor of 1,000 by requiring material balance discrepancy (MBD)
surveillances (WHC 1994f).  MBD surveillances combined with restrictions on
the number and types of salt well tanks  (i.e., High Source Term) could reduce
the maximum leak volume to 4,500 to 18,200 L (1,200 to 4,800 gal).  Table F-6
shows respirable volumes released based on a leak volume of 18,200 L (4,800
gal) as a mitigated case.  Including frequencies of 0.1 failure per year for
failure of leak detection and of 0.05 failure per year for failure to respond
to a leak detection alarm (WHC 1994b) would shift the frequency of pipe leaks
in the 200 West Area Salt Well Transfer System into the Unlikely category.

F.2.2 SALT WELL SYSTEM SPRAY LEAKS

Spray leaks could occur in SST pump pits, DCRT pump pits, and valve pits
during pumping and transfer of salt well liquids.  Stahl estimated (WHC 1994e)
frequencies of occurrence and release rates for spray leaks during transfer of
SWLs from a SST to a DCRT and from a DCRT to a DST.  Stahl noted that these
accidents are also applicable to Diversion Boxes 241-UX-154 and 241-ER-151 on
the ECSTS and to other diversion boxes in the SST/DST and Aging Waste Facility
waste transfer system.
Section F.2.2.1 describes the potential accidents which could occur in SST to
DCRT transfers and Section F.2.2.2 describes DCRT to DST transfer accident
potential.
F.2.2.1 Spray Leak During SST to DCRT Transfer
 - This accident scenario
assumes (WHC 1994f) that a jumper was improperly installed during routine
maintenance in a jumper pit providing liquid transfer from the SST to a DCRT. 
The jumper misalignment is assumed not to be discovered during visual
inspections or leak testing before the pit is returned to service.  The jumper
is assumed to leak at both ends.  A maximum flow of 19 L/min (5.0 gpm) and
pressure of 80 psig are assumed.  It is also assumed that the spray leak is
not detected for 16 hours and that an additional 8 hours are required to
terminate the leak.  Workers are exposed to spray aerosol for 8 hours (one
shift) while members of the public are exposed for 24 hours.
Two accident scenarios were analyzed:  an unmitigated spray release with cover
blocks not in place and a mitigated spray release with cover blocks in place. 
As discussed in the following sections, these scenarios have different
frequencies of occurrence, release durations, and release rates.
.     Unmitigated Spray Release - The frequency of a spray leak in pump and
      valve pits is estimated to be 0.112/yr (WHC 1994f).  This frequency
      estimate assumes continuous operation and considers the length of pipe,
      the number of gaskets and valves in a pit, and the frequency of jumper
      misalignment.  Due to the relatively low flow rate, it is assumed that
      leak detection would not be activated.  Inclusion of the frequency for
      failure to replace cover blocks (0.001/yr) reduces the frequency for an
      unmitigated spray release during SST to DCRT transfer to 1.1 x 10-4/yr. 
      The quantities of respirable liquids for 8-hour worker exposures and
      24-hour public exposures are shown in Table F-5 and are based on
      optimization of the aerosolization rate (WHC 1994f). 
.     Mitigated Spray Release - The accident scenario for a mitigated spray
      release during SST to DCRT transfers from a misaligned jumper assumes
      that cover blocks are in place.  Leak detection functions are assumed
      not to be active due to the low flow rate.  These assumptions do not
      alter the duration of the release relative to the unmitigated case but
      do alter the frequency of occurrence and release rate.  The frequency of
      the event is 0.112/yr (WHC 1994f).  The spray saturates the atmosphere
      inside the pit and the aerosol is forced out as liquid accumulates in
      the pit.  Assuming a vapor loading of 10 g/m3 and a pipe pressure of 80
      psig, workers would be exposed to 1.92 x 10-5 L of respirable liquids
      and the public to 5.76 x 10-5 L.
F.2.2.2 Spray Leak During DCRT To DST Transfer
 - This accident scenario
assumes that a jumper was improperly installed resulting in misalignment
during routine maintenance in a jumper pit providing liquid transfer from the
DCRT to another tank (e.g., Tank 102-SY or a load and unload facility) (WHC
1994f).  The jumper misalignment is assumed not to be discovered during visual
inspections or leak testing before the pit is returned to service.  The jumper
is assumed to leak at both ends.  The DCRT pumps in the T and U Tank Farms
operate at a pressure of 207 psig and that in the S Tank Farm at 80 psig, all
with flow rates ranging from 189 L to 379 L/min (50 to 100 gpm).  It is
assumed that the spray leak is not detected for 16 hours and that an
additional 8 hours are required to terminate the leak.  Workers are exposed to
spray aerosol for 8 hours (one shift) while members of the public are exposed
for 24 hours.
Two accident scenarios were analyzed:  an unmitigated spray release with cover
blocks not in place and a mitigated spray release with cover blocks in place. 
As discussed in the following paragraphs, these scenarios have different
frequencies of occurrence, release durations, and release rates.
.     Unmitigated Spray Release - The frequency of a spray leak in pump and
      value pits is estimated to be 0.112/yr (WHC 1994f).  This frequency
      estimate assumes continuous operation and considers the length of pipe,
      the number of gaskets and valves in a pit, and the frequency of jumper
      misalignment.  Inclusion of frequencies for leak detection failure
      (0.1/yr) and failure to replace cover blocks (0.001/yr) reduces the
      frequency for an unmitigated spray leak in a DCRT pump pit to 1.1 x
      10-5/yr.  The quantities of respirable liquids for 8-hour worker
      exposures and 24-hour public exposures are shown in Table F-6 and are
      based on optimization of the aerosolization rate (WHC 1994f). 
.     Mitigated Spray Release - The accident scenario for a mitigated spray
      release from a DCRT pump pit from a misaligned jumper assumes that cover
      blocks are in place and the leak detection functions.  These assumptions
      do not alter the duration of the release relative to the unmitigated
      case but do alter the frequency of occurrence and release rate.  The
      frequency of the event is 0.112/yr (WHC 1994f).  The spray saturates the
      atmosphere inside the pit and the aerosol is forced out as liquid
      accumulates in the pit.  Assuming a vapor loading of 6.2 x 10-4 lbs/ft3
      (10 g/m3) and a pipe pressure of 207 psig, workers would be exposed to
      3.03 x 10-5 L (8 x 10-6 gal) of respirable liquids and the public to 9.09
      x 10-5 L (2.4 x 10-5 gal).

F.3 UNDERGROUND CROSS-SITE TRANSFER

Underground cross-site transfer could be accomplished through the use of the
ECSTS or, if constructed, through the RCSTS.  The ECSTS was constructed in the
1950s, and is expected to have a higher failure rate than the RCSTS which
would be designed to meet current safety standards.  Four of the six lines in
the ECSTS are believed to be plugged.  One of the remaining lines passed a
pressure test in June 1995.
Two major types of accidents can be hypothesized for the cross-site transfer
systems.  The first is a pipe break, or its equivalent.  Depending on the
leakage rate, location, and duration, the liquid waste released could remain
totally below grade or could reach the surface and be released to the
atmosphere.  The second is a spray leak.  Spray leaks could occur in a
diversion box or in pump and valve pits.  Depending upon the spray
characteristics (flow, geometry, particle size) and pit status (cover in place
or not), the consequences of spray leaks could range from very low to severe.
Although the types of accidents that could occur during operation of the ECSTS
and RCSTS are similar, their frequencies of occurrence and release rates are
different.  Accidents involving the ECSTS are discussed in Section F.3.1 and
those involving the RCSTS in Section F.3.2.  

F.3.1 EXISTING CROSS-SITE TRANSFER SYSTEM

The ECSTS is comprised of the 241-ER-151 Diversion Box located in the 200 East
Area, 241-UX-154 Diversion Box located in the 200 West Area, 241-EW-151 Vent
Station located at the high point between the 200 East and West Areas, and
approximately 5.6 km (3.5 mi) of concrete-encased stainless steel pipe that is
buried at depths of 1.5 to 5 m (5 to 15 ft).  There are six ECSTS pipelines,
of which four are believed to be plugged.  Each has a nominal pipe size of 8
cm (3 in).  There are 58 encasement test risers spaced regularly along the
concrete encasement between the diversion boxes.  These test risers provide
access to the encasement void space for leak detection.  The concrete
encasement slopes in both directions from the vent station and drains into a
catch tank at each diversion box.  Catch tank contents can be transferred to a
designated DST and held for later processing.  Additional descriptive
information regarding the ECSTS is in Chapter 3 of this EIS.
Five events associated with the ECSTS are considered to adequately encompass
the range of plausible accident scenarios.  They are:
.     Waste transfer line leak
.     Overflow of the 241-EW-151 Vent Station Catch Tank
.     Rupture of the encasement and pipeline, either by an earthquake during a
      transfer of waste, or by excavation activities with a subsequent
      transfer of waste
.     Spray release from a diversion box with the cover blocks installed
.     Spray release from a diversion box with the cover blocks not installed.
Accident scenarios for the first three events were developed in  Operational
Safety Analysis Report, Cross-Country Waste Transfer System, (WHC 1989) and in
Safety Analysis; Tank Farms Waste Transfer System Leak, Breaks, and Spray
Releases, (WHC 1994f).  Frequencies of occurrence and release rates for these
five accidents are summarized in Table F-7.
Table F-7
Summary of ECSTS Accident Releases
 
                                                                                    Respirable 
Accident                             Frequency                  Exposure Duration   Volume 
Scenario                             (yr-1)                     (hr)                (L) 
Waste Transfer Line                                             On-site N/Aa        N/A 
Leak                                 Anticipated 
                                                                Off-site N/A        N/A 
Overflow of the                                                 On-site N/A         N/A 
Vent Station Catch                   Unlikely 
Tank
                                                                Off-site N/A        N/A 
Rupture of the                                                  On-site 1           0.318 
Pipeline and                          Unlikely                   7                  0.200 
Encasement                                                                          0.518 
                                                                Off-site 1          0.318 
                                                                 23                 0.658 
                                                                                    0.976 
Unmitigated Spray                    1.1 x 10-5                 On-site 8           28.5 
Release w/cover                      Extremely 
Blocks not                           Unlikely 
Installed
                                                                Off-site 24         85.5 
Mitigated Spray                      1.1 x 10-2                 On-site 8           3.03 x 10-5 
Release w/Cover                      Anticipated 
Blocks Installed
                                                                Off-site 24         9.09 x 10-5
Source:  WHC 1989, WHC 1994f
      aN/A = Not Applicable.  Waste liquids are not expected to reach the
ground surface.
F.3.1.1 Waste Transfer Line Leak
 - For this accident scenario, leaks could
occur in an ECSTS pipeline during waste transfer.  The majority of the leak
volume would be retained within the concrete encasement.  Plugged drain lines
leading to the catch tanks from the encasement would result in waste liquid
being backed up into the pipe chase of Diversion Box 241-ER-151 and/or
241-UX-154, which would overflow to encasements leading to various other sumps
and catch tanks.  Some of the waste liquid in these encasements could escape
to the surrounding soil through joints or small cracks.  Entrop (WHC 1989)
estimated that up to 79,500 L (21,000 gal) of waste could be released into the
encasement and that 10 percent of this volume would be released to the soil
through small cracks in pipeline or diversion box encasements.  Since the
hydrostatic head for this ground release would be very small, the flow rate at
any single leak point would likely be very low, approximately 2 L/min (0.5
gpm).  Based on this very low flow rate, Entrop concluded that no waste liquid
would reach to ground surface.  Accordingly, Table F-7 shows no release of
respirable material for this accident.
An ECSTS waste transfer line leak is an anticipated event based on an analysis
of transfer pipe failure rates by Stahl (WHC 1994f).  Stahl estimated the
failure rate of 3.0 x 10-7 per hr-ft for pipes similar to that in the ECSTS. 
The ECSTS is 5.6-km (3.5-mi) long and has a nominal pumping rate of 190 L/min
(50 gpm).  If the ECSTS were used to transfer all the SWL from the 200 West
Area and the free liquid from Tank 102-SY, several leaks of this type would be
expected to occur in the ECSTS.  If drain lines within the diversion box were
plugged or if there were large cracks in the ECSTS encasement, a significant
volume of waste liquid could reach the ground surface.  The integrity of the
concrete encasement cannot be directly determined at this time.  The
consequences of waste transfer pipe leaks under these conditions are bounded
by the encasement rupture accident considered in Section F.3.1.3.
Several factors would tend to reduce the frequency of waste transfer pipe
leaks.  Current practice at the Hanford Site is to perform a hydrostatic test
prior to each use of an ECSTS pipeline.  This test entails pressurizing the
pipeline to a predetermined pressure and subsequent monitoring of the pipeline
pressure for a period of time to ensure that no leak path (as would be
revealed by a pressure drop in the pipeline) exists.  Leakage could be
detected through inspection of encasement test risers, recognition of a
discrepant material balance, or liquid level rise in a catch tank.  Leaks
could be detected by a conductivity probe located inside the ECSTS Diversion
Boxes.
F.3.1.2 Overflow of The 241-EW-151 Vent Station Catch Tank
 - An open vent
valve on an ECSTS pipeline could cause the 241-EW-151 Vent Station Catch Tank
to overflow into the pipeline encasement.  To pump liquid into the 241-EW-151
Vent Station Catch Tank, it would be necessary to have an obstruction in the
pipeline somewhere past the vent station and have the vent station vent valve
left open.  This scenario is unlikely.
Liquid entering the 241-EW-151 Vent Station Catch Tank would eventually
actuate the high-level alarm in the catch tank, which is transmitted to the
Computer Automated Surveillance System (CASS) in the 2750E Building.  Also,
any increase in ambient radiation levels in the vicinity of the vent station
would be transmitted to the CASS.  The CASS operator would then notify the
appropriate personnel so that corrective actions could be taken.  Failure to
identify the event or failure to take the proper corrective actions would
result in solution overflowing to the ECSTS encasement with subsequent
drainage into the Catch Tanks 241-UX-302-B and/or 241-ER-311.  Catch Tank 241-
UX-302-B is associated with Diversion Box 241-UX-154.  Catch Tank 241-ER-311
is associated with Diversion Box 241-ER-151.  Should the increase in level in
these catch tanks go unnoticed, the leak would be detected by the recognition
of a MBD.  Material balances are performed every 2 hours.
Entrop (WHC 1989) estimated that these factors would limit the overflow to the
ECSTS encasement to 20,900 L (5,520 gal).  As discussed in Section F.3.1.1,
only 10 percent of this volume would be expected to escape the encasement and
none would be expected to reach the ground surface.
F.3.1.3 Rupture of the Encasement and Pipeline
 - Both the ECSTS pipelines and
their concrete encasement could be ruptured by either an excavation accident
or a seismic event.  The leak would be maximized if the encasement ruptured
immediately adjacent to an ECSTS diversion box.  A recent study of similar
accidents for the RCSTS estimated frequencies for leaks detected within 2
hours of 7.5 x 10-7/yr for the excavation-initiated events and 5.4 x 10-8/yr
for events initiated by a BDBE (WHC 1995b). 
The frequency of the excavation-initiated event for the RCSTS is considered
applicable to the ECSTS but that of the BDBE-initiated events is not.  Entrop
concluded that seismic events with horizontal ground motion exceeding 0.05 g
would be sufficient to damage both the ECSTS pipelines and encasement.  The
design basis earthquake for the RCSTS is 0.2 g with a frequency of 1.44 x
10-4/yr.  An earthquake with a horizontal ground motion of 0.09 g has an
estimated frequency of 2 x 10-3/yr (WHC 1994a, WHC 1994g).  On this basis, the
frequency of a release from an earthquake-induced rupture of the ECSTS
pipeline and encasement is estimated as Unlikely.
Entrop estimated that a maximum of 79,500 L (21,000 gal) of waste could leak
from the ruptured pipeline and encasement under these conditions.  It is
assumed that this entire volume reaches the ground surface and forms a pool
for 1 hour.  Respirable radioactive material is assumed to be released from
this pool at the rate of 4.0 x 10-6/hr (DOE 1993).  Thereafter, soil at the
site of the release remains saturated, releasing respirable material at the
rate of 3.6 x 10-7/hr (DOE 1993) until covered 24 hours after the initial
spill began.  The volume of respirable material released during an 8-hour work
shift is 0.518 L (0.137 gal) and the total volume of respirable material
released in 24 hours is 0.976 L (0.26 gal).
F.3.1.4 Spray Release From a Diversion Box With Cover Blocks Installed
 - A
recent safety analysis of hazards involving leaks, breaks, or spray releases
from waste transfer systems associated with the tank farms at the Hanford Site
included evaluation of spray releases applicable to the ECSTS Diversion Boxes
(WHC 1994f).  Four initiating events were identified for a spray release
within a pit or diversion box.  These events are failures of gaskets, valve
packing, and piping, and a faulty jumper connection due to a maintenance
error.  The total frequency of occurrence of these initiating events was
calculated to be 0.112 per year, with the dominant contributor being leaks
from valve packing.  This frequency assumes two gaskets, two valves, and 6 m
(20 ft) of piping in the pit, and continuous operation of the diversion boxes.
The ECSTS diversion boxes are equipped with conductivity probes that would
detect the leak.  Inclusion of frequency for leak detection failure (0.1/yr)
(WHC 1994b) reduces the frequency of a mitigated spray release in an ECSTS
diversion box to 1.1 x 10-2/yr which corresponds to an anticipated event.
Stahl assumed that the spray leak occurred at both ends of the jumper and
remained undetected for 24 hours (WHC 1994f).  It is assumed that the spray
saturates air inside the diversion box to a vapor loading of 10 mg/m3 (6 x
10-7 lbs/ft3) and that this air is forced between the cover blocks as the leak
continues.  The corresponding volume of respirable material released is 9.09 x
10-5 L.  The volume released as a respirable aerosol during an 8-hour work
shift is 3.03 x 10-5 L (8 x 10-6/gal).
F.3.1.5 Spray Release From a Diversion Box With Cover Blocks Not Installed
 -
The initiating events for a spray release accident with cover blocks not
installed are the same as discussed in Section F.3.1.4; however, based on a
frequency of 0.001/yr for failure to install the cover blocks (WHC 1994b), the
frequency of occurrence drops to 1.1 x 10-5/yr which corresponds to Extremely
Unlikely.  Stahl assumed (WHC 1994f) a pressure of 207 psig and maximized the
amount of respirable aerosol but adjusting the size of the slit through which
the spray escapes.  Stahl also assumed a 24-hour release which corresponds to
a respirable volume of 85.5 L (22.6 gal) and 28.5 L (7.5 gal) during an 8-hour
work shift.  This release rate is approximately one to two orders of magnitude
less that release rates for similar accidents involving NTF, RCSTS, and ITRS. 
The resulting spray may not be readily visible from a distance and would
therefore be more difficult to detect.

F.3.2 REPLACEMENT CROSS-SITE TRANSFER SYSTEM

The RCSTS has many characteristics in common with the ECSTS, including similar
accident scenarios.  Since the RCSTS is longer 10.5 km (6.2 mi), operates at a
higher pressure, 1,200 psig, and has a higher transfer rate, 530 L/min (140
gpm), than the ECSTS, the accident scenarios could result in larger releases. 
However, as a newly designed and constructed system, it would be more risk-
free than the ECSTS.  The RCSTS would not have the aging problems of the
existing system (corrosion, secondary concrete containment cracking), and its
design reflects the current state-of-the-art and incorporates lessons learned
over the past 40 years of operation.
New features which add to the system reliability and integrity include the
following:
.     Hard-connected piping used in place of jumpers which historically have
      had a number of significant failures.
.     Diversion box(es) designed to eliminate the need to remove cover blocks
      for routine maintenance and inspection activities.  A stairwell with
      Safety Class 1 doors provides access for these activities.  The geometry
      of the doors, stairwell, and support building entry does not provide a
      direct path to the atmosphere for a spray leak.  Cover blocks are
      installed directly over heavy equipment (e.g., pumps) and are no larger
      than required to allow replacement of the equipment to further reduce
      the likelihood of a spray release directly to the atmosphere.
.     Double containment provided for each transfer line by a concentric outer
      pipe rather than the single concrete encasement for the ECSTS pipelines. 
      This provides greater leak detection sensitivity and separate leak
      detection for each transfer line.
.     The control and alarm systems are more sensitive and reliable.
Potential RCSTS accident frequencies and consequences were evaluated in Cross-
Site Transfer System Preliminary Safety Analysis Report (WHC 1995c). 
Quantitative estimates were provided for four accidents:
.     Transfer line breaks
      -     Beyond design basis (unmitigated)
      -     Design basis (mitigated)
.     Spray releases
      -     Cover blocks not in place (unmitigated)
      -     Cover blocks in place (mitigated).
The frequencies of occurrence, exposure durations, and quantity of respirable
materials released are summarized in Table F-8.  Descriptions of these
accidents are provided in Sections F.3.2.1 and F.3.2.2.
Table F-8
Summary of RCSTS Accident Releases
                                             Exposure            Respirable 
Accident         Frequency                   Duration            Volume 
Scenario         (yr-1)                      (hr)                (L) 
Transfer Pipe     2.2 x 10-6 to 5.4 x 10-8   On-site      1      1.17 
Break            Extremely Unlikely to Not                7      0.736 
(Unmitigated)    Reasonably Foreseeable                          1.91 
                                             Off-site     1      1.17 
                                                          23     2.42 
                                                                 3.59 
Transfer Pipe    1.5 x 10-5 to 1.1 x 10-6    On-site      1      0.404 
Break            Extremely Unlikely                       7      0.255 
(Mitigated)                                                      0.659 
                                             Off-site     1      0.404 
                                                          23     0.836 
                                                                 1.24 
Unmitigated      1.9 x 10-9                  On-site      8      6,700 
Spray Release    Not Reasonably 
                 Foreseeable 
                                             Off-site     8      6,700 
Mitigated        0.11 to 0.03                On-site      8      0.0075 
Spray Release    Anticipated 
                                             Off-site     8      0.0075
Source:  (WHC 1995c) 
F.3.2.1 Transfer Line Breaks
 - The RCSTS transfer line consists of an 8-cm
(3-in) diameter, Schedule 40 stainless steel pipe within a 15-cm (6-in)
diameter carbon steel pipe.  The primary piping is of all-welded construction. 
An electronic system in the annular space is capable of detecting and
identifying the approximate location of any leak.  The secondary containment
pipe is a closed system and can be pressure tested to confirm its integrity. 
Such testing would be performed at least once per year (WHC 1995c).  All of
these new design features add to the integrity of the RCSTS and would result
in lower probability of accident and/or failure events. 
Lindberg estimated the frequencies of transfer line breaks initiated by
excavation accidents and by a BDBE (WHC 1995b).  It was determined that common
backhoes used for construction were not capable of rupturing both the primary
and secondary pipes; however, an oversized backhoe could cause a double break. 
The excavation scenario considered the following events and frequencies:
.     Excavation occurs (1.0)
.     Waste transfer in progress (0.3/yr)
.     Oversized backhoe is available and used (0.01)
.     Administrative control fails - wrong area excavated (0.1)
.     Location fails - "terra tape" and marker posts not seen (0.1)
.     Rupture occurs (0.5)
.     Warnings fail - material balance, flow, pressure, level without leak
      detection (0.05).
The result of this scenario would be a leak lasting more than 2 hours with a
frequency of 7.5 x 10-7/yr which corresponds to Incredible.  If warnings are
recognized and responded to, the frequency becomes 1.5 x 10-5/yr (Extremely
Unlikely) but the leak is limited to not more than 2 hours.
The earthquake scenario considered (WHC 1995c) the following events and
frequencies:
.     BDBE occurs (1.44 x 10-4/yr)
.     Waste transfer in progress (0.3/yr)
.     Administrative control fails - manual shutdown not performed (0.05)
.     Leak detection fails (0.5)
.     No response to leak detection occurs (0.001)
.     Warnings fail - material balance, flow, pressure, level (does not
      include leak detection) (0.05)
Two event tree branches lead to spills of more than 2 hours.  The more likely
of the two assumes that leak detection and material balance and other warnings
fail and has a frequency of occurrence of 5.4 x 10-8/yr.  This sequence is
considered not reasonably foreseeable.  The frequency of a leak of not more
than 2 hours is 1.1 x 10-6/yr which corresponds to Extremely Unlikely.  
It could be argued that failures of engineered systems are not independent for
a BDBE so that the frequency of leak detection failure would be 1.0.  It could
also be argued that it is inappropriate to consider both failure to execute a
manual shutdown and failure to perform material balance under these
conditions.  This would increase the frequency of an 8-hour release to 2.2 x
10-6/yr.
The total volume of waste spilled during an unmitigated transfer pipe break is
292,000 L (77,100 gal).  This includes 254,000 L (67,200 gal) pumped in the 8
hours before the leak is detected and 37,500 L (9,900 gal) that drains from
the filled line through the break.  A 2-hour leak would spill 101,000 L
(26,700 gal).  It is conservatively assumed that all of the waste spilled
reaches the ground surface.
The following paragraphs describe unmitigated and mitigated RCSTS pipe break
accidents.
.     Unmitigated Transfer Pipeline Break - An unmitigated transfer pipeline
      break is assigned a frequency of occurrence ranging from Extremely
      Unlikely to Not Reasonably Foreseeable.  This frequency range reflects a
      usage factor of 0.3 and the assumptions that a BDBE would cause
      simultaneous failure of all engineered systems and that material balance
      would not be performed.  It is assumed that 292,000 L (77,000 gal) of
      waste are spilled in the 8 hours before the leak is detected.  The spill
      forms a pool on the ground surface for 1 hour and then keeps the soil
      saturated until the spill area is covered 16 hours after detection. 
      Respirable material is released from the pool at a rate of 4.0 x 10-6/hr
      and from the saturated ground at a rate of 3.6 x 10-7/hr.  The total
      amount of respirable material released in 24 hours is 3.59 L (0.9 gal). 
      A total of 1.91 L (0.5 gal) would be released during an 8-hour work
      shift.
.     Mitigated Transfer Pipeline Break - The mitigated transfer pipe break
      assumes that the initiating event is within the design basis and is
      considered to be Extremely Unlikely.  The scenario assumes that the leak
      is detected within 2 hour and would spill 101,000 L (27,000 gal) of
      waste to the ground surface.  Respirable material is released from the
      pool at a rate of 4.0 x 10-6/hr and from the saturated ground at a rate
      of 3.6 x 10-7/hr.  The total amount of respirable material released in
      24 hours is 1.24 L (0.33 gal).  A total of 0.659 L (0.174 gal) would be
      released during an 8-hour work shift.
F.3.2.2 Spray Releases
  - Spray releases and accidents are less likely in the
RCSTS diversion box(es) than in existing process pits since the diversion
boxes use welded stainless steel piping instead of jumpered steel piping. 
Also, the system design makes it less likely that aerosol will be sprayed
directly to the atmosphere.  However, since the RCSTS would operate at much
higher pressures than existing transfer piping, potential releases are
correspondingly larger.
Information on unmitigated and mitigated RCSTS spray releases and accidents
from Cross-Site Transfer System Preliminary Safety Analysis Report (WHC 1995c)
is discussed in the following paragraphs.
.     Unmitigated Spray Release - The unmitigated spray release accident
      assumes that a valve in a RCSTS diversion box fails creating a 3 cm
      (1.2 in) by 0.15 mm (0.006 in) crack.  The transfer system pressure is
      assumed to be 2,000 psig.  It is also assumed that there are no
      additional barriers to prevent release, that is, the diversion box is
      open to the sky.  Respirable material is assumed to be released at the
      rate of 0.231 L/s (0.06 gal/s) which, in an 8-hour release produces
      6,700 L (1,800 gal) of respirable material (WHC 1995c).  A release of
      this magnitude would be expected to have catastrophic consequences.  No
      frequency was provided for the scenario.  
      To assign an accident frequency estimate to the RCSTS unmitigated spray
      release, an event sequence was developed which reflects the unique
      design features of the RCSTS diversion boxes.  These features provide
      access for all routine maintenance and inspection functions through an
      access corridor with a 90-degree turn and doors at each end.  The lower
      door opens into a shield baffle within the diversion box and is entirely
      below grade.  This geometry eliminates the possibility of the release of
      a spray directly to the atmosphere via this route.  A route would exist
      if it were necessary to replace heavy equipment such as a pump.  A
      relatively small removable shield block located in the roof of the
      diversion box directly over the pump would need to be removed to allow
      use of a crane to remove and replace the defective component.  If the
      block were not replaced before operations resumed, a direct path to the
      atmosphere would exist and an unmitigated spray release could occur
      should a valve or weld subsequently fail.  
      The frequency that the shield block would need to be removed can be
      estimated from failure data for large pumps in a chemical environment
      (WHC 1995d).  The overall failure rate is estimated to be 6.0 x 10-5/hr
      with 8.5 percent of these failures being catastrophic.  Thus the
      frequency of a failure requiring replacement is 5.1 x 10-6/hr.  It is
      assumed that there is a 0.1 percent chance that the blocks would not be
      replaced before resuming operations.  The failure rate of a valve in an
      RCSTS diversion box (WHC 1995c) is 3.5 x 10-6/hr and there are
      approximately 12 valves in a diversion box.  Assuming 24-hour operation,
      the frequency of an RCSTS unmitigated spray release is 1.9 x 10-9/yr and
      not reasonably foreseeable.
.     Mitigated Spray Release - The mitigated spray release scenario differs
      from the unmitigated case in that it assumes that the diversion box is
      closed.  This requires that doors in the entry stairwell be closed, that
      the small cover block(s) be in place, and that a small penetration to
      allow connection of a portable exhauster be closed.
      It is assumed that the confined spray saturates the air inside the
      diversion box with vapor at a loading of 100 mg/m3 (6 x 10-6 lbs/ft3). 
      This saturated air is assumed to be forced out of the diversion box by
      the combination of the rise in humidity due to evaporation and the
      accumulation of bulk liquid in the box.  The estimated total release is
      0.0075 L (.002 gal) in the 8 hours assumed to elapse before the leak is
      detected.  Approximately 40 percent of this release occurs in the first
      20 seconds.  The frequency of this event for a RCSTS consisting of four
      diversion boxes and operating 643 hr/yr is 0.11/yr (WHC 1995c).  Current
      plans are to construct only one diversion box which reduce the frequency
      to 0.03/yr.  In either case, the mitigated spray scenario is an
      anticipated event.
      This scenario does not consider the presence of leak and radiation
      detectors which could limit the duration of the release; however, based
      on the modeling of evaporative release, they reduce the release only by
      about one-half.  On the non-conservative side, drawings (e.g., H-2-
      822231), (WHC 1995c) show a HEPA filter that appears to draw from the
      entry stairwell and exhaust into the diversion box.  The flow rate of
      this filter could not be found but could be considerably higher than the
      0.187 m3/min (6.6 ft3/min) assumed for the vapor release rate.

F.4 ABOVE-GROUND CROSS-SITE TRANSFER

This evaluation considers two options for above-ground cross-site transfer of
high-level tank wastes from the 200 West Area.  The first option is the use of
tanker trailer trucks.  Two tanker sizes are considered: 3,800 L (1,000 gal)
and 19,000 L (5,000 gal).  Accidents associated with the movement of loaded
tanker trailer trucks are discussed in Section F.4.1.  The second option for
above-ground cross-site transfer of high-level tank waste from the 200 West
Area is the use of 38,000 L (10,000 gal) rail tanker cars.  Accidents
associated with the movement of loaded rail tanker cars are discussed in
Section F.4.2.  Either of these above-ground transfer options would require
construction and operation of new HLW load and unload facilities in the 200
East and 200 West Areas to process the HLW in the tankers.  Accidents at these
facilities are discussed in Section F.4.3.

F.4.1 TANKER TRAILER TRUCKS

This section discusses accidents that could occur while using tanker trailer
trucks to transport of HLW between the 200 East and West Areas.  Two types of
tanker trailer trucks are considered.  The LR-56(H) Cask System is licensed
and operated in France as a Type B quantity package for radioactive liquids
and has a capacity of approximately 3,800 L (1,000 gal) (WHC 1994h).  The
second tanker trailer truck has a capacity of 19,000 L (5,000 gal).  No tanker
of this size currently exists for the transport of HLW; however, a shielded
19,000-L (5,000-gal) tank truck has been used to transport high activity LLW
at the Savannah River Site.  It is assumed that neither the LR-56(H) nor the
19,000-L (5,000-gal) tanker trailer truck would be licensed as Type B packages
for use in the United States.
The movement of vehicles carrying radioactive materials is more strictly
controlled on the Hanford Site than on public roadways.  This control
includes:
.     Speed restrictions - Vehicles transporting HLW are limited to 40 kmph
      (25 mph) under good conditions and 16 kmph (10 mph) under icy, snowy,
      and reduced visibility conditions.
.     Escorts required - Escorts accompany the vehicle to monitor road
      conditions, control local traffic, and control proximity of other
      vehicle to the transport vehicle.  When appropriate, roads would be
      closed.
This evaluation does not specifically address whether either of these tanker
trailer trucks meet equivalent safety requirements at the Hanford Site.  Such
a determination would be made based on a SARP.  A SARP has not been prepared
for either the LR-56(H) or 19,000-L (5,000-gal) package.  Packaging design
criteria have been developed for the slightly modified LR-56(H) planned for
use at Hanford (WHC 1994h). 
The following initiating events are postulated for potential releases during
truck transport of HLW on the Hanford Site:
.     In-transit punctures
.     Fire-induced breaches
.     Collisions and rollovers
.     Criticality.
The frequencies of these initiating events, the likelihood that they would
result in the release of package contents, and the quantity of material
released are discussed in the following sections.
F.4.1.1 In-Transit Punctures
 - Objects thrown up by passing vehicles,
propelled by wind or near-by explosions, or deliberately directed projectiles
could strike the tanker trailer truck during transit.  Both International
(IAEA Safety Series No. 6, Regulations for the Safe Transport of Radioactive
Material, 1985 Edition) and DOE regulations (DOE/RL Order 5480.3, Safety
Requirements for the Packaging and Transportation of Hazardous Materials,
Hazardous Substances, and Hazardous Wastes) contain the same requirement
regarding puncture of Type B packages.  The package must withstand without
failure a free drop through a distance of 1 m (40 in) onto the top end of a
vertical cylindrical mild steel bar mounted on an essentially unyielding
horizontal surface and  striking in a position for which maximum damage is
expected.
Although the French LR-56(H) met this requirement, a separate demonstration
would be required for Type B certification in the United States.  The ability
of the larger and yet undesigned 19,000 L (5,000 gal) tanker to meet this
requirement is unknown.  Certification is not required if the tankers are not
transported by public conveyance and if equivalent safety can be demonstrated
(DOE 1985).  The accident scenarios discussed in Section F.4.1.3 bound any
reasonably foreseeable puncture scenarios.
F.4.1.2 Fire Induced Breaching
 - A fire of sufficient energy and duration to
cause the breaching of an LR-56(H) Cask System or a 19,000-L (5,000-gal) HLW
package in the absence of the collisions and rollovers discussed in Section
F.4.1.3 is considered to be extremely unlikely.  Based on statistics for
trucks over 4,000 kg (8,500 lb)  operated on the Hanford Site, the frequency
of a random fire (one not associated with a collision or rollover) is 6.5 x
10-10/km (1.04 x 10-9/mi) (WHC 1993c).  The contribution of random truck fires
is considered in Section F.4.1.3.
F.4.1.3 Collisions and Rollovers
 - Collisions and rollovers could lead to
release of the contents of the LR-56(H) or 19,000-L (5,000-gal) tanker trailer
truck, particularly if a fire also occurred.  A previous analysis concluded
that only accidents involving uncontrolled fires and rollovers would result in
the release of radioactive materials from packages transported by truck.  The
frequencies of these types of accidents have been estimated from Hanford Site
accident report data for trucks with gross vehicle weights over 4,000 kg
(8,500 lb) (Wilson 1992, WHC 1993c) and are summarized in Table F-9.  The
total frequency of events that could result in release of radioactive
materials is 2.7 x 10-9/km (4.3 x 10-9/mi).  The frequency of truck accidents
in the State of Washington is 2.62 x 10-7/km (4.2 x 10-7/mi).  Based on data
presented in NUREG/CR-4829, Shipping Container Response to Severe Highway and
Railway Accident Conditions, a similar analysis of transportation of Hanford
radioactive materials concluded that only 0.6 percent of these accidents would
result in a release (WHC 1994i).  This corresponds to a release frequency of
2.5 x 10-9/mi.
Table F-9
Accident Frequencies for Trucks at the Hanford Site
Accident                                                         Frequency 
 Initiator                           Result                      (/mile)             (/kilometer) 
Random Fire                          Uncontrolled Fire           1.04 x 10-9         6.46 x 10-10 
Collision                            Uncontrolled Fire           6.27 x 10-11        3.90 x 10-11 
Rollover, Good Road                  Uncontrolled Fire           2.38 x 10-11        1.48 x 10-11 
Rollover, Harsh Road                 Breach, No Fire             3.10 x 10-9         1.93 x 10-9 
Rollover, Harsh Road                 Breach, Fire                3.77 x 10-11        2.34 x 10-11 
Total                                                            4.26 x 10-9         2.65 x 10-9
Source:  Wilson 1992 
Both sets of frequency data include radioactive material packages ranging from
strong tight containers to Type B fissile containers.  In the period 1971
through 1982, 45 Type B packages survived transportation accidents with no
package failure and no release of radioactive materials (SNL 1984).  Although
the trucks considered here would transport Type B quantities, the transport
packages cannot be assumed to meet Type B package requirements.
To estimate the frequency of accidents for the two tanker trailer truck
options, a total frequency of an accident resulting in release of any
radioactive material is assumed to be 4.3 x 10-9/mi, the more conservative of
the two estimates.  The distance between the SY and A Tank Farms, the assumed
locations of the HLW load and unload facilities, is 10.7 km (6.5 mi) (WHC
1995e).  Based on this distance, the frequency of an accident releasing any
radioactive material would be 2.8 x 10-8 per trip.
The quantity of material released is assumed to be a function of the severity
of the accident.  Fractional release frequencies of rail accidents (WHC 1993d)
are shown in Table F-10 and are considered to be applicable to truck
accidents.  Of those accidents resulting in any release, 27.9 percent release
less than 1 percent of the contents, 24.5 percent release 90 to 100 percent of
the contents.  No other release fraction interval accounts for more that 4
percent of the total release frequency.  The 100 percent release accident is
therefore used as the basis of evaluated tanker trailer truck accidents.  The
frequency of this accident is 6.8 x 10-9 per trip.
Table F-10
Fractional Release Frequencies for Rail Accidents
 
Percent Released                                    Frequency/mile 
 0.0001 -   0.99                                    6.70 x 10-9 
 1.00   -   9.999                                   2.39 x 10-10 
10      -  19.999                                   6.45 x 10-10 
20      -  29.999                                   7.09 x 10-10 
30      -  39.999                                   7.09 x 10-10 
40      -  49.999                                   6.45 x 10-10 
50      -  59.999                                   8.38 x 10-10 
60      -  69.999                                   5.80 x 10-10 
70      -  79.999                                   2.58 x 10-10 
80      -  89.999                                   7.74 x 10-10 
90      - 100                                       5.89 x 10-9 
Total                                               2.4 x 10-8
Source:  WHC 1993d, Appendix 6.4.
Table F-11 shows the total probability and quantity of respirable material
released during accidents in which 100 percent of the tanker contents is lost
for each of the types of high-level tank waste considered in this EIS.  The
amount of respirable material released is based on the assumption that the
entire contents are spilled on the ground and that the area remains uncovered
for 24 hours.  During the first hour, the spill forms a pool that releases
material at the rate of 4.0 x 10-6/hr.  The spill then sinks into the ground
but keeps the area wet.  During this phase, respirable radioactive material is
released at the rate of 3.6 x 10-7/hr.  Workers are assumed to be exposed for
one shift (8 hour).  The public is exposed until the spill area is covered.
F.4.1.4 Criticality
 - The LR-56(H) Cask System and 19,000-L (5,000-gal)
tanker trailer truck, and the contents allowed in them, would be required to
meet the subcriticality requirements of DOE/RL Order 5480.3 for hypothetical
accident conditions.  Analyses are required to demonstrate that criticality is
not a credible event.  Criticality analyses routinely use extremely
Table F-11
Summary of Maximum Accident Releases from Transport Vehicles
During Cross-Site Transfers
 
                              Frequency of                Exposure            Respirable 
Accident                      Complete Loss of            Duration            Volume Released 
Scenario                      Contents                    (hr)                (L) 
LR-56(H) Tank Breach          6.8 x 10-9/trip             On-site 1           0.0151 
   SWL                        2.9 x 10-5                       7              0.0095 
   102-SY Supernatant         4.7 x 10-6                                      0.0246 
   101-SY (1:1 Dilution)      1.5 x 10-5 
                              4.9 x 10-5 
                                                          Off-site 1          0.0151 
                                                               23             0.0313 
                                                                              0.0464 
5,000 Gal Tank Truck Breach   6.8 x 10-9/trip             On-site 1           0.0756 
   SWL                        5.7 x 10-6                       7              0.0476 
   102-SY Supernatant         9.4 x 10-7                                      0.123 
   101-SY (1:1 Dilution)      3.0 x 10-6 
                              9.6 x 10-6 
                                                          Off-site 1          0.0756 
                                                               23             0.156 
                                                                              0.232 
Rail Tank Breach              5.7 x 10-8/trip             On-site 1           0.152 
   SWL                        2.4 x 10-5                       7              0.0955 
   102-SY Supernatant         3.9 x 10-6                                      0.248 
   101-SY (1:1 Dilution)      1.3 x 10-5 
                              4.1 x 10-5 
                                                          Off-site 1          0.152 
                                                               23             0.314 
                                                                              0.466 
conservative bounding conditions (such as ideal moderation, perfect reflection
of neutrons at the boundaries, and optimum geometry.  Mechanisms that could
segregate fissionable isotopes from the rest of the liquid waste (e.g.,
settling, chemical or thermally induced precipitation out of solution,
unintended filtering effects) would be evaluated.  Administrative controls
would be established to limit the quantities of fissionable materials. 
Sampling would be performed as necessary to ensure that administrative
controls are being met.  
Hanford Site high-level tank wastes have been found to be highly subcritical
because of the relatively high concentrations of neutron absorbers to Pu in
the wastes (WHC 1994c).  Since it is very likely that the high-level tank
wastes that would be transported by tanker trailer truck would be highly
subcritical, no criticality accident scenarios have been developed.

F.4.2 RAIL TANK CARS

This section discusses accidents that could occur while using a 38,000-L
(10,000-gal) rail tanker car to transport high-level tank waste from the 200
West to the 200 East Area.  The tanker car has not been designed for HLW at
Hanford but is assumed to be a heavily-shielded, double-wall steel tank.  A
shielded 19,000-L (5,000-gal) rail tank car is used to transport high activity
LLW at the Savannah River Site.
This evaluation does not address whether this type of HLW transport package
can be designed or will meet Hanford equivalent safety requirements.  The
latter determination would be made based on a SARP.
The movement of rail cars carrying radioactive materials at the Hanford Site
is strictly controlled (WHC 1993d).  Controls include:
.     Train speed is limited to 6 kmph (4 mph) while coupling.
.     Speed is limited to maximum of 40 kmph (25 mph).  Speed is limited to
      16 kmph (10 mph) on paved road crossings, during icy or snowy
      conditions, and when visibility is limited. Speed is limited to 8 kmph
      (5 mph) on rail spurs.
.     Patrol blockages are established to stop traffic at paved road
      crossings.
.     At least one spacer car is required on either side of the HLW tank car.
.     At least one person in the locomotive cab must keep the cars under
      observation at all times.
These controls would reduce the likelihood and consequences of rail car
accidents.
The frequencies of these initiating events, the likelihood that they would
result in the release of container contents, and the quantity of material
released are discussed in the following sections.
The following initiating events are postulated for potential releases during
rail car transport of SWLs or 200 West Area facility wastes on the Hanford
Site:
.     In-transit punctures
.     Fire-induced breaches
.     Collisions and Derailments
.     Criticality.
F.4.2.1 In-Transit Punctures
 - In-transit punctures could conceivably occur
if a piece of broken rail were thrown up by the car wheels.  Due to the
limited train speeds, the energy of such an object would be low.  Track
maintenance and routine and pre-transfer track inspections would keep the
tracks clear of spikes and rail debris and, in general, greatly minimize the
likelihood of a puncture event.  A misaligned coupler with another rail car
could also conceivably cause a puncture, but with minimum coupling operations
and with the use of automatic hood-and-shelf type couplers such an event would
essentially be precluded.
F.4.2.2 Fire-Induced Breaches
- A fire of sufficient energy and duration to cause the breaching of a rail tank car designed to transport HLW is considered to be extremely unlikely if the fire is not related to derailment or a collision. Track crews currently spray weed killer at least once every 2 years in a 3 m (10 ft) swath on either side of the centerline of the tracks, thus decreasing the possibility of a vegetation fire next to the tracks. Loose tumbleweeds are removed as necessary. To minimize the potential impact from the diesel fuel of the locomotive catching on fire at least one railroad spacing car would be placed between the engine and the HLW rail tank car.
F.4.2.3 Collisions and Derailments
- Collisions or derailments could cause loss of the integrity of the HLW rail tanker car. In view of speed limitations and requirements for blockades at road crossings only, collisions involving derailments or fires are considered to be credible initiating events. Derailment is considered to be the most likely of the potential initiating events (WHC 1993d). The SARP for the rail tank cars used to transport LLW at the Hanford Site includes frequencies and release fractions. These data are shown in Table F-11 and are based on national rail statistics with adjustments to reflect the more controlled and safer transport conditions within the Hanford Site. The total frequency of a rail accident that would result in any release of radioactive materials is 1.5 x 10-8/km (2.4 x 10-8/mi). The entire contents are lost with a frequency of 3.7 x 10-9/km (5.9 x 10-9/mi). The distance by rail between the A and SY Tank Farms, the assumed locations of the HLW load and unload facilities, is 15.5 km (9.7 mi). The frequency of any accidental release 2.3 x 10-7/trip and 5.7 x 10-8/trip for a total loss of contents. Table F-11 shows the probability of an accident involving complete loss of the rail tanker car contents for each type of high-level tank waste considered in this EIS and the amount of respirable material that would be released. The amount of respirable material released is based on the assumption that the entire contents are spilled on the ground and that the area remains uncovered for 24 hours. During the first hour, the spill forms a pool that releases material at the rate of 4.0 x 10-6/hr. The spill then sinks into the ground but keeps the area wet. During this phase, respirable radioactive material is released at the rate of 3.6 x 10-7/hr. Workers are assumed to be exposed for one shift (8 hours). The public is exposed until the spill area is covered.
F.4.2.4 Criticality
 - The HLW rail tanker car and its contents would be
required to meet the subcriticality requirements or DOE/RL Order 5480.3 for
hypothetical accident conditions.  Analyses are required to demonstrate that
criticality is not a credible event.  Criticality analyses routinely use
extremely conservative bounding conditions (such as ideal moderation, perfect
reflection of neutrons at the boundaries and optimum geometry).  Mechanisms
that could segregate fissionable isotopes from the rest of the liquid waste
(e.g., settling, chemical or thermally induced precipitation out of solution,
unintended filtering effects) would be evaluated.  Administrative controls
would be established to limit the quantities of fissionable materials. 
Sampling would be performed as necessary to ensure that administrative
controls are being met.  
Hanford Site high-level tank wastes have been found to be highly subcritical
because of the relatively high concentrations of neutron absorbers to Pu in
the wastes (WHC 1994c).  Since it is very likely that the high-level tank
waste transported in the HLW rail tank car would be highly subcritical, no
criticality accident scenarios are developed.

F.4.3 LOAD AND UNLOAD FACILITIES

High-level waste load and unload facilities would be designed to protect both
workers and the general public from the hazards associated with the loading
and unloading of the tanker trailer trucks and rail tank cars.  Design
criteria for a load and unload facility would comply with the following DOE
orders:  
.     DOE Order 6430.1A, General Design Criteria 
.     DOE Order 5820.2A, Radioactive Waste Management 
.     DOE Order 5480.28, Natural Phenomena Hazards Mitigation.  
Compliance with these DOE orders assures that adequate accident related
preventive and mitigative measures would be considered during the design of
the load and unload facilities.  Furthermore, such a facility would not be
allowed to begin operations until a Final SAR, prepared in accordance with the
extensive requirements of DOE Order 5480.23, Nuclear Safety Analysis Reports,
has been approved by the appropriate authorities.
The load and unload facilities would accommodate rail tanker cars, tanker
trailer trucks, or both depending on the option selected.  The facility would
be similar in concept to the existing 204-AR facility for unloading of low-
level waste but would differ considerably in design and operation to
accommodate handling of HLW liquids.  Some of the features that would
distinguish the HLW load and unload facilities from the 204-AR facility
include (WHC 1993c):  
.     Placement of pumps and valves in shielded cells equipped with remotely
      operated controls
.     Drive-through bays to eliminate backing of transport vehicles
.     Remotely-operated fill/drain lines and vent lines
.     Heavily-shielded bay access doors
.     Differential pressure zones in the HVAC system to isolate areas based on
      expected level of contamination with dual stage HEPA filtration in
      contaminated zones.
Three categories of initiating events are often examined in the performance of
an accident safety analysis:  operational events, natural phenomena, and
external events.  Each category of initiating event is capable of resulting in
different types of accidents (e.g., fires and spills).  Accident scenarios
induced by seismic events and high winds or tornadoes have often received the
most attention in the performance of safety analyses.  External events include
the crashing of aircraft and energetic (i.e., accident) events at facilities
located near the facility being evaluated.  An examination of transportation
routes and facilities around likely potential sites for an HLW load and unload
facility in the 200 Areas revealed no sources that could provide the necessary
energy to cause an accident scenario more severe than those postulated in the
following sections.  Though not methodically evaluated, an accident at an HLW
load and unload facility induced by nearby transportation routes and/or
facilities is considered to be extremely unlikely.
Accident analyses specific to the HLW load and unload facilities are not yet
available.  For purposes of this evaluation, scenarios for the following
accident categories are considered:
.     Spills
.     Spray releases
.     Fires.
The frequency of occurrence and quantities of respirable material released
during these accident events are summarized in Table F-12.  These accident
categories are further discussed in Sections F.4.3.1, F.4.3.2, and F.4.3.3,
respectively.  Other accident scenarios could be postulated, but their
consequences would likely be relatively small and limited to local
contamination and to in-facility workers.  Examples of such accidents include 
Table F-12
Summary of Accident Releases for the HLW Load and Unload Facilities
 
                                                   Exposure            Respirable 
Accident               Frequency/100               Duration            Volume 
Scenario               Tankers                     (hr)                (L) 
Loading/Unloading      Anticipated to              On-site 0.5         0.00568 
Spill                  Unlikely 
                                                   Off-site 0.5        0.00568 
LR-56(H) Earthquake    3.2 x 10-5                  On-site 8           2.53 
Breach                 Extremely 
                       Unlikely 
                                                   Off-site 12         3.79 
5,000 Gal Tank Truck   3.2 x 10-5                  On-site 8           12.6 
Earthquake Breach      Extremely 
                       Unlikely 
                                                   Off-site 12         18.9 
Rail Car Tank          3.2 x 10-5                  On-site 8           25.2 
Earthquake Breach      Extremely 
                       Unlikely 
                                                   Off-site 12         37.9 
Source:  WHC 1991 
overflow of a catch tank located in a pit, containment breach during changeout
of a HEPA filter, and loss of off-site power (LOOP).  Regarding LOOP, a
standby generator would be provided to power key loads in the event of a LOOP. 
If the standby generator also failed, then an uninterruptible power supply
would provide power to essential items such as emergency lights and fire
monitoring and alarm components.  LOOP and failure of the standby generator
would result in loss of the differential pressure zones previously discussed. 
F.4.3.1 Spills
 - Various hardware failures or human errors could lead to a
spill within the HLW load and unload facilities.  Leaks could occur in pipes,
valves, pumps, and connectors due to mechanical failure or human error. 
Holding tanks, catch tanks, or the transport tanker could fail or be
overfilled.  A BDBE could also cause spills, either by damaging facility
components or by rupture of a loaded transport vehicle.  Small leaks up to
38 L (10 gal) are categorized (WHC 1994j) as anticipated events, and larger
spills up to 1,900 L (500 gal) are categorized as unlikely.  A DBE (0.25 g)
has a frequency of 4 x 10-4 to 1 x 10-3/yr (WHC 1991). Frequencies and released
quantities of waste are shown in Table F-12.
The safety assessment for the 204-AR facility considered a spill during
filling of a tank car (WHC 1991).  It was assumed that a gasket failed during
filling at 757 L/min (200 gpm) and 10 percent of the flow spilled to the floor
over a 30-minute period.  The frequency of the spill was estimated at 2.7 x
10-2/yr based on a failure rate of 3 x 10-6/hr for each of 23 gaskets in a
facility requiring 4 hours to fill each of 100 rail cars.  Although a
quantitative estimate cannot be made without design information, it is
reasonable to expect that the frequency would be less at the HLW load and
unload facilities.  It was assumed that 0.1 percent of the spill became
airborne and that each stage of a two-stage HEPA filter removed 99.95 percent
of the material.  The resulting quantity of respirable material released is
0.00568 L (0.0015 gal) with a corresponding frequency of anticipated to
unlikely.  The monitoring and alarm systems common to facilities of this type
at the Hanford Site would be expected to reduce both the frequency and
consequences of this spill.
An earthquake-induced spill was analyzed for the 204-AR facility (WHC 1991). 
The frequency of the DBE was taken as 7 x 10-4/yr and it was assumed that 100
tankers per year were processed at the rate of 4 hour/tanker.  The frequency
of the accident is therefore 3.2 x 10-5/yr.  It was assumed that the entire
contents of the transport vehicle were spilled to the ground and not covered
for 12 hours.  During this time, 0.001 of the spill was assumed to become
airborne.  The corresponding amounts of respirable liquid released from each
of the different transport vehicles is shown in Table F-12.  The frequencies
assume 100 tankers/year, 4 hours per tanker regardless of vehicle capacity.
F.4.3.2 Spray Releases
 - The same mechanisms that cause leakage can also
cause spray releases (e.g., failure of pipes, valves, pumps, and connections
between them).  A spray leak is an anticipated event.  The frequency and
magnitude of any resultant release is difficult to assess without design
information.  The magnitude of the release would probably be less than those
for mitigated spray leaks postulated for other proposed facilities such as the
RCSTS and NTF.  The frequencies could be somewhat higher since new connections
must be made each time a vehicle is loaded or unloaded.  Spray releases at the
HLW load and unload facilities are considered to be bounded by the spill
scenario discussed in Section F.4.3.1 due to the large fractional release
assumed for respirable material.
F.4.3.3 Fires
 - Mechanisms for a fire at an HLW load and unload facility are
extremely limited.  There would be very little combustible material in the
load/unload bay, and throughout the facility in general.  The likelihood of
electrical fires would be minimized by the use of industry accepted electrical
system design standards, which include the use of overcurrent and short
circuit protection devices.  Further electrical fires, with no significant
fuel supply, are not significant.  Lightning protection equipment would also
be installed in accordance with applicable industry standards.  An aircraft
crash at an HLW load and unload facility could lead to a fire scenario. 
However, the total frequency of aircraft accidents (due to all types of
aircraft) at the postulated NTF in the 200 Areas is less than 1 x 10-7/yr (WHC
1994b).  Accordingly, accidents in the HLW load and unload facilities due to
fires are considered to be bounded by the transportation accidents considered
in Section F.3.

APPENDIX F REFERENCES

ARH, 1977, Exothermic Potential of Sodium Nitrate Saltcake, Beitel, G.A., ARH-
LD-163, Atlantic Richfield Hanford Company, Richland, WA 
ARH, 1976, Chemical Stability of Salt Cake in the Presence of Organic
Materials, Beitel, G.A., ARH-LD-119, Atlantic Richfield Hanford Company,
Richland, WA
Cloud, 1993, Position Paper, Project W-236A Multifunction Waste Tank Facility
Waste Storage Tank Heat Removal Systems, Kaiser Engineers Hanford, Richland,
WA
DOE, 1995, Environmental Assessment Tank 241-C-106 Past-Practice Sluicing
Waste Retrieval, Hanford Site, Richland, WA, DOE/EA-0944, February 1995,
United States Department of Energy, Richland, WA
DOE, 1994, Environmental Assessment, Waste Tank Safety Program, DOE/EA-0915,
U.S. Department of Energy, Hanford Site, Richland, WA 
DOE, 1993, Recommended Values and Technical Bases for Airborne Release
Fractions (ARFs), Airborne Release Rates (ARRs), and Respirable Fractions
(RFs) at DOE Non-Reactor Nuclear Facilities, DOE Handbook, DOE-HDBK-0013-93,
July 1993, U.S. Department of Energy, Washington D.C.
DOE, 1992a, Environmental Assessment for Proposed Pump Mixing Operations to
Mitigate Episodic Gas Releases in Tank 241-SY-101, Hanford Site, Richland,
Washington, DOE/EA-0803, U.S. Department of Energy, Washington, D.C. 
DOE, 1992b, An Environmental Assessment for Proposed Pump Mixing Operations to
Mitigate Episodic Gas Releases in Tank 241-101-SY.  Hanford Site, Richland,
Washington, DOE/EA/0803, U.S., Department of Energy, Washington, D.C., August
1992 
DOE, 1987, Final Environmental Impact Statement, Disposal of Hanford Defense
High-Level, Transuranic and Tank Wastes, Hanford Site, Richland Washington,
DOE/EIS-0113, U.S. Department of Energy, Washington, D.C.
DOE, 1985, Safety Requirements for the Packaging and Transportation of
Hazardous Materials, Hazardous Substances, and Hazardous Wastes, DOE/RL Order
5480.3, July 9, 1985 
KEHC, 1993, Project W-030 Process Flow Diagrams, Stack Elevation and Civil
Plot Plan, Kaiser Engineers Hanford Company for the U.S. Department of Energy,
Richland Field Office, Richland, WA
LANL, 1994, Los Alamos National Laboratory, A Safety Assessment for Proposed
Pump Mixing Operational to Mitigate Episodic Gas Release in Tank 241-SY-101,
LA-UR-92, Rev. 8 (DRAFT)
PNL, 1994a, Mitigation of Tank 241-SY-101 by Pump Mixing: Results of Full-
Scale Testing PNL-9959/UC-510, Pacific Northwest Laboratory 
PNL, 1994b, Mitigation of Tank 241-SY-101 by Pump Mixing: Results of Testing
Phases A and B, PNL-9423, UC-510, Pacific Northwest Laboratory, Richland, WA  
SNL, 1984, The Transportation of Nuclear Materials, SAND84-0062, TTC-0471,
Unlimited Release, UC-71, T.A. Wolff, December, Sandia National Laboratories,
Albuquerque, NM 
WHC, 1995a, Safety Assessment, Initial Tank Retrieval Systems, Project W-211,
WHC-SD-W211-SAD-001, Rev. A, June 1, 1995 by R.J. Kidder
WHC, 1995b, Human Reliability Analysis of Backhoe and Seismi Events Involving
The Cross-Site Transfer Line (Internal Memo, OM640-sel-95005), Westinghouse
Hanford Company, Richland, WA 
WHC, 1995c, Cross Site Transfer System Preliminary Safety Analysis Report,
WHC-SD-W058-PSAR-001 Rev. 1, (DRAFT) Westinghouse Hanford Company, Richland,
WA 
WHC, 1995d, Multi-Function Waste Tank Facility Path Forward Engineering
Analysis Technical Task 3.6, Estimate of Operations Risk in the 200 West Area,
WHC-SD-W236A-ES-014, Revision OA, G.A. Coles, Westinghouse Hanford Company,
Richland, WA
WHC, 1995e, Replacement of the Cross Site Transfer System Liquid Waste
Transport Alternatives Evaluation, Project W-058, WHC-SD-W058-TA-001, Revision
O., D.V.Vo, E.M. Epperson, Westinghouse Hanford Company, Richland, WA 
WHC, 1994a, Leach, D. S., 1994, Multi-Function Waste Tank Facility -
Preliminary Safety Analysis Report, WHC-SD-W236A-PSAR-001, Rev. A, Vol. II,
SEAC Review Issue Draft, Westinghouse Hanford Company, Richland, WA
WHC, 1994b, Supplemental PSAR Analysis, WHC-SD-W236A-ANAL-002, August 1994,
Additional Analysis Related to the MWTF
WHC, 1994c, High-level Waste Tank Subcritically Safety Assessment, Braun,
D.J., et al., WHC-SD-WMSARR-003, Rev. 0, Westinghouse Hanford Company,
Richland, WA 
WHC, 1994d, Ferrocyanide Safety Program: Safety Criteria for Ferrocyanide
Watch List Tanks, WHC-EP-0691, UC-600, Westinghouse Hanford Company, Richland,
WA 
WHC, 1994e, Preliminary Safety Evaluation for 241-C-106 Waste Retrieval,
Project W-320, J.C.Conner, WHC-SD-WM-PSE-010, Rev. 2. October 1994,
Westinghouse Hanford Company, Richland, WA
WHC, 1994f, Safety Analysis; Tank Farms Waste Transfer System Leaks, Breaks,
and Spray Releases, WHC-SD-WM-SARR-005, Rev 0, July 28, 1994, Westinghouse
Hanford Company, Richland, WA 
WHC, 1994g, Leach, D. S., 1994, Multi-Function Waste Tank Facility -
Preliminary Safety Analysis Report, WHC-SD-W236A-PSAR-001, Rev. A, Vol. I &
II, SEAC Review Issue Draft, Westinghouse Hanford Company, Richland, WA
WHC, 1994h, Packaging Design Criteria for the LR-56(H) Cask System, WHC-SD-TP-
PDC-021, Rev 0, EDT 142720, March 15, 1994, Westinghouse Hanford Company,
Richland, WA 
WHC, 1994i, Transportation Impact Analysis for the Tank Waste Remediation
System Environmental Impact Statement Proposed Alternatives, WHC-SD-TP-RPT-
0161, Draft, Rev A, Westinghouse Hanford Company, Richland, WA 
WHC, 1994j, Hazard and Accident Analysis (Interim Chapter 3), WHC-SD-WM-SAR-
065, Rev 0, July 1994, Westinghouse Hanford Company, Richland, WA 
WHC, 1993a, Radionuclide and Chemical Inventories for the Double Shell Tanks,
Oscarson, E. E. and Tusler, L.A., WHC-SD-WM-TI-543, July 1993
WHC, 1993b, Interim Safety Basis Topical Report Flammable Gas Waste Tanks,
Section 5.3 of WHC-SD-WM-ISB-001, Vol. 1, Rev. 0, Westinghouse Hanford
Company, Richland, WA 
WHC, 1993c, Pilot Plant Hot Test Facility Siting Study, WHC-SD-WM-TA-143,
Draft, Rev 0, Westinghouse Hanford Company, Richland, WA
WHC, 1993d, SAR for Packaging Railroad Liquid Waste Tank Car, WHC-SD-RE-SAP-
013, Rev 5, Westinghouse Hanford Company, Richland, WA
WHC, 1992, Safety Study of Interim Stabilization of Non-Watchlist Single Shell
Tanks, SD-WM-RPT-048, Revision 0, Westinghouse Hanford Company, Richland, WA 
WHC, 1991, SAR for the 204-AR Waste Unloading Facility, WHC-SD-WM-SAR-040, Rev
0, Westinghouse Hanford Company, Richland, WA
WHC, 1989, Operational Safety Analysis Report, Cross-Country Waste Transfer
System, SD-WM-SAR-039, Rev 0, Westinghouse Hanford Company, Richland, WA 
WHC, 1988, Nonreactor Facility Safety Analysis Manual, Safety, Quality
Assurance and Security, WHC-CM-4-46, Level II, Westinghouse Hanford Company,
Richland, WA
Wilson, G.P., 1992, Above Ground Transportation System, Memorandum from G.P.
Wilson to O.S. Wang, May 12, 1992

Previous PageTable Of ContentsList Of FiguresList Of TablesNext Page



NEWSLETTER
Join the GlobalSecurity.org mailing list