UNITED24 - Make a charitable donation in support of Ukraine!

Weapons of Mass Destruction (WMD)

Previous PageTable Of ContentsList Of FiguresList Of TablesNext Page

APPENDIX D MITIGATION FOR LOST HABITAT

TABLE OF CONTENTS

       MITIGATION FOR LOST HABITAT                                            D-1
             D.1  MITIGATION STRATEGY                                         D-1
             D.2  HANFORD SITE MITIGATION STRATEGY                            D-2
             D.3  MITIGATION PLANS FOR THE PREFERRED ALTERNATIVE              D-2

APPENDIX D MITIGATION FOR LOST HABITAT

This appendix addresses the proposed mitigation strategy and its relationship
to the site-wide mitigation program.  Actions proposed as part of the
alternatives would require clearing shrub-steppe habitat to construct new
facilities.  The part of that habitat dominated by mature sagebrush has been
designated as a priority habitat by the State of Washington because of its
importance to wildlife and because it is becoming relatively scarce in the
state.  Therefore, the loss of substantial acreage of this habitat type is an
issue of concern for any alternative.  Compensatory mitigation for unavoidable
losses of this habitat, in the form of restored, enhanced, or newly
established similar habitat, is planned.
The following sections discuss mitigation strategy in general, mitigation
strategy for the Hanford site, and mitigation plans for the preferred
alternative.  

D.1 MITIGATION STRATEGY

Such a mitigation requirement assumes that the restoration of sagebrush
habitat or creation of favorable conditions for it on disturbed sites is
feasible.  Revegetation projects (including some on the Hanford Site) have
successfully planted and established sagebrush.  The possible approaches to
mitigation range from seeding to planting nursery stock to transplanting
mature shrubs.  While each strategy has its advantages, each also has
disadvantages.  Seeding is the cheapest method for revegetating barren soil,
but the length of time to achieve mature sagebrush is likely to be years, even
decades.  There are also many factors that can interfere with the success of a
seeding effort, and some sites are less amenable to this approach than others. 
Planting nursery stock offers several advantages, including a higher
likelihood of success, adaptability to a wide range of sites, and a slightly
shorter time from planting to maturity than seeding.  The costs are higher,
and it may be necessary or desirable to establish a nursery nearby to optimize
survival and use local genetic stock.  Transplanting mature or near-mature
plants from sites scheduled for construction would probably be the most
expensive on a unit basis, and the techniques may be least proven; but the
rewards could be substantial.  Using this transplanting approach, it should be
possible to establish habitat for wildlife species that require mature shrubs
as a key component of the habitat.  Transplanting would avoid the gap between
the time of habitat loss and the time when replacement habitat is useable by a
species of concern for which it is critical such as the loggerhead shrike.

D.2 HANFORD SITE MITIGATION STRATEGY

A Hanford site-wide mitigation strategy is being discussed by representatives
of the DOE, their contractors, the WDFW, the USFWS, and other members of the
Natural Resource Trustees Council.  The development of the strategy is in a
formative stage, with concepts and procedures for agreements being the initial
focus.
Under a site-wide mitigation strategy, there should be a substantial savings
of time to all parties because the negotiations of mitigation details could be
done once, rather than repeatedly for each separate project.  The results
should be more predictable and success more readily achievable, because each
project would contribute an increment to a comprehensive study of the critical
information needed to assure success rather than have to rely on a more
limited study that would be economically feasible for one project.  The site-
wide strategy would also facilitate a broader landscape and ecosystem approach
to mitigation than would be expected with separate project mitigation. 
Perhaps the most significant benefit would be to the habitat and the species
that use it, because efforts would be focused on creating, enhancing, or
revegetating habitat rather than on negotiations.

D.3 MITIGATION PLANS FOR THE PREFERRED ALTERNATIVE

Since a site-wide mitigation strategy has not yet been adopted and
implemented, the mitigation for the clearing of mature sagebrush habitat for
the RCSTS would necessarily be a stand-alone program.  The concepts, developed
more fully in the MAP, generally follow the mitigation approach described in
the Draft EIS and apply the key elements of the draft site-wide mitigation
strategy.  The following are key components of the mitigation strategy:
.       Avoidance and minimization of impact through siting
.       Salvage and transplant
.       Restoration of temporarily disturbed habitat
.       Compensation for lost habitat.
Each of these components are discussed in the following paragraphs.
Measures to avoid and minimize impacts have been applied to the extent
feasible.  The anticipated loss of mature sagebrush has been reduced
substantially since the Draft EIS was published.  The construction corridor
for the RCSTS would incorporate previously cleared roadways to reduce the
width of the construction corridor from a nominal 30.5 m (100 ft) to 26 m (85
ft).  Another means of minimizing the impact is that mature shrubs would be
salvaged from the area to be cleared and planted in the enhancement area. 
Restoration of temporarily disturbed habitat could be an important feature of
the mitigation program.  It is anticipated that an average of 23 m (75 ft) of
the RCSTS construction corridor could be restored, if there will be no need
for further disturbance associated with the use of the RCSTS. However, if
decommissioning of the RCSTS required removal of the pipes, the area would be
disturbed again at the end of the useful life of the facility.  About 8 ha (20
acres) of cleared sagebrush habitat could be restored in place and provide
good potential habitat if the pipes can be left in place when decommissioned. 
In addition, about 0.6 ha (1.5 acres) of the corridor, now occupied by
cheatgrass/rabbitbrush habitat, could be planted with sagebrush.  The
remainder must be kept clear of vegetation to prevent deep-rooted shrubs from
drawing up contaminated material in the unlikely event a leak should occur. 
Since it is assumed that decommissioning of the RCSTS would require pipe
removal, the method of restoration would be to add sagebrush seeds to a seed
mixture of native grasses that would be sown on the disturbed areas.  This
combination will help prevent invasive plant species from excluding desirable
native species.  If tanks are built as part of the new storage alternative,
some of the area disturbed for construction could also be similarly restored. 
Compensation for lost habitat values would be accomplished by enhancing the
habitat value of an area west of the 200 West Area (see Figure 5-2) that has
had no sagebrush component for many years due to past fires, but has the other
components of a mature habitat (e.g., understory species).  A baseline
characterization of the proposed compensation area is included in the MAP.  
The compensation site area has also been surveyed for cultural resources to
make sure the mitigation action would not affect cultural resources. 
Enhancement would be through restoration of the shrubs in a selected area of
habitat.  Compensation for lost habitat value (for up to 50 years) is to be
done at a ratio of 3 ha (7.4 acres) of replacement for each 1 ha (2.5 acres)
lost.
Under the preferred alternative, 9 ha (23 acres) of mature sagebrush would be
lost initially.  As described in Section 5, at a ratio of 3:1, 28 ha (69
acres) would be replaced for this project.  Of that, 9 ha (23 acres) would
have mature sagebrush plants transplanted from the RCSTS corridor (salvaged
prior to clearing of the corridor).  These transplants would be placed at a
density of 50 per ha (20 per acre) and will be supplemented with tubeling
nursery stock at a density of 500 per ha (200 per acre).  The remaining 18 ha
(46 acres) would be planted with tubelings at a density of 750 per ha (300 per
acre).  If the new storage alternative is selected, the compensation would be
done at the same ratio by expanding the proposed compensation area.  
To assure that the concerns of tribes and natural resource agencies are
considered, the detailed mitigation plans for inclusion in the MAP are being
prepared in consultation with interested members of the Natural Resource
Trustees Council.  Since potentially significant cultural resource sites have
been identified in the 560 ha (1,300 acre), a specific plan for avoidance of
these sites will be included in the MAP.  Procedures to follow in the event of
encountering other cultural resource sites will also be specified.  Tribes and
natural resource agencies will be given the opportunity to participate in
mitigation activities to make sure that their concerns are adequately
considered during implementation of the MAP.

Previous PageTable Of ContentsList Of FiguresList Of TablesNext Page



NEWSLETTER
Join the GlobalSecurity.org mailing list