Lublin class Project 767 transport and mine ships
Ship |
yard number |
Laid down position of the keel |
Launched | Transfer to Navy | Commissioned |
Flotilla |
ORP |
767/1 | 08.12.1987 | 12.07.1988 | 28.08.1989 | 12 October 1989 | 8th Coast Defence Flotilla Swinoujscie |
ORP |
767/2 | 08.06.1988 | 27.12.1988 | 07.12.1989 | 23 Febuary 1990 | 8th Coast Defence Flotilla Swinoujscie |
ORP |
767/3 | 18.08.1988 | 07.03.1989 | 09.05.1990 | 27 June 1990 | 8th Coast Defence Flotilla Swinoujscie |
ORP |
767/4 | 22.05.1989 | 05.01.1990 | 19.12.1990 | 8 March 1991 | 8th Coast Defence Flotilla Swinoujscie |
ORP |
767/5 | 21.08.1989 | 08.06.1990 | 28.03.1991 | 24 May 1991 | 8th Coast Defence Flotilla Swinoujscie |
767/ 6 | Cancelled 1989 |
|||||
767/ 7 | Cancelled 1989 |
|||||
767/ 8 | Cancelled 1989 |
|||||
767/ 9 | Cancelled 1989 |
|||||
767/ 10 | Cancelled 1989 |
|||||
767/ 11 | Cancelled 1989 |
|||||
767/ 12 | Cancelled 1989 |