EXECUTION E-DATE TIMELINES
365 - DAY TIMELINE (CONT) |
---|
TIMELINE | ACTIVITY/EVENT |
E-28
- Stop forecasting training ammunition.
- Coordinate closure of Battalion Aid Station (BAS). Supporting TMC provides sick call support upon closure of unit's BAS.
- Transfer medical records. Transfer unit's remaining medical records to the supporting TMC.
E-25
- Notify unit of automation transfer instructions.
E-2l
- Coordinate date for copier turn in.
- Inventory DEH property in the BAS and turn in.
- Turn in BAS medical equipment hand receipted from a TMC.
- Turn in sick call medical supplies to the supporting TMC.
E-18
- Clear all CDE and related hazardous waste.
- Purge hard drives and reload software.
E-l5
- Unit COMSEC custodian completes turn-in of all COMSEC material on account to the DCOR.
- Complete turn-in on all MTOE/CTA equipment.
- Complete lateral transfers/turn-ins on all MTOE/CTA equipment.
- Cease all requisitioning of Class II, III(P), and IV.
- Modify or cancel all duE-ins for all supply classes.
- Notify FSB/MSB of last parts pickup.
- Cease PLL operations.
- Use/turn in all excess Class IX.
- Inventory, secure, and laterally transfer ASLs to the MSB. (MSB to ESU as applicable.)
- Cease logistics reporting of ESU transfers. Continue reporting lateral transfer actions.
- Ensure Class II (OCIE) is on property book turn-in to CIF.
- Transfer personal security information (PSI) and accreditation documentation to G2.
- Complete all required SCI debriefings.
- Turn in TSC long-term loan equipment and clear and receipt(s).
- Transfer automation equipment to gaining unit or staff.
E-10
- Issue official letter of closing to inactivating unit's COMSEC subaccount.
- Clear all organizational subhand receipts.
- Ensure transfer of classified holdings are complete and inform G2.
- Complete all lateral transfers.
E-7
- Complete preparation of relief from accountability documents.
- Send invitations to media for Inactivation Ceremony.
E-5
- Turn in final promotion board results.
- Complete final C-27 review.
E-5
- Turn in installation property to IPBO.
- Close unit's SSSC account.
- Transfer supply records to ESU.
- Turn in TSC short-term loan equipment and close account(s)
- Notify DAMO that transfer is completed.
- Turn in unit and regimental memorabilia.
E-4
- Notify corps installation post office of impending closure of mail room.
E-3
- Hand receipt holder finish final DEH TI of real property; clear and sign over buildings to DEH.
E-2
- Turn in barracks furniture (DEH).
E-1
- Give one copy of each soldier's reassignment orders to CIF.
- Last day for delivery of personal and official mail. Final closure of mail room.
- Notify DAMO RFADs are complete.
- Receive lateral transfer instructions.
E-Date
- Turn in final C-27 to PSC.
- Complete all property accountability adjustments IAW AR 735-5.
- Change unit's DODAAC ship to address to ESU.
- Hold Inactivation Ceremony.
- Media visits Inactivation Ceremony (PAO escort).
E+5
- Report all property accountability adjustment actions to ACofS, G4.
E+25+28
- Purge hard drives and reload software if applicable.
E+28
- Prepare residual support equipment for transfer.
E+30
- Delete unit's UIC.
E+60
- Final AAR submitted to higher HQ and Center for Army Lessons Learned.
180 - DAY TIMELINE |
---|
TIMELINE | ACTIVITY/EVENT |
E-180
- MSC/Separate Bn S2 submit milestone list to G2.
- Plan and coordinate augmentation of transportation assets for inactivating unit.
- Submit. inactivation plan to Chief of Inactivation Task Force.
E-l45
- Coordinate intelligence/security actions.
E-120
- Brief ADC on lnactivation Plan.
- Ten-percent stabilization requests submitted.
- Submit unit inactivation milestones to G2.
- Inventory 100-percent CDE.
- Wipe-test M8A1 Chemical Agent Alarms.
- Requisition Class II, III(P) and IV needed for inactivation.
- Begin use of project/fund codes and demand code N on requisitions related to inactivation.
E-105
- Key leaders receive ESU inbrief.
E-100
- Coordinate to effect all milestones.
- Conduct final coordination for intelligence/security actions/unresolved issues.
D-90
- Cut off all but critical gains; future gains managed by exception.
- Complete Personnel Data Worksheets; submit to G1 after chain-of-command review/establishment of proposed availability dates.
- Technically inspect (2404) CDE.
- Schedule radio meter calibration.
- Notify DPBO of any due-ins no longer needed.
- Verify all MTOE property is on hand, on valid requisition, or laterally transferred to another unit.
- Verify all components are on hand or on a shortage annex with a valid requisition. (Seventy percent of components on hand)
- Set up special Army Oil Analysis Program schedule.
D-90
- Inventory and inspect Class VIII. Conduct 100-percent inventory and MES and identify excesses. Turn in equipment requiring repair to Bio-Medical Maintenance, DMSO.
- Conduct final unit QTB.
- Complete crew-served weapons qualification.
- Set up appointment for turn-in of TSC equipment.
E-90
- Begin 100-percent inventory of TSC property On hand receipts.
- Conduct assistance visit. Provide unit with generic automation asset listing.
- Submit request for transfer of records.
- Start DOL Inspection Team initial TIs.
E-80
- Turn in unserviceable CDE.
- Turn in CDE hazardous material/waste.
E-75
- Conduct inventory of automation assets. INCLUDES ADMINISTRATIVE AND TACTICAL AUTOMATION!!