May 2002 Excerpt
In-Service
Support Offered
for Prototype Mast Aboard USS Radford
By Leslie Spaulding
PHILADELPHIA
AND WEST BETHESDADuring this past winter, Carderock Division personnel
upgraded portions of the prototype Advanced Enclosed Mast Sensor (AEM/S) System
aboard USS Radford (DD 968). The AEM/S mast design has paved the way
for the composite mast on LPD 17 Class, as well as efforts to install a composite
helicopter hangar and composite remote minehunting system (RMS) enclosure
on the DDG 51 Class.
This work involved upgrading the masts ladder access and fall protection
systems to meet Navy standards and INSURV inspection criteria. Also the work
accomplished addressed overheating issues with the main radar, and designing
and installing a composite foundation that allowed for the relocation of the
INMARSAT antenna and the new installation of the ROS Fire Control camera.
Ladders
The USS Radford AEM/S mast is a composite structure which encloses
the radar and antenna systems. Unlike conventional masts, the access path
to the upper levels is totally enclosed within the structure, with a total
vertical climb of 76 feet, serving five platforms or landings.
In August 2001, an INSURV report identified several discrepancies within the
AEM/S mast pertaining to personnel access and fall protection. Since the mast
was built as a technology demonstrator, the installing activity chose commercial
grade ladders and fall-arrest systems, with the emphasis on performance of
the structure and electronics contained within.
Hull Outfitting Section (9782) representatives Stephen Grasso and Anthony
Venti were tasked to perform a visual and operational inspection of the five
ladders (three fixed and two portable) and the existing commercial fall arrest
system and provide solutions.
Two main discrepancies were identified along with several secondary problems.
First, the existing fall arrest system was attached directly to the vertical
ladders. This violates Navy climber safety requirements. Per specifications,
fall protection systems shall be mounted back to the ships structure,
independent of the ladder. This ensures that the impact load generated from
a fall is transmitted directly back to a suitable structure, and not dependent
on the integrity of the ladder assembly. The second discrepancy was that one
portable ladder did not have any associated fall protection system. Personnel
free climbed the ladder without any protection. Secondary problems
included inadequate fall protection for personnel when climbing off of or
on to the top of a ladder, as well as a poor design and inadequate material
selection of the portable ladders mounting foundation which attached
to the ships structure.
To solve the problems, Grasso and Venti, teaming with Ed Devine (651), designed
and engineered a fall protection system around commercial fall protection
components to meet the Navys safety and operational requirements. To
provide protection for the portable ladders, the NSWC design team selected
commercial-off-the-shelf, self-retracting lifelines (SRLs) mounted to anchor
plates on the underside of each level, close to the access openings. SRLs
are commonly used in the commercial and industrial sectors. While unconventional
by Navy fall protection standards, these SRLs provide full protection for
personnel during their total climb and descent. Two SRLs were mounted at each
portable ladder location, one for primary use and one reserved for back-up
(emergency rescue). For the fixed ladder, the existing fall protection system
was retained but was augmented with additional support structure, engineered
to transmit the impact load (from a fall) back to the ships structure.
As for the inadequate portable ladder mounting foundation, Devine, redesigned
and engineered the mounting foundation which ensured safety and increased
strength and reliability when personnel attached the ladder to the ships
structure. Design upgrades were installed by NSWC during a brief in-port period
last December. Additionally, the ladders were successfully tested to prove
their strength and adequacy.
The lessons learned from USS Radford will be incorporated into the
LPD 17 AEM/S design.
INMAR SAT Antenna
While work was underway on the ladders, Composite Systems Section (6551) personnel
Michael Bergen, Ed Devine, and Lindsay Miller reconfigured the mast to accommodate
the reinstallation of a fire control video camera. This camera was part of
the original prototype, but was removed to make room for an INMAR SAT antenna,
which is a communications satellite that enables the ship to send and receive
email. The original design would not accommodate both pieces of equipment.
USS Radford requested Code 6551 develop designs to accommodate both
units. The engineers took into consideration several requirements: antenna
performance must not be degraded; signatures and maintenance requirements
must be minimized; the field of view for the remote optical site (ROS) camera
must be provided; and the structure must be stable. There were concerns about
placing conductive foundations so close to the antennas.
The engineers developed a design that would meet the criteria: a cantilevered
fiberglass sandwich structure. This structure is basically an L-shaped platform,
which is mounted above the ROS video camera. The INMAR SAT, which weighs 200
pounds, sits on the cantilever. The structure was manufactured using layers
of glass reinforced vinylesther plastic wrapped around a foam core for stiffness.
The fabrication of the parts was done under contract to Atlantic Marine Plastics
and Capital Industrial Supply.
Since the fix, like the mast, was a prototype, there were no installation
guidelines. Therefore, Bergen, Devine, and Miller performed the installation,
so they could resolve any technical issues that arose.
The neat thing about this project is that it demonstrates Carderocks
ability to directly support Fleet needs, said Miller. Generally,
here in West Bethesda we dont design, fabricate, and install things
on Navy ships by ourselves.
The installation was done by trial and error. When they first hauled the structure
up, they found that the dimensions were slightly off. Fortunately, the contractor
was willing to resize it immediately, so the installation could take place.
It was fairly scary up there, said Miller. We were really
high up, connected by safety harnesses. The first four days, we had ideal
weather. But the fifth day we were up there with gusts of wind of 20 to 30
mph. This was the day they were painting, leaving no doubt in anyones
mind that they were Navy workers as they left the site decked in Navy gray.
Additionally, while they dangled 100 feet above the deck, they watched a taping
of David Lettermans Top 10 aboard a neighboring ship.
USS Radford emailed their appreciation for the work done on the AEM/S.
NEWSLETTER
|
Join the GlobalSecurity.org mailing list |
|
|