UNITED24 - Make a charitable donation in support of Ukraine!

Weapons of Mass Destruction (WMD)


Voice of America 5/15/97

SPACE STATION SCHEDULE

BYLINE=DAVID MCALARY
DATELINE=WASHINGTON
CONTENT=
VOICED AT: 
INTRO:  THE DELAY IN CONSTRUCTION OF THE 
INTERNATIONAL SPACE STATION WILL  NOT 
BE AS LONG AS ORIGINALLY ANNOUNCED BY 
THE U-S SPACE AGENCY NASA LAST MONTH.  
AS V-O-A SCIENCE CORRESPONDENT DAVID 
MCALARY REPORTS, NASA SAYS THE 
POSTPONEMENT -- CAUSED BY RUSSIAN 
FINANCIAL DIFFICULTIES -- WILL BE ONLY 
EIGHT MONTHS INSTEAD OF ELEVEN AS
RUSSIAN SPACE CONTRACTORS RESUME 
BUILDING A KEY STATION COMPONENT.
TEXT:  NASA SAYS IT HAS FORMALLY 
AGREED TO A SPACE STATION CONSTRUCTION 
SCHEDULE WITH THE RUSSIAN SPACE AGENCY. 
THE REVISED CONSTRUCTION SCHEDULE 
MEANS THE FIRST SPACE STATION MODULE 
WILL BE LAUNCHED IN JUNE, 1998, INSTEAD 
OF THE FOLLOWING OCTOBER AS PREVIOUSLY 
ANNOUNCED.  
STATION ASSEMBLY WAS TO HAVE BEGUN 
IN ORBIT THIS COMING NOVEMBER, BUT THE
RUSSIAN GOVERNMENT'S FAILURE TO PAY 
FOR COMPLETION OF A KEY RUSSIAN 
COMPONENT SET BACK THE SCHEDULE. 
THIS CAUSED THE EUROPEAN, CANADIAN, 
AND JAPANESE PARTNERS IN THE PROJECT
AND MANY CRITICS IN THE U-S CONGRESS 
TO WONDER IF RUSSIA COULD LIVE UP TO 
ITS SPACE STATION COMMITMENTS.
NOW, NASA SAYS WORK ON THE 
COMPONENT HAS RESUMED BECAUSE THE 
YELTSIN GOVERNMENT IS PAYING ITS 
CONTRACTORS AGAIN.  THE RUSSIAN 
SPACE AGENCY EXPECTS TO HAVE 
280 MILLION DOLLARS FOR THE PROJECT 
BY SEPTEMBER.
      // BRINKLEY ACT //
I'M HAPPY TO REPORT THAT IT APPEARS
THAT THAT FUNDING PROBLEM IS BEHIND US.
      // END ACT //
THIS IS THE NASA OFFICIAL OVERSEEING 
U-S PARTICIPATION IN THE PROGRAM -- 
RANDY BRINKLEY.  HE SAYS RUSSIAN 
SPACE AGENCY OFFICIALS OPENED THEIR 
BOOKS TO HIM ON A RECENT VISIT TO PROVE 
GOVERNMENT MONEY WAS FLOWING AGAIN
INTO THE SPACE STATION PROGRAM.
       // BRINKLEY ACT //
WHEN WE WERE OVER THERE, WE HAD THE
OPPORTUNITY TO LOOK AT THE COMPONENTS,
TO LOOK AT THE DOCUMENTS FOR THE 
FUNDING.  WE KNOW THE NAMES OF THE 
BANKS AND WE'RE SURE THAT THE MONEY 
HAS IN FACT FLOWED -- NOT ONLY TO THE 
PRIME CONTRACTORS, BUT WE'VE HAD 
VALIDATION BY THE HEADS  OF THE
SUBCONTRACTORS THAT THEY WERE UNDER 
CONTRACT, THEY WERE FULLY FUNDED, 
AND THEY COULD MEET THEIR COMMITMENT 
OF THEIR SCHEDULE.
       // END ACT //
THE DELAYED RUSSIAN UNIT -- CALLED A 
SERVICE MODULE -- IS TO HOUSE SPACE 
STATION CREWS AND PROVIDE STEERING 
CAPABILITY.  IT IS NOW SCHEDULED FOR 
LAUNCH IN DECEMBER, 1998.  BUT BECAUSE
ITS FUNCTIONS ARE CRITICAL TO STATION
CONSTRUCTION, THE UNITED STATES
IS  NOT  TAKING ANY CHANCES.  IN CASE 
THE RUSSIAN SPACE AGENCY,  OR R-S-A, 
ENCOUNTERS FURTHER FUNDING PROBLEMS 
AND CANNOT MEET THE NEW DEADLINE, 
NASA IS SPENDING 200 MILLION DOLLARS
MORE THAN IT HAD PLANNED TO REFIT 
TWO OTHER MODULES -- ONE RUSSIAN, 
THE OTHER AMERICAN -- WITH SOME OF 
THE SERVICE MODULE'S CAPABILITIES. 
MR. BRINKLEY ACKNOWLEDGES THAT 
THE RISK OF A RENEWED DELAY HAS  NOT 
BEEN ELIMINATED, BUT BELIEVES THE 
DECEMBER, 1998 LAUNCH OF THE RUSSIAN 
SERVICE MODULE CAN BE MET.
      // BRINKLEY ACT //
THERE'S LITTLE MARGIN LEFT IN TERMS OF 
THE SCHEDULE RESERVE.  WE DO BELIEVE, 
HOWEVER, IT'S VERY EXECUTABLE. THE 
PEOPLE WE HEARD FROM -- BOTH R-S-A
AND THEIR MAJOR  SUBCONTRACTORS -- 
WERE VERY COMMITTED TO MEET THAT 
SCHEDULE.
        // END ACT //
MR. BRINKLEY ALSO REFUTED A NEWS 
REPORT IN RUSSIAN NEWSPAPER WEDNESDAY 
SAYING U-S AND RUSSIAN OFFICIALS WERE 
CONSIDERING USING THE SPACE STATION FOR
MILITARY PURPOSES.  HE INSISTS THE 
ORBITING RESEARCH LABORATORY IS TO 
BE USED FOR PEACEFUL PURPOSES.  
(SIGNED)
NEB/DEM/KL
15-May-97 3:36 PM EDT (1936 UTC)
NNNN



NEWSLETTER
Join the GlobalSecurity.org mailing list