Plutonium and Aldermaston - an historical account
The Government set in hand in the Strategic Defence Review (SDR) a process
of declassification and historical accounting with the aim of producing, by
the Spring of 2000, an initial report of defence fissile material production
since the start of the United Kingdom's defence nuclear programme in the 1940s.
This report is the first part of this study and deals with plutonium. The
scope of this initial review, in line with Government initiatives on openness,
provides information on the movement of plutonium to and from the Atomic Weapons
Establishment (AWE) Aldermaston where all fissile components for nuclear warheads
have been manufactured. This work complements the SDR announcement
of the current stock of nuclear material, held outside international safeguards,
for national security purposes. The SDR also announced that surplus stock
would be placed under Euratom safeguards and made liable to inspection under
the terms of the safeguards agreement between the UK, Euratom and the IAEA.
The plutonium stored at Sellafield has now been placed under safeguards and
the process of transferring the 0.3t of surplus weapons grade plutonium from
Aldermaston to a civil nuclear site, and bringing into safeguards, has commenced. Records were raised each time material was
moved between sites. The review was therefore conducted primarily from an
audit of annual accounts and delivery records from Sellafield supported by
receipt records at Aldermaston where these are available. Evidence was also
sought from available secondary sources. Records for the early years are inevitably
less complete and less detailed than for more recent years, although Sellafield
has maintained good accounts throughout, which cover the great bulk of material
transferred. Overall, confidence in the completeness and accuracy of the information
available is very high for the 1980s and 1990s, but less so before the mid
1960s. The review concludes that Aldermaston acquired
16.83 tonnes of plutonium from the start of the programme until 31 March 1999,
the baseline date for this report. Records suggest that during this period
13.61 tonnes of plutonium were removed from Aldermaston. However, there were
definitely still 3.51 tonnes in the defence nuclear stockpile on 31 March
1999. The sum of the recorded removals from Aldermaston and of the audited
stockpile (17.12 tonnes) is therefore 0.29 tonne higher than the recorded
total of plutonium acquired by Aldermaston (16.83 tonnes). This 0.29 tonne
excess of stockpile over what records suggest it should be represents some
1.7% of recorded acquisitions. However, this is regarded as a reasonable outcome
given the long period covered and the limited availability of records for
the early years. SECTION 1: INTRODUCTION 1. Since the end of the Cold War there has
been a re-examination of many of the capabilities required to meet our minimum
nuclear deterrence needs. Information relating to our nuclear stockpile has
historically been closely protected to ensure uncertainty in the minds of
others over just what our capabilities were. It was concluded in the Strategic
Defence Review (SDR), in July 1998, that we could safely make significant
reductions in planned warhead numbers and changes to the operational posture
of the nuclear deterrent as a result of the improved strategic circumstances.
Transparency about nuclear weapons holdings also plays a significant role
in arms control and adds to international confidence. It was also stated in
the SDR that the UK intends to be significantly more open about stocks of
fissile material, as part of the confidence building measures required to
support long term nuclear weapon arms control and warhead reduction initiatives. 2. One study initiated under the SDR was;
a process of declassification and accounting with the aim of producing
by Spring 2000 an initial report of defence fissile material production since
the start of Britain's defence nuclear programme in the 1940s. This report
is the first part of this study and deals with plutonium. The scope of this
initial review, in line with Government initiatives on openness, provides
information on the movement of plutonium to and from the Atomic Weapons Establishment
(AWE) Aldermaston where all fissile components for nuclear warheads have been
manufactured. Examination of reactor discharge records and subsequent tracking
of material through fuel reprocessing are not included. There was no requirement
to create consolidated records that would allow this path to be followed easily.
Records for individual reactor discharges would need to be located and compiled.
Some of these records were observed but there is no way of knowing without
an exhaustive search whether all are available. In any event, to follow this
process with the required degree of accuracy it would be necessary to know
what went into and out of the reprocessing facilities at a level of detail
that the available records, even if complete, do not provide. Ownership of
plutonium stocks is allocated to BNFL customers on the amount of fuel reprocessed
over a given financial year. 3. This work complements the SDR announcement
of the current stock of nuclear material, held outside international safeguards,
for national security purposes. The SDR also announced that surplus stock
would be placed under Euratom safeguards and made liable to inspection under
the terms of the safeguards agreement between the UK, Euratom and the International
Atomic Energy Agency (IAEA). The plutonium stored at Sellafield has now been
placed under safeguards and the process of transferring the 0.3t of surplus
weapons grade plutonium from Aldermaston to a civil nuclear site, and bringing
into safeguards, has commenced. SECTION 2: BACKGROUND Management of UK Nuclear Industry
4. The UK nuclear weapons programme was formally
initiated in January 1947. The military and civil nuclear cycles have been
run in parallel and to some extent were entwined during the early years of
the nuclear programme. The Ministry of Supply was the lead organisation until
the United Kingdom Atomic Energy Authority (UKAEA) was formed in 1954. The
great part of the UKAEA's activity at that time was research, development
and production in the civil and military fields. 5. The UKAEA managed a broad range of nuclear
facilities in the early years and was managed as four Groups; Production,
Reactor, Research and Weapons before the next major change came. In 1971 British
Nuclear Fuels Ltd (BNFL) was established from the production activities of
the UKAEA. BNFL took over the major share of the assets. The BNFL portion
of the Windscale site was renamed Sellafield in 1981 to distinguish it from
the remaining UKAEA activities on the same site. (The name Sellafield will
be used in this report, for clarity, to refer to the site where plutonium
originated, even for the early years). 6. The UKAEA organisation that remained after
1971, excluding the Weapons Group, was primarily research and development
(R&D) based with major facilities concentrated at Dounreay for Fast Breeder
reactor development, Winfrith for other reactor development, Windscale for
reactor development, fuel production and examination and Harwell. In 1989,
after reorganisation into businesses, the UKAEA started to use the trading
name AEA Technology. Further changes in the organisation subsequently took
place enabling privatisation, as AEA Technology, of the contract research
part of the UKAEA. The remaining UKAEA organisation is a non-departmental
public body, reporting to the Government through the Department of Trade and
Industry. It is concerned mainly with carrying out the decommissioning and
waste management responsibilities from the past nuclear research and development
programme and for the fusion research programme. 7. In 1950 nuclear weapons design work moved
from Fort Halstead to the Atomic Weapons Research Establishment (AWRE) at
Aldermaston. AWRE, with the trials range at Foulness in Essex, made up the
UKAEA Weapons Group which transferred to MOD ownership in 1973. In 1987 AWRE
was renamed the Atomic Weapons Establishment (AWE), on incorporation of two
of the former Royal Ordnance Factories at Burghfield and Cardiff, to reflect
the integration of all aspects of the nuclear weapons production programme
under one management control. (The name Aldermaston will be used in this report
for clarity). AWE then comprised four sites: Management
arrangements at the site were radically changed in 1993 when legislation was
put in place creating AWE as a Government Owned Contractor Operated (GOCO)
site and the Hunting BRAE consortium became the management contractor. Following
a rationalisation initiative, the Cardiff site has been closed and Foulness
transferred to the Defence Evaluation and Research Agency (DERA). A further
competition for the management contract has seen AWE Management Limited take
over as the management contractor from April 2000.
8.
The wide-ranging nature of the early UKAEA organisation meant that some blurring
of the distinctions between the military and civil roles of the establishments
was inevitable. The mixing of military and civil programmes was not seen as
significant at the time, in the context of one integrated organisation, and
the weapons fabrication facility also carried out development work in support
of the civil industry. UK Fissile Material Facilities
9.
Annex 1 lists the major facilities in the UK nuclear industry that are discussed
in this report.
10.
Work commenced on the Windscale Piles in Cumbria in 1947 and plutonium for
the early nuclear weapons programme was produced until the fire in Pile 1
in 1957. A reprocessing facility was constructed for the separation of plutonium
and uranium from spent fuel, and later replaced with another plant as the
Magnox programme grew. Even at this early stage some plutonium was sent to
Harwell, via Aldermaston, for research on civil applications of nuclear power.
The Calder Hall Magnox power station, constructed on the Sellafield site,
started operations in 1956 and consisted of four dual-purpose reactors for
commercial electricity generation and plutonium production for defence needs.
The Chapelcross power station in Southern Scotland started operations in 1958
and was operated on the same basis as Calder Hall. These two stations (8 reactors
in all) were owned and operated by UKAEA and subsequently transferred to BNFL.
11.
Plutonium was not produced continually for the weapons programme from these
reactors. During periods when they were not required for defence purposes
their operation was optimised for electricity generation by UKAEA/BNFL. They
were maintained as defence stand-by facilities and, since international safeguards
requirements applied, have been fuelled from safeguards excluded stocks of
uranium. On 18 April 1995 the Foreign Secretary announced that the UK has
ceased the production of fissile material for explosive purposes. Arrangements
were subsequently made to bring the Calder Hall reactors under Euratom safeguards
and make liable to inspection under the terms of the safeguards agreement
between the UK, Euratom and the IAEA. The Chapelcross reactors are still used
for producing tritium for nuclear weapons and are not subject to international
safeguards inspection. However, the SDR announced that all reprocessing of
spent fuel from defence reactors at Chapelcross will in future be conducted
under Euratom safeguards and made liable to inspection by IAEA. This is now
the case, irradiated fuel from the Chapelcross reactors is brought into safeguards
on arrival at Sellafield.
12.
The first Civil Magnox stations came on line in 1961 and were operated by
the Central Electricity Generating Board (CEGB). The fuel from all the civil
stations was sent to the same reprocessing facility at Sellafield as used
for spent fuel from Calder Hall and Chapelcross. The reprocessing plant was
initially operated on a campaign basis to segregate weapons grade material,
to maintain the isotopic purity of the plutonium. MoD has always relied on
BNFL, even in recent years, for UK production of nuclear materials.
13.
Some plutonium for civil programmes, in addition to plutonium for the defence
programme, was also shipped to Aldermaston (when part of UKAEA) for subsequent
transfer to other sites or for use in fuel development work. For example Aldermaston; This
work diminished as a result of transferring Aldermaston to the MOD and the
increasing focus of that establishment on the defence mission. There was also
increasing segregation of the civil and military programmes as a result of
the implementation of safeguards within the civil nuclear industry.
Plutonium
14.
Plutonium is a radioactive element that exists in many isotopic forms (different
forms of the same element only varying by the number of neutrons in the nucleus
of the atom). Plutonium-239 is produced when uranium-238 in reactor fuel absorbs
a neutron and then decays to plutonium. This plutonium isotope is preferred
for making nuclear weapons. As fuel in a reactor becomes exposed to neutron
irradiation, higher isotopes of plutonium build up as additional neutrons
are absorbed, creating plutonium-240, plutonium-241and plutonium-242. To produce
relatively pure plutonium-239 for weapon purposes the fuel rods are removed
from the reactor and reprocessed after a relatively short irradiation. For
power production the fuel is left in the reactor much longer to increase efficiency,
resulting in a much greater concentration of the higher isotopes of plutonium.
Any plutonium with more than 8 percent plutonium-240 is known in the UK as
reactor grade (alternatively referred to as "O" Grade). Plutonium
containing 8 percent or less plutonium-240 is known as weapons grade (alternatively
referred to as "A" Grade in the UK).
International Safeguards
15.
The Non-Proliferation Treaty (NPT) has placed obligations on the five Nuclear
Weapon States (NWS) of the United Kingdom, United States, France, Russia and
China. The NPT also obliges NNWS party to the Treaty not to manufacture or
otherwise acquire nuclear weapons. NNWS are obliged to conclude a comprehensive
safeguards agreement with the International Atomic Energy Agency (IAEA). Such
agreements provide for measures to deter and detect the diversion of nuclear
material from peaceful uses to nuclear weapons or other nuclear explosive
devices. A comprehensive safeguards agreement is not required of the NWS parties
although each has agreed a Voluntary Offer Safeguards Agreement with the IAEA.
16.
The UK has also been subject to the 1957 Euratom Treaty since joining the
European Community in 1973. All nuclear material in the UK not intended for
defence purposes is therefore subject to reporting to, and inspection by,
the Euratom safeguards inspectorate.
17.
Plutonium that is held outside safeguards for defence purposes is subject
to a stringent regime of controls and audits. Site operators are responsible
for; the physical security of the material, instituting controls for accurate
accountancy of the quantity of plutonium held and its location, raising detailed
accounts and having robust internal audit arrangements. The MoD conducts an
independent assessment of the site systems, audits the accounts and conducts
physical inventory checks.
SECTION 3: RECORD REVIEW
Details of the Review
18.
This study is similar in scope, from the UK perspective, to the major United
States Department of Energy (USDOE) programme of work to account for defence
stocks of nuclear materials. The conclusions of the US material accounting
review for defence stocks of plutonium were published in February 1996 in
the report; "Plutonium: The First 50 years".
19.
The most important factor in being able to derive a detailed account of the
defence stocks of plutonium is access to complete and accurate records. Records
were raised when material was transferred between sites (and within sites
for local accounting procedures). This review has been conducted primarily
from an audit of annual accounts and delivery records from Sellafield supported
by receipt records at Aldermaston where these are available. The quality and
completeness of records held by Sellafield is, overall, very good. However,
for earlier years, the accountancy detail recorded, though fully acceptable
at the time, is to a different standard to that required today. The early
Sellafield transfer source documents have been destroyed but details of transfers
off-site are contained in the annual accounts. As early documentation for
moves from other sites is not available or incomplete, evidence has been sought
from all available secondary sources. There is therefore a risk that the information
available is not complete. In addition to the Sellafield accounts, Aldermaston
movement orders and other documentation were used to produce derived accounts
for Aldermaston for the period where original accounts are not available.
Records at the UKAEA sites were also examined, where available.
20.
Confidence is high for the completeness and accuracy of the information obtained
for the 1980s and 1990s as the primary transfer records are still available.
Prior to this period confidence falls with elapsed time, particularly that
before the mid-1960s. The exception to this is the confidence obtained from
the good quality Sellafield records for plutonium movements for all periods,
which accounts for the great bulk of the material transferred.
21.
In general, weapons grade plutonium would have been separated from spent fuel
at Sellafield and delivered to Aldermaston for manufacture of weapon components.
However, there were other more minor routes by which plutonium was transferred
to and from Aldermaston as outlined in Paragraph 13, where material was supplied
to support civil development work at Aldermaston, which have been examined
to give a full picture of material movements. The situation was also complicated
up to 1985 by the return of plutonium process residues from Aldermaston to
Sellafield for recovery and then subsequent return to Aldermaston for re-use.
Care has been taken in examining the accounts not to double count any of these
acquisitions/removals.
SECTION 4: RESULTS OF THE REVIEW
Plutonium Material Balance for Transfers To/From Aldermaston
22.
An overall summary account of acquisitions and removals of plutonium for Aldermaston
has been drawn up (Table 1) based on receipts from Sellafield and other sources
and issues from Aldermaston. The cumulative inventory difference for the period
from 1952 is 0.29 tonnes. An annual breakdown of transfers of plutonium between
Aldermaston and other UK sites is given in the attached Tables 2-5, compiled
from available documentation. Acquisitions were predominantly from Sellafield.
Removals were from Aldermaston to Harwell, Dounreay, Winfrith, USDOE, and
plutonium was used in weapons tests and assigned to waste.
23.
A more detailed discussion of the acquisitions data in Table 1 is given below:
24.
A more detailed discussion of the removals data in Table 1 is given below:
To Establishments in Tables 2-5 (7.50 t): ·
The removals to Sellafield
(Table 2) (3.93 t) constitute the return of residues to the recovery plant.
Not all this material would be for Defence purposes as the civil work at Aldermaston
also generated residues that were returned to Sellafield for treatment.
·
In the early years while Aldermaston
was under UKAEA management, there were several cooperative programmes of work
with other UKAEA sites. In the period 1958-1977 Aldermaston sent 0.22t of plutonium
to Dounreay (Table 3), in association with uranium as oxide or carbide, in support
of development of fuel for the fast reactor development work at Dounreay. Aldermaston
also undertook fuel development work in support of the ZEBRA reactor at Winfrith.
In the period 1961-1984 fuel containing a total of 2.82t of plutonium (Table
4) was sent to Winfrith for use in the civil programme. Both these activities
were in support of civil objectives. This material transferred to Aldermaston
in support of civil applications was not subject to Euratom safeguards after
1973 because of the need to protect national security information and facilities
on the site. Once Aldermaston was incorporated into MoD in 1973 there was a
steady closing down of civil development work. ·
Some transfers were made to
Harwell (Table 5) in support of both military and civil programmes. These transfers
were mainly contained in samples for chemical analysis, for small-scale research
studies or for waste disposal. The records for the early years do not allow
an easy distinction between the civil and military programmes. However, a clear
12kg of the 0.53t transferred to Harwell was designated as stock belonging to
the civil programme. To US (0.47t): Plutonium
transferred to the US. These transfers remain classified and are therefore
not broken down further. ·
discarded waste as
either liquid effluent or in solid waste sent to the low level waste disposal
site at Drigg ·
the quantity of material
that was disposed of to sea, before sea dumping was discontinued in 1983
·
waste currently stored
on the Aldermaston site awaiting final disposal, but written off of the stockpile
accounts. 25.
Stockpile (3.51t): The weapon cycle stock figure, comprising the total
plutonium held at AWE sites and that which is in service, was published in
the SDR and is known accurately using modern material accounting practices.
It stands at 3.51t at the baseline date for this study of 31 March 1999. This
includes the 0.3t of weapons grade plutonium declared as excess to military
requirements in the SDR, some of which has since been moved from Aldermaston
to Sellafield and placed under international safeguards.
26.
The cumulative inventory difference is the difference between the amount of
material accounted for in this exercise as being delivered to Aldermaston
and the quantity measured by physical inventories. This is calculated;
INVENTORY DIFFERENCE = PHYSICAL INVENTORY - BOOK INVENTORY Where: Physical Inventory = Weapon Cycle Stock Book Inventory = Acquisitions - Removals
Applying
the equation above gives a positive cumulative inventory difference indicating
that the stockpile contains more material, by 0.29t, than can be confirmed
by examination of the available documents. The explanation for this discrepancy
is due to the poorer quality and completeness of some of the older records.
It can never be certain that all transfer records have been preserved. The
records are of variable quality in the period of the 1950s and early 1960s.
Other factors such as the technology available, measurement uncertainties
and inaccuracies and sampling problems also contribute to this figure. However,
the overall level of the Inventory Difference is low in comparison to the
amount of material delivered to Aldermaston, at some 1.7% of plutonium delivered.
27.
A readily identifiable net transfer of 2386kg (3053kg issued - 667kg received
from Dounreay, Winfrith and Harwell) of plutonium was recorded from Aldermaston
to other UKAEA sites in support of civil development work. The net removal
of plutonium for civil programmes indicates that there was no diversion to
the nuclear weapons programme, as far as the scope of this study could determine.
28.
Calder and Chapelcross reactors also produced substantial quantities of reactor
grade plutonium. This resulted from the periods when the reactors were solely
used for generating electricity or also for tritium production in the case
of Chapelcross. Some of this material was used in the Barter programme with
the US. The plutonium stored at Sellafield has now been placed under safeguards
as stated in the SDR. Ownership of this plutonium is split between MOD and
BNFL depending on which organisation owned the fuel and received the benefits
of reactor operation. It is in a similar oxide form to all the other plutonium
from Magnox reprocessing stored at Sellafield and was only kept segregated
because it was unsafeguarded. Ownership was assessed by past usage of the
reactors.
29.
MOD has never had a requirement for the reactor grade plutonium stored at
Sellafield in the weapons programme and it has been regarded more as a by-product
of material production. It was retained outside of safeguards inspection to
protect against calculation of the quantity of weapons grade plutonium produced.
Knowledge of the capabilities of the Calder Hall and Chapelcross Magnox reactors
and the amount of reactor grade produced would have given some credence to
informed estimates of weapons grade production.
SECTION 5: BARTER ARRANGEMENTS
30.
Between 1960 and 1979 the UK supplied the US with approximately 5.4 tonnes
of plutonium under the 1958 UK/US Mutual Defence Agreement (MDA) which enables
transfers between the UK and US of special nuclear materials. The material
was supplied in three tranches; known respectively as Barters A, B and C.
Barters A and C came from the military production reactors at Calder Hall
and Chapelcross, whereas civil Magnox reactors also produced some material
for Barter B. In exchange, the UK received from the US 6.7kg of tritium and
7.5 tonnes of high enriched uranium (HEU) for Defence applications.
31.
As part of the ongoing USDOE fundamental classification policy review, details
of the quantities of material involved in the Barter exchanges were released
in December 1997, expanding on the information provided on the total quantities
published in February 1996. Both announcements by the USDOE had the support
of the UK Government. The quantities of plutonium involved were: 32.
Further background information was also released, including the breakdown
of the isotopic composition of the plutonium sent to the US. Prior to 1964,
some plutonium received by the US was used for military purposes. Given that
this material was derived from UK military stocks and was exchanged under
a military agreement, however, it was only to be expected that it would have
been used in the US weapons programme. However, although in principle the
1958 US/UK MDA allowed the US to use plutonium produced in civil UK reactors
for nuclear weapons, the US undertook in 1964 not to do so. Civilian programmes
include californium production and reactor research. Barter C was not subject
to the 1964 statement as all of the UK plutonium was obtained from the military
reactors. Some of the plutonium received under Barter C was used in US nuclear
weapons.
33.
The timescale between start-up of the first civil reactors in August 1961
and the time involved for irradiation of fuel, cooling, reprocessing and shipment
to the US would have been considerable. In practice, therefore, it is extremely
unlikely that any civil plutonium was supplied to the US before the announcement
in 1964 that no civil plutonium was to be used in the US weapons programmes.
34.
The arguments presented in Paragraph 2 make it clear that the records do not
exist to trace categorically, with the practice of co-processing of fuel from
civil and military reactors, the fate of actual atoms of civil fuel. However,
the overall accounts are used to ascribe the appropriate customer liability.
This is analogous to the practice of financial accounting, individual notes
are not physically traced, but each customers account is kept balanced. It
is therefore a fruitless task at this distance to pursue any attempt to trace
the fate of civil fuel when it has already been acknowledged that UK civil
plutonium has been used in Barter B. The US Government has given assurances
that it was not used in the US nuclear weapons programme
SECTION 6: CONCLUSIONS
A
study has been made of plutonium production for the nuclear weapons programme
as outlined in the SDR, in support of the Government's openness initiative.
A comprehensive investigation of existing records has revealed a positive
1.7% discrepancy in the through life inventory of plutonium at Aldermaston
- ie. the stockpile contains more material than has been confirmed by the
accounting exercise. This is regarded as a reasonable outcome given the long
period covered and the limited availability of records for the early years.
SUMMARY
ANNEX 1
RELEVANT UK NUCLEAR SITES DISCUSSED IN THIS REPORT
Springfields |
Uranium
Ore Storage, treatment and fuel fabrication |
Transferred
to BNFL in 1971 |
Chapelcross |
Dual
purpose (plutonium, tritium and power production) reactors, Tritium
processing |
Transferred
to BNFL in 1971 |
Windscale
(Sellafield)and Calder Hall |
Windscale
Piles, dual purpose plutonium production and power reactors, reprocessing
plant |
Transferred
to BNFL in 1971. UKAEA leases part of site and retain responsibility for the
Piles |
Aldermaston |
Nuclear
weapons R&D |
MOD owned
from 1973 |
Burghfield |
Warhead
Assembly |
Transferred
to AWE from ROF in 1987 |
Other Facilities: |
|
|
Foulness |
Weapon
trials (non nuclear) |
MOD owned
from 1973 |
Cardiff |
Depleted
uranium fabrication |
MOD owned
from 1973 |
Dounreay |
Fast reactor R&D |
UKAEA site |
Harwell |
Research |
UKAEA site |
Winfrith |
Reactor
R&D |
|
TABLE 1
CONSOLIDATED SUMMARY ACCOUNT FOR ALDERMASTON PLUTONIUM
TRANSFERS
UP TO 31 MARCH 1999
ACQUISITIONS |
|
From
Sources in Tables 2-5 |
15.99 |
TOTAL
ACQUISITIONS |
17.12 |
|
|
REMOVALS |
|
To
Establishments in Tables 2-5 |
7.50 |
TOTAL
REMOVALS |
17.12 |
TABLE 2
TRANSFERS BETWEEN ALDERMASTON AND SELLAFIELD
YEAR |
Pu DELIVERED (kg) |
YEAR |
Pu DELIVERED (kg) |
||
|
From |
To |
|
From |
To |
1952/53 |
20.3 |
|
1975/76 |
184.1 |
130.4 |
1953/54 |
89.9 |
6.7 |
1976/77 |
183.7 |
83.0 |
1954/55 |
72.9 |
4.6 |
1977/78 |
257.2 |
146.7 |
1955/56 |
75.0 |
8.8 |
1978/79 |
410.1 |
37.7 |
1956/57 |
90.6 |
11.2 |
1979/80 |
186.8 |
24.7 |
1957/58 |
115.2 |
20.0 |
1980/81 |
* |
10.7 |
1958/59 |
155.2 |
19.7 |
1981/82 |
* |
109.2 |
1959/60 |
150.3 |
17.6 |
1982/83 |
169.3 |
72.5 |
1960/61 |
271.5 |
17.2 |
1983/84 |
95.7 |
203.2 |
1961/62 |
436.2 |
39.5 |
1984/85 |
155.4 |
107.4 |
1962/63 |
486.1 |
236.7 |
1985/86 |
124.8 |
|
1963/64 |
289.4 |
186.1 |
1986/87 |
* |
|
1964/65 |
437.4 |
108.8 |
1987/88 |
* |
|
1965/66 |
776.4 |
161.3 |
1988/89 |
* |
|
1966/67 |
920.1 |
223.6 |
1989/90 |
180.9 |
|
1967/68 |
1527.2 |
251.2 |
1990/91 |
270.7 |
|
1968/69 |
1963.4 |
416.7 |
1991/92 |
178.7 |
|
1969/70 |
1314.6 |
174.2 |
1992/93 |
268.1 |
|
1970/71 |
713.3 |
211.2 |
1993/94 |
180.9 |
|
1971/72 |
799.8 |
241.9 |
1994/95 |
171.2 |
* |
1972/73 |
420.4 |
291.0 |
1995/96 |
21.3 |
|
1973/74 |
217.6 |
237.8 |
1996/97 |
* |
|
1974/75 |
293.9 |
120.4 |
1997/98 |
* |
|
|
|
|
1998/99 |
* |
|
|
|
|
TOTAL |
14675.6 |
3931.7 |
* indicates transfer of
less than 0.1kg
TABLE 3
TRANSFERS BETWEEN ALDERMASTON AND DOUNREAY
YEAR |
Pu DELIVERED (kg) |
YEAR |
Pu DELIVERED (kg) |
||
|
From |
To |
|
From |
To |
1952/53 |
|
|
1975/76 |
|
4.5 |
1953/54 |
|
|
1976/77 |
* |
100.6 |
1954/55 |
|
|
1977/78 |
|
|
1955/56 |
|
|
1978/79 |
|
|
1956/57 |
|
|
1979/80 |
|
|
1957/58 |
|
|
1980/81 |
|
|
1958/59 |
|
0.1 |
1981/82 |
|
|
1959/60 |
|
6.9 |
1982/83 |
|
|
1960/61 |
3.1 |
3.0 |
1983/84 |
|
|
1961/62 |
0.2 |
3.4 |
1984/85 |
|
|
1962/63 |
127.6 |
5.5 |
1985/86 |
|
|
1963/64 |
0.3 |
3.6 |
1986/87 |
|
|
1964/65 |
0.9 |
4.9 |
1987/88 |
|
|
1965/66 |
0.5 |
7.9 |
1988/89 |
|
|
1966/67 |
|
10.6 |
1989/90 |
|
|
1967/68 |
0.1 |
4.6 |
1990/91 |
|
|
1968/69 |
|
2.2 |
1991/92 |
|
|
1969/70 |
2.7 |
3.2 |
1992/93 |
|
|
1970/71 |
2.8 |
1.4 |
1993/94 |
|
|
1971/72 |
5.5 |
1.7 |
1994/95 |
|
|
1972/73 |
|
4.2 |
1995/96 |
|
|
1973/74 |
|
33.2 |
1996/97 |
|
|
1974/75 |
|
20.0 |
1997/98 |
|
|
|
|
|
1998/99 |
|
|
|
|
|
TOTAL |
143.7 |
221.5 |
* indicates transfer of
less than 0.1kg
- plutonium in spent fuel
transferred to Dounreay from Aldermaston research reactors is not included in
this Table - this report only deals with separated plutonium
TABLE 4
TRANSFERS BETWEEN ALDERMASTON AND WINFRITH
YEAR |
Pu DELIVERED (kg) |
YEAR |
Pu DELIVERED (kg) |
||
|
From |
To |
|
From |
To |
1952/53 |
|
|
1975/76 |
110.7 |
43.4 |
1953/54 |
|
|
1976/77 |
|
|
1954/55 |
|
|
1977/78 |
|
|
1955/56 |
|
|
1978/79 |
|
|
1956/57 |
|
|
1979/80 |
0.1 |
|
1957/58 |
|
|
1980/81 |
|
|
1958/59 |
|
|
1981/82 |
|
|
1959/60 |
|
|
1982/83 |
|
25.1 |
1960/61 |
|
|
1983/84 |
|
8.2 |
1961/62 |
|
15.3 |
1984/85 |
|
|
1962/63 |
|
0.1 |
1985/86 |
|
|
1963/64 |
2.0 |
104.0 |
1986/87 |
|
|
1964/65 |
24.9 |
122.9 |
1987/88 |
|
|
1965/66 |
144.6 |
248.4 |
1988/89 |
|
|
1966/67 |
1.2 |
16.6 |
1989/90 |
|
|
1967/68 |
0.1 |
0.1 |
1990/91 |
|
|
1968/69 |
0.6 |
* |
1991/92 |
|
|
1969/70 |
89.8 |
0.6 |
1992/93 |
|
|
1970/71 |
118.3 |
561.9 |
1993/94 |
|
|
1971/72 |
0.2 |
1163.8 |
1994/95 |
|
|
1972/73 |
4.0 |
255.8 |
1995/96 |
|
|
1973/74 |
70.0 |
256.4 |
1996/97 |
|
|
1974/75 |
82.1 |
|
1997/98 |
|
|
|
|
|
1998/99 |
|
|
|
|
|
TOTAL |
648.6 |
2822.6 |
* indicates transfer of
less than 0.1kg
TABLE 5
TRANSFERS BETWEEN ALDERMASTON AND HARWELL
YEAR |
Pu DELIVERED (kg) |
YEAR |
Pu DELIVERED (kg) |
||
|
From |
To |
|
From |
To |
1952/53 |
|
|
1975/76 |
0.1 |
1.0 |
1953/54 |
|
|
1976/77 |
0.4 |
* |
1954/55 |
|
|
1977/78 |
4.4 |
0.5 |
1955/56 |
|
|
1978/79 |
|
* |
1956/57 |
|
|
1979/80 |
* |
1.3 |
1957/58 |
10.9 |
9.8 |
1980/81 |
* |
5.0 |
1958/59 |
19.2 |
|
1981/82 |
0.9 |
15.7 |
1959/60 |
|
|
1982/83 |
97.4 |
147.4 |
1960/61 |
* |
6.0 |
1983/84 |
265.6 |
239.6 |
1961/62 |
|
6.4 |
1984/85 |
4.4 |
3.6 |
1962/63 |
|
4.8 |
1985/86 |
5.8 |
4.9 |
1963/64 |
3.8 |
8.9 |
1986/87 |
10.4 |
5.5 |
1964/65 |
3.4 |
9.3 |
1987/88 |
2.5 |
13.3 |
1965/66 |
0.5 |
0.4 |
1988/89 |
18.1 |
3.6 |
1966/67 |
0.2 |
0.2 |
1989/90 |
5.5 |
11.9 |
1967/68 |
0.4 |
2.3 |
1990/91 |
8.9 |
12.4 |
1968/69 |
|
0.8 |
1991/92 |
9.9 |
5.9 |
1969/70 |
* |
2.2 |
1992/93 |
38.2 |
5.3 |
1970/71 |
0.1 |
0.1 |
1993/94 |
1.2 |
1.2 |
1971/72 |
* |
* |
1994/95 |
0.6 |
0.4 |
1972/73 |
0.4 |
0.1 |
1995/96 |
0.3 |
0.2 |
1973/74 |
1.8 |
0.1 |
1996/97 |
0.2 |
0.1 |
1974/75 |
5.4 |
3.8 |
1997/98 |
0.2 |
0.3 |
|
|
|
1998/99 |
0.2 |
|
|
|
|
TOTAL |
521.3 |
534.3 |
* indicates transfer of
less than 0.1kg
© Crown Copyright 2000
NEWSLETTER
|
Join the GlobalSecurity.org mailing list |
|
|