GC(40)/16
20 August 1996
GENERAL Distr.
|
|
Fortieth regular session Item 20 of the provisional agenda (GC(40)/1) |
Implementation of the Agreement Between the Agency and the Democratic People's Republic of Korea for the Application of Safeguards in Connection with the Treaty on the Non- Proliferation of Nuclear Weapons
Report by the Director General to the General Conference
- In resolution GC(39)/RES/3 of 22 September 1995, the General
Conference, inter alia, decided:
"to include in the agenda for its fortieth regular session an item entitled "Implementation of the agreement between the Agency and the Democratic People's Republic of Korea for the Application of Safeguards in connection with the Treaty on the Non-Proliferation of Nuclear Weapons"".
This report is designed to provide information to the General Conference in its consideration of this item of its agenda.
THE SITUATION PREVAILING WITH REGARD TO SAFEGUARDS IMPLEMENTATION IN THE DPRK AT THE TIME OF THE THIRTY-NINTH REGULAR SESSION OF THE GENERAL CONFERENCE
- The Director General's report to the General Conference in
1995 in document GC(39)/18 of 17 August 1995 gave the background
to the developments which had taken place during the previous
year in safeguards implementation in the DPRK pursuant to the
DPRK's Safeguards Agreement with the Agency (INFCIRC/403) and
described those developments. They included the Board of
Governors' authorization to the Director General, on 11 November
1994, to carry out the tasks which the United Nations Security
Council had asked the Agency to undertake in the light of the
"Agreed Framework" (see Annex l); the discussions which
subsequently took place between an Agency technical team and DPRK
representatives; the visit to the DPRKby an IAEA technical team
in November 1994, and the later visit by the team in January
1995.
- The report last year referred to the further technical
discussions between the Agency and DPRK scheduled for April 1995,
but which had not taken place. This was because DPRK had informed
the Agency that it continued to regard the IAEA activities in
their country as being directly related to the implementation of
the "Agreed Framework", and took the view that, when negotiations
between the United States and the DPRK were at stalemate
over aspects of the "Agreed Framework" there was little point in
further technical discussions with the Agency. Notwithstanding,
the Director General was subsequently able to inform last year's
General Conference that further technical discussions between the
IAEA team and the DPRK had taken place in September 1995,
following US/DPRK bilateral discussions. Limited progress had
been made on some issues.
- In the light of this and of the Director General's report in
document GC(39)18, the General Conference adopted resolution
GC(39)/RES/3. By that resolution, the General Conference,
inter alia, endorsed the actions and commended the efforts
taken by the Secretariat to implement the Safeguards Agreement
and to monitor the freeze in the DPRK; expressed concern over the
continuing non-compliance of the DPRK with its Safeguards
Agreement; and urged it to co-operate fully with the Agency in
the implementation of that Agreement.
DEVELOPMENTS OVER SAFEGUARDS IMPLEMENTATION IN THE DPRK SINCE THE THIRTY-NINTH REGULAR SESSION OF THE GENERAL CONFERENCE
- At the post-General Conference meeting of the Agency Board of
Governors on 25 September 1995, the Director General reported on
the talks held in the DPRK from 12-18 September 1995. He
explained that although the DPRK had agreed to measurements of
irradiated fuel rods in storage at the 5 MWe experimental reactor
which would verify whether the rods were all irradiated fuel, it
had not agreed to measures which would give information about the
total amount of plutonium in the spent fuel. As a result, the
information required about that plutonium would have to be
obtained through measurements, with some limitations in accuracy,
to be made at a much later date and could require opening
the storage containers at significant additional cost. The Board
of Governors was reminded that the Agency had envisaged taking
the required measurements during the transfer of the spent fuel
into containers for storage.
- The Director General said that no agreement had been reached
about installing additional Agency monitoring equipment at
nuclear waste tanks in the DPRK's reprocessing plant, to enable
the Agency to verify, on a continuous basis, the absence of any
movement or operation involving those wastes. On the other hand,
some implementation measures which had been agreed in January
1995 with the DPRK but not yet applied because of objections by
the operator (e.g. photographing of the new process line of the
reprocessing plant by inspectors) would now be implemented as
soon as possible. The Director General also told the Board that a
detailed technical paper on the subject of the preservation of
information, which had been given to DPRK representatives at the
beginning of the talks, had not been discussed; the DPRK intended
to study the paper and discuss it with the Agency at a future
meeting. The paper describes the information that the DPRK needs
to preserve (and which the Agency requires) in connection with
verifying the correctness and completeness of the DPRK's initial
report.
- At the meeting of the Board of Governors on 12 December 1995,
the Director General said that in September 1995 the Agency had
asked the DPRK to undertake minor but essential modifications to
the design of the storage racks for the cans to contain spent
fuel discharged from its Experimental Reactor. This was to allow
the cans to be sealed effectively in the racks under water. The
modifications requested would not cause delay in the canning
operations, the timetable for which appeared to have slipped
because of technical difficulties. The Director General also said
that, despite the agreement reached with the DPRK about
photographing the new process line and other areas of the
Radiochemical Laboratory, DPRK operators had raised fresh
objections and the photographing had still not been possible. The
Agency's technical paper about the preservation of information
was also on the agenda for the next technical meeting planned for
January 1996.
- In his report to the Board of Governors for its March 1996
meeting (GOV/2687/Add.11), the Director General reported that a
fourth round of technical discussions had taken place in
Pyongyang from 23-29 January 1996. Although discussion had
resulted in limited progress in some areas, the DPRK had
continued to decline a number of important measures. Thus, the
DPRK had said that the Agency could now "resume ad-hoc and
routine inspections" (required by the Safeguards Agreement) but
had made clear that such inspections would be permitted only at
facilities not subject to the freeze.
- During the January talks, there was reconfirmation of
agreement on Agency inspectors continuing baseline photographing
at all facilities subject to the freeze. Reconfirmed too was
that the DPRK would provide (as the freeze requires) advance
notice to Agency inspectors about any maintenance work involving
facilities and equipment. Also reconfirmed was that short notice
inspections and visits by Agency inspectors already in the DPRK
would continue to take place at different parts of facilities
subject to the freeze. This was as an interim measure, until
agreement were reached about installing containment and
surveillance and other monitoring devices (e.g. at certain parts
of the Radiochemical Laboratory). Additionally, to help obviate
delays in issuing visas for Agency inspectors, it was agreed that
the Agency would give inspector notifications two weeks in
advance so as to facilitate the timely issue of visas in Vienna.
- The report in GOV/2687/Add.11 recorded that the technical
talks of January 1996 had also involved a detailed discussion
about inspection activities to be carried out at specific
locations. The report also covered other issues addressed,
especially the preservation of information required to verify the
correctness and completeness of the DPRK's initial declaration
under its Safeguards Agreement.
- In that regard, the report said that no agreement could be
reached in January 1996 about the proposals in the Agency's
technical paper. Agency representatives had reiterated
that in the absence of early agreement on the measures required,
any possibility for the Agency to verify the correctness and
completeness of the DPRK's initial declaration in the future
might be lost. The report also said that a fifth round of
technical discussions between the Agency and the DPRK had been
planned for the second half of May 1996.
- In his introductory statement to the June 1996 meeting of the
Board of Governors, the Director General said that "because of
unforeseen reason", the DPRK had had to postpone the fifth round
of technical discussions from May until mid-June. The Agency had
proposed that the discussions focus on the need for early
implementation of measures for the preservation of the
information required in connection with the verification of the
correctness and completeness of the DPRK's initial declaration.
The consultations would also cover issues related to safeguards
implementation in the DPRK, including the installation of
monitoring equipment at nuclear waste tanks in the reprocessing
plant and monitoring the freeze. The Director General reminded
the Board that the Agency maintains a continuous inspector
presence in the Nyongbyon area, and also said that canning of the
spent fuel rods at the 5 MWe reactor had started at the end of
April 1996. Agency inspectors were performing verification of the
rods by measurements which, however, did not provide any
information about the total amount of plutonium contained in the
irradiated fuel.
- Details of the sealing arrangements for the containers with
spent fuel rods had not yet been agreed. Progress in canning was
slow and the completion of the operation could be expected only
by the beginning of 1997. Until then, three to four Agency
inspectors would need to be stationed in the Nyongbyon area to
cover all the required activities. This would increase the
financial burden resulting from the Agency's work in the DPRK.
- The fifth round of technical discussions between IAEA and
DPRK representatives took place from 25 to 28 June 1996.
Discussions resulted in some progress in certain areas
but the DPRK still did not accept some important measures.
- There was discussion about a paper from the IAEA on the
status of Agency activities performed in the DPRK. This included
clarification about issues regarding the implementation of the
activities, agreement on procedures for short-notice inspections
and visits and activities related to the canning operations. The
June 1996 technical meeting did not result in agreement about the
long-standing issue of reports by the DPRK on facilities
subject to the freeze, or on installing monitoring equipment to
allow the monitoring of nuclear waste tanks. Neither was there
agreement about measuring or taking samples at locations in the
Radiochemical Laboratory selected by the IAEA. As for monitoring
the graphite blocks and other nuclear related equipment and
components for the 50 MWe and 200 MWe reactors under construction
at the inception of the freeze, the DPRK reiterated that
manufacturing such equipment and components had been discontinued
in 1993. The two sides agreed that this subject would again be
addressed during the next technical meeting, after appropriate
consultations.
- During discussion about the Agency paper on the preservation
of information the DPRK made the following comments:
- The Agency should not make excessive requirements even in the
light of the contents of the US/DPRK Agreed Framework;
- IAEA proposals on the preservation of inforrnation should be
linked to progress in the implementation of the Agreed Framework;
- verification of the correctness and completeness of the
initial declaration of the DPRK's nuclear material is to be
carried out following consultations between the IAEA and the
DPRK when a significant portion of the LWR project is
completed, but prior to the delivery of key, nuclear related
components;
- the DPRK is now ready to discuss verification measures at
facilities both subject to and not subject to the freeze.
However, issues related to "other" facilities would be discussed
when "the time comes";
- the monitoring activities which the Agency is currently undertaking at DPRK facilities both subject to and not subject to the freeze, are important for the preservation of information. Additionally, a lot of information has previously been provided to the Agency.
- The Agency should not make excessive requirements even in the
light of the contents of the US/DPRK Agreed Framework;
- During the discussions, the Agency team pointed out that the
requirements in the Agency paper applied to all comprehensive
safeguards agreements. The team also made clear that crucial to
verifying the correctness and completeness of the DPRK's initial
declaration is information about "other" facilities, that is
nuclear waste sites and a pilot plant at which the first core of
the 5 MWe reactor had been manufactured and which, the DPRK
said, had been dismantled. The Agency could not agree to the
DPRK's intention to split provision of the information into two
parts. The data required needed to be preserved urgently and in
its entirety.
- The DPRK presented a paper dated 27 June 1996 on
"Preservation of information relevant to verification of the
correctness and completeness of initial declaration". Providing
the paper which, to a limited degree, incorporates measures
contained in the Agency paper on the same subject, is a step in
the right direction. However, the DPRK paper does not
include any proposal for implementing the measures required.
Moreover, it includes only limited information about facilities
subject to and not subject to the freeze, and does not
cover "other" facilities and locations. Further discussions will
take place during the next technical meeting. This was
tentatively scheduled and later confirmed to take place in
Vienna in September 1996.
- In the light of increased technical activities, the DPRK agreed to take the measures necessary to improve communications from the DPRK. The DPRK also agreed to designate nine more Agency inspectors.
NEWSLETTER
|
Join the GlobalSecurity.org mailing list |
|
|