Length | 153.5 feet
|
Draft | 9.5 feet
|
Flank Speed | 28 knots
|
Crew | 24
|
Stern Launch Cutter Boat |
|
Cutter Boat | 7.9 meters (40 knots)
|
Endurance | 5 days
|
Tonnage | 353 metric tons
|
Hull | Steel
|
Superstructure | Aluminum
|
Propulsion |
MTU-DD (TognumAmerica, Inc) Single System Integrator (SSI)
Propulsion plant configuration:
2 MTU 20V4000M93L MDEs
MCMS
ZF Reduction Gears
Schaffran Propellers
|
Electrical System |
Easy Gen Power Controls
SSDG: Cummins QSM11-DM
EDG: Cummins 6BTA5.9-D(M)
|
C4ISR |
Comms
Sensors
L3 Symphony: communications management
C2 System: SEAWATCH software (GFI) / hardware (CFE)
|
Auxiliary Systems |
HVAC: Novenco
Reverse Osmosis Units: 2 Village Marine Model 20700 (440 gpd)
Bow Thruster: Schottel STT60FP
Stabilizers: Quantum QC-1500
Anchor: Fortress FX-125
Stern Launch & Recovery System
Cutter Boat: NAIAD 7.9m HJ274
|
Armament |
360°coverage
MK38 Mod 2 (GFE)
4, .50 cal machine guns (GFE)
|
Differences between RFP and current design: |
Defined factor of safety for structure
Added two Ensigns to crew. Change was accommodated by converting guest racks to permanent racks.
No loiter drive
Bow thruster inherited from parent craft
|
Length | 120 ft. - 160 ft.
|
maximum draft | 10 ft
|
Flank Speed | 28 knots min.
|
Independent Operations | 5 days min.
|
Seakeeping | At a minimum conduct all missions through SS4 and survive through SS6
|
C4ISR | electronic navigation, communications, and surveillance systems Interoperable with CG, DHS, DOD, RESCUE 21.
|
Armament | 25mm remote operated weapon system, .50-caliber machine guns
|
Crew Size | 20 Enlisted and 2 Officers
|
Small Boat Launch/recovery | Performed safely with no more than 3 personnel
ability to safely launch and recover the cutter boat through sea state 4.
|