LPD-17 SAN ANTONIO Class
(formerly LX Class)
Ships | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
LPD Flight I | |||||||||||||
Name | # | Builder | Home | Unit | Cost $ M [2003] |
Cost $ M [2007] |
Ordered | Laid Down |
Launch | Original Contract Delivery |
Actual Delivery |
Comm | |
San Antonio | LPD-17 | Avondale | Little Creek | PHIBGRU 2 | 641.4 | 08 Apr 1997 | 09 Dec 2000 | 12 Jul 2003 | Jul 2002 | 20 Jul 2005 | 11 Jan 2006 | ||
New Orleans | LPD-18 | Avondale | San Diego | PHIBGRU 3 | 391.0 | 1,251 | 18 Dec 1998 | 14 Oct 2002 | 11 Dec 2004 | Feb 2004 | 22Dec 2006 | 05 Mar 2007 |
|
Mesa Verde | LPD-19 | Avondale | Little Creek | PHIBGRU 2 | 492.0 | 1,208 | 15 Feb 2000 | 25 Feb 2003 | 20 Nov 2004 | Aug 2004 | 28 Sep 2007 | 15 Dec 2007 |
|
Green Bay | LPD-20 | Avondale | San Diego | PHIBGRU 3 | 477.2 | 1,208 | 30 May 2000 | 07 Aug 2003 | 11 Aug 2006 | Dec 2004 | 29 Jul 2008 | 24 Jan 2009 | |
New York | LPD-21 | Avondale | Little Creek | PHIBGRU 3 | 816.6 | 1,286 | 25 Nov 2003 | 30 Aug 2004 | 19 Dec 2007 | Aug 2007 | 21 Aug 2009 | 07 Nov 2009 | |
San Diego | LPD-22 | Avondale | San Diego | PHIBGRU 3 | 1,403 | 01 Jun 2006 | 23 May 2007 | 07 May 2010 | 19 Dec 2011 | 19 May 2012 | |||
Anchorage | LPD-23 | Avondale | Sasebo | PHIBGRU 1 | 1,357 | 01 Jun 2006 | 24 Sep 2001 | 12 Feb 2011 | 17 Sep 2012 | 04 May 2013 | |||
Arlington | LPD-24 | Avondale | San Diego | PHIBGRU 3 | 1,486 | 06 Nov 2006 | 26 May 2008 | 23 Nov 2010 | 07 Dec 2012 | 06 Apr 2013 | |||
Somerset | LPD-25 | Avondale | Little Creek | PHIBGRU 2 | 1,798 | 21 Dec 2007 | 11 Dec 2009 | 14 Apr 2012 | 18 Oct 2013 | 01 Mar 2014 | |||
John P. Murtha | LPD-26 | Avondale | Little Creek | PHIBGRU 2 | 01 Apr 2011 | 06 Feb 2012 | 30 Oct 2014 | 13 May 2016 | 11 Aug 2016 | ||||
Portland | LPD-27 | Avondale | San Diego | PHIBGRU 3 | 27 Jul 2012 | 20 May 2013 | 13 Feb 2016 | 18 Sep 2017 | 14 Dec 2017 | ||||
Ft Lauderdale | LPD-28 | Avondale | Little Creek | PHIBGRU 2 | 19 Dec 2016 | 13 Oct 2017 | 28 Mar 2020 | May 2022 | 2023 | ||||
Richard McCool | LPD-29 | Avondale | Little Creek | 16 Feb 2018 | 12 Apr 2019 | 2023 | 2024 | ||||||
LPD Flight II | |||||||||||||
Name | # | Builder | Home | Unit | Cost $ M [2019] |
Cost $ M [] |
Ordered | Laid Down |
Launch | Original Contract Delivery |
Current Contract Delivery |
Comm | |
Harrisburg | LPD-30 | Avondale | TBD | 1,823 | 25 Mar 2019 | 20 | 20 | Feb 2025 | Feb 2025 | Oct 2026 | |||
Pittsburgh | LPD-31 | Avondale | TBD | 03 Apr 2020 | 20 | 20 | Feb 2027 | Feb 2027 | Aug 2028 | ||||
LPD-32 | Avondale | TBD | 1,865 | 2023 | 2024 | 2027 | 202 | 202 | 2030 | ||||
LPD-33 | Avondale | TBD | 1,878 | 2025 | 2026 | 2029 | 202 | 202 | 2031 | ||||
LPD-34 | Avondale | TBD | 2,163 | 2026 | 2027 | 2030 | 202 | 202 | 2032 | ||||
LPD-35 | Avondale | TBD | 2,046 | 2027 | 2028 | 2031 | 202 | 203 | 2033 | ||||
LPD-36 | Avondale | TBD | 2,083 | 2028 | 2029 | 2032 | 203 | 203 | 2034 | ||||
LPD-37 | Avondale | TBD | 2,174 | 2029 | 2030 | 2033 | 203 | 203 | 2035 | ||||
LPD-38 | Avondale | TBD | 2,166 | 2030 | 2031 | 2034 | 203 | 203 | 2036 | ||||
LPD-39 | Avondale | TBD | 2,264 | 2031 | 2032 | 2035 | 203 | 203 | 2037 | ||||
LPD-40 | Avondale | TBD | 2,291 | 2032 | 2033 | 2036 | 203 | 203 | 2038 | ||||
LPD-41 | Avondale | TBD | 2,411 | 2033 | 2034 | 2037 | 203 | 203 | 2039 | ||||
LPD-42 | Avondale | TBD | 2,557 | 2034 | 2035 | 2038 | 203 | 203 | 2040 |