Mission Description and Budget Item Justification: This program element funds the development of the All Source Analysis System (ASAS) Evolutionary Acquisition
(EA) system and its operational testing. ASAS is the automated support system for the intelligence and electronic warfare (IEW) functional area of the Army Battle
Command System (ABCS). It is a tactically deployable Automated Data Processing (ADP) system designed to support management of IEW operations and target
development in battalions, brigades, armored cavalry regiments (ACR), separate brigades, divisions, corps, and echelons above corps (EAC). The projects in this program
element support research efforts in the engineering and manufacturing development phases of the acquisition strategy and therefore are correctly placed in Budget Activity
5.
COST (In Thousands)
FY 1996
Actual
FY 1997
Estimate
FY 1998
Estimate
FY 1999
Estimate
FY 2000
Estimate
FY 2001
Estimate
FY 2002
Estimate
FY 2003
Estimate
Cost to
Complete
Total Cost
DB19
ASAS Evolutionary Acquisition
48496
35660
21598
23813
22695
31632
30880
30118
Continuing
Continuing
A. Mission Description and Justification: Project DB19-ASAS Evolutionary Acquisition: This project funds the development of the Army's only tactical intelligence
fusion project, the ASAS Block II Evolutionary Acquisition, within the Intelligence Fusion Project Office. The successful execution of military operations requires a
flexible and modular intelligence and targeting system that will provide tactical commanders a common view of the battlefield and a means for gaining a timely and
comprehensive understanding of enemy force deployments, capabilities, and potential courses of action. The ASAS is a ground based, mobile, command and control,
intelligence processing system. The ASAS system provides automated support to the combat commander in the areas of intelligence and collection management, all-source
target and situation analysis, single- and multi-source processing, intelligence reporting, electronic warfare, and operational security as well as automation support to the
battlefield commander's command and control.
Acquisition Strategy: The ASAS Block II development program will build upon and expand the capabilities and functionalities developed and produced in the ASAS
Block I System including conversion to the Army Tactical Command and Control System (ATCCS) Common Hardware/Software Open architecture and the OSD directed
Common Operating Environment (COE) and Modernized Integrated Database (MIDB). Additional software capabilities include enhanced intelligence and command and
control functionality, jump and degraded mode operations, enhanced communications, and improved reliability and supportability. ASAS Block II strategy maximizes the
use of Government Furnished Equipment (GFE), government and commercial Non-Developmental Item (NDI) software, reuse of proven Office of Secretary of Defense
(OSD) and ATCCS Command, Control, Communications and Intelligence (C3I) software, multiple prototype deliveries and continuous user test and evaluation
opportunities. This strategy provides early user capabilities and streamlines acquisition. Building upon experience and feedback gained from the fielded ASAS and other
tactical fusion prototypes, ASAS Block II will undergo Army Systems Acquisition Review Council (ASARC) Milestone III review in FY 99.
In March 1994, the Army was directed to accelerate fielding the ASAS capability across the force (including all Military Intelligence reserve units and National Guard
brigades) by FY99. This ASAS-Extended program accomplishes this through: reuse of proven Block I software; leveraging the traditional acquisition successes of Block I;
use of relatively low cost NDI equipment; and tailoring the existing training and maintenance support structure. The Army's intent is to keep fielded ASAS technology as
current as possible by initiating value engineering and technology insertion to the fielded ASAS, and by packaging some of the ASAS Block II software drops into
capability packages and inserting them into the fielded ASAS. These capability packages will be used with all of the fielded ASAS systems and modules. ASAS Block II
will be fielded to Army active and reserve armored cavalry regiments, separate brigades, divisions, corps, and echelons-above corps. Brigades and Battalions will receive
Collateral Remote Workstations.
FY 1996 Accomplishments:
43281
Continued ASAS Block II Evolutionary E&MD Capability Packages
-Developed and integrated ASAS Common Applications
-Developed and integrated Joint Collection Management Tools
-Incorporated DOD directed Common Operating Environment (COE)
-Add MIDB Capability
-Developed Remote Workstation-Collateral for Task Force XXI
B. Budget Acquisition History and Planning Information : Following for Block II ASAS.
Performing Organizations
Contractor or
Government
Performing
Activity
Contract
Method/Type
or Funding
Vehicle
Award or
Obligation
Date
Performing
Activity
EAC
Project
Office
EAC
Total
Prior to
FY 1996
FY 1996
FY 1997
FY 1998
FY 1999
Budget to
Complete
Total
Program
Product Development Organizations
Lockheed Martin
CPAF
Oct 93
113600
113600
41289
26748
23025
11242
10739
Cont
113043
Tobyhanna Depot
MIPR
4075
2835
1000
2200
Cont
10110
Contractor Eng
5347
4750
4239
4541
Cont
18877
Systems Eng
1300
1050
800
1200
Cont
4350
SBIR/STTR
835
835
Support and Management Organizations
Contractor Spt
2502
2100
1600
2000
Cont
8202
Gov't In House
3717
1900
1600
1900
Cont
9117
Test and Evaluation Organizations: None
Government Furnished Property
Item
Description
Contract
Method/Type
or Funding
Vehicle
Award or
Obligation
Date
Delivery
Date
Total
Prior to
FY 1996
FY 1996
FY 1997
FY 1998
FY 1999
Budget to
Complete
Total
Program
Product Development Property
CHS II
MIPR
1587
1100
0
359
397
0
3443
Support and Management Property: None
Test and Evaluation Property
Test sets CHS II
0
2872
0
758
836
0
4466
Subtotal Product Development
42876
39405
31660
17640
19077
150658
Subtotal Support and Management
6219
4000
3200
3900
17319
Subtotal Test and Evaluation
2872
758
836
4466
Total Project
42876
48496
35660
21598
23813
172443
COST (In Thousands)
FY 1996
Actual
FY 1997
Estimate
FY 1998
Estimate
FY 1999
Estimate
FY 2000
Estimate
FY 2001
Estimate
FY 2002
Estimate
FY 2003
Estimate
Cost to
Complete
Total Cost
D2FT
ASAS Operational Test
1416
3648
2447
2415
0
0
0
0
Continuing
Continuing
A. Mission Description and Justification: Project D2FT - ASAS Test and Evaluation
: This project finances the direct costs of planning and conducting testing and
evaluation of the ASAS by the Operational Test and Evaluation Command (OPTEC). ASAS is an Acquisition Category (ACAT) I system with several dedicated iterations
of Test and Evaluation (Technical and Operational) between FY 95 and FY 99. Testing and evaluations are conducted under conditions, as close as possible, to those
encountered in actual combat with typical user troops trained to employ the system. As necessary, OPTEC provides Army leadership with an evaluation of effectiveness and
suitability of the system. Project D2FT is restructured from PE 0605712A. TECOM provides the Army leadership with testing of the ASAS, and is not a new start.
Acquisition Strategy: Not applicable, see B19 above.
FY 1996 Accomplishments:
1416
Conducted ASAS Block II Technical and Operational Testing and Evaluation
Total
1416
FY 1997 Planned Program:
3559
Conduct ASAS Block II Technical and Operational Testing and Evaluation
89
Small Business Innovation Research/Small Business Technical Transfer (SBIR/STTR)
Total
3648
FY 1998 Planned Program:
2447
ACE Characterization Test and Evaluation
Total
2447
FY 1999 Planned Program:
2415
Phase IV PPQT
Total
2415
B. Project Change Summary
FY 1996
FY 1997
FY 1998
FY 1999
FY1997 President's Budget
1452
3767
2515
2514
Appropriated Value
1467
3648
Adjustments to Appropriated Value
-51
FY1998 Pres Bud Request
1416
3648
2447
2415
C. Other Program Funding Summary: Not Applicable
D. Schedule Profile
FY 1996
FY 1997
FY 1998
FY 1999
1
2
3
4
1
2
3
4
1
2
3
4
1
2
3
4
ASAS Testing
- CP-Single Source
X
X
- CP-Remote Workstation
X
X
- CP-ACE
.
X
X
- CP-Comms
X
A. Project Cost Breakdown
FY 1996
FY 1997
FY 1998
FY 1999
Operational Test , Evaluation , Assessment
1416
3559
2447
2415
SBIR/STTR
89
Total
1416
3648
2447
2415
B. Budget Acquisition History and Planning Information