Weapons of Mass Destruction (WMD)


Yongbyon Radiochemical Laboratory

The Radiochemistry Laboratory uses the “chop-leach” PUREX process used in many commercial and military reprocessing facilities in other countries. The facility is estimated to be capable of reprocessing 200-250 tons of Magnox spent fuel and extracting 100kg of plutonium annually. One end of the building has provisions for receiving spent fuel.

Construction of a reprocessing facility at Yongbyon began in 1988-1989. Some sources state that construction began in 1987, while other sources identify 1985 as the starting date. By late 1988 US satellite imagery detexted what was suspected to be a nuclear reprocessing facility under construction near the 5MW reactor at Yongbyon. The reprocessing facility separates weapons-grade plutonium-239 from the reactor's spent fuel. This large facility was key because it would have enabled Pyongyang to extract weapons-grade plutonium from irradiated fuel from both the 5- and 50-megawatt (electric) reactors.

A probable nuclear waste storage facility (nicknamed 'Building-500') was built in 1976 in close proximity to the radiochemistry lab as a waste liquid storage tank, connected to the test lab with steel pipes on the ground. With the IAEA inspection just around the corner, North Korea covered the connecting steel pipes with dirt in October, 1991, encased the waste liquid storage building with a concrete wall, transplanted trees in the areas to camouflage it, and then built a storage building above the storage tank. However, the whole process was photographed by US imagery intelligence satellites. Two underground pipe lines connect the Radiochemistry Laboratory to Building 500.

The main source of concern for the IAEA is the reprocessing plant's ability to reprocess and store plutonium. The reprocessing plant is where they extract the plutonium and this is the stuff of nuclear weapons. Without IAEA measures in place the agency is not in a position to monitor that facility and therefore cannot know whether this material is used for peaceful purposes or for weapons. The IAEA said North Korea could start removing about 8,000 spent fuel rods stored in a special pond at the Yongbyon plant. North Korea's purpose might be to move the spent fuel rods to sites around the country where they could be weaponized, in order to convince the US that there could be no pre-emptive strike. The plutonium reprocessing plant at Yongbyon could be ready to begin producing fissile material for bombs within a few months, according to the director general of the IAEA. By taking possession of the 8,000 spent fuel rods in late December 2002, the North could conceivably begin producing plutonium-based bombs in as little as six months -- by late June 2003.

On 10 January 2003 Son Mun San, in charge of Pyongyang's relations with the International Atomic Energy Agency, said that the reprocessing plant now stands in a state of "readiness." He said the reactor at the site would be up and running in a matter of weeks, roughly in line with earlier forecasts by the IAEA.

During talks in Beijing in April 2003, US officials said North Korea claimed it had reprocessed 8,000 spent nuclear fuel rods. However, US and South Korean officials said they could not verify the claim. Signs had been detected in late April 2003, but no additional activities or unusual movement had been confirmed as of early May 2003. Satellite imagery showed smoke coming from the Radiation and Chemical Laboratory reprocessing facility. Other signs of nuclear activity, such as traces of chemicals used in reprocessing or heat signatures, had not been detected. National security adviser Condoleezza Rice ordered an intelligence review which was delivered to the White House in mid-April 2003.

During the 08 January 2004 visit of the American delegation, the North Koreans allowed the Americans to tour the corridor next to the hot cells in which the reprocessing occurs. The campaign is complete; the facility is not operating now. Everything has been cleaned up and there is no radiation hazard in the corridor. Based on the tour the delegation was not able to confirm or deny that the facility operated during the first half of 2003. [Hecker testimony]

Credit: DigitalGlobe. Copyright (c) DigitalGlobe. ALL RIGHTS RESERVED. Online and news media distribution or publishing requires permission from DigitalGlobe.

New Activity at the Yongbyon Facility as of 28 January 2003

Commercial satellite images from Digital Globe depicted possible North Korean efforts to prepare for the reprocessing of spent fuel in order to extract plutonium. A pair of images acquired on 15 January 2003 and 28 January 2003 showed smoke coming from a coal fired steam plant as well as steam coming from the steam line connecting the steam plant to the plutonium reprocessing facility.

Subsequent imagery, taken one week later, suggested but did not confirm unambiguously that the coal-fired steam plant appeared to have ceased operation. This sequence suggested that the operation of the plant in early January 2003 may have been intended to evaluate the readiness of the facility to support eventual reprocessing. The later imagery, suggesting that operations may have halted, was consistent with an interpretation that reprocessing had not begun.

In the early 1990's, the Clinton Administration identified reprocessing as a "red line" activity that might provoke an American military strike against Yongbyon.

Overview of the Yongbyon reprocessing facility and the coal-fired steam plant as of 15 January 2003

Overview of the Yongbyon reprocessing facility and the coal-fired steam plant as of 28 January 2003

Leaking steam from the transmission lines and exhaust from the coal smoke stack indicate the steam plant has been recently reactivated

Exhaust can be seen from coming from the shadow of the smoke stack indicate the steam plant is in operation


Radiochemical Laboratory
Plutonium reprocessing facility

Plutonium reprocessing facility as of March 2, 2002