|
|
|
CHAPTER 6 TACTICAL PETROLEUM TERMINAL |
Section I. Concept and Primary Components
Today's highly mobile military forces require a fuel supply system that is easily set up and flexible. The fuel supply system must be able to hold large quantities of fuel. The older steel, welded pipelines have been replaced with the new lightweight aluminum, quick-coupled IPDS. The new system for fuel storage now being used with the IPDS is the TPT as shown in Figure 6-1. The TPT replaces bolted and welded steel bulk fuel tanks with lightweight collapsible fabric tanks in various capacities. These new tanks can be transported with minimal transportation assets compared to the steel tanks of the past. They can be installed in a fraction of the time of the older system. The TPT is a facility designed and packaged for rapid erection at almost any location for the receipt, storage, and dispensing of liquid fuels. Fuels can be received into the TPT from the pipeline, tank vehicles, or railcars. The TPT can dispense fuel into tank trucks, 500-gallon collapsible drums, or return fuel to the pipeline for downstream distribution. The facility can be disassembled and moved to another location or returned to an equipment storage facility. The TPT can be used as the base terminal receiving fuel from ship-to-shore operations for distribution forward through the pipeline. It can also be used as the head terminal at the end of the IPDS for fuel storage and further distribution forward by tank vehicle and hoseline to nearby airfields.
PRIMARY COMPONENTS
The standard TPT is modular with three identical Fuel Units. A standard TPT is shown in Figure 6-2. The total TPT is stored in 77 twenty foot ISO containers. A pipeline connection assembly will be issued when the TPT is to be connected to a pipeline. The primary components are discussed below.
FUEL UNIT
Each fuel unit consists of three Tank Farm Assemblies, with two 210,000-gallon collapsible fabric tanks each, a Tanker-Truck Receipt Manifold, a Fuel Dispensing Assembly, a Transfer Hoseline Assembly, six Fire Suppression Assemblies, an Optional Tank Configuration and a Fuel Unit Support Assembly. A total of 24 ISO containers are used to store one Fuel Unit.
PIPELINE CONNECTION ASSEMBLY
The pipeline connection assembly is required if fuel is to be received or issued to the pipeline. It consists of the following major components.

Figure 6-1. Tactical petroleum terminal

Figure 6-2. Standard tactical petroleum terminal
Section II. System Components
THE 210,000-GALLON FABRIC COLLAPSIBLE TANKS
The 210,000-gallon capacity, fabric collapsible, fuel storage tanks also known as BFTA are complete with fittings, accessories, and emergency repair items. The BFTA as shown in Figure 6-3. For more information on the 5,000 barrel tank see Chapter 22.
THE 50,000-GALLON FABRIC COLLAPSIBLE TANKS
The eight 50,000-gallon fabric collapsible tanks furnished with the TPT are complete with fittings, accessories, and emergency repair items. The 50,000-gallon fabric collapsible tank is shown in Figure 6-4. For more information on the 50,000-gallon tank, see Chapter 22.
THE 600-GPM HOSELINE PUMPS
The 600-GPM hoseline pumps are wheel-mounted, diesel engine-driven, self-priming, air-cooled, centrifugal units. The pump is close-coupled to a turbo-charged diesel engine which can be operated manually or automatically through an electric governor. Controls regulating either mode of engine operation are contained in the control panel mounted directly over the pump. The pump and engine are mounted on a two-wheel trailer assembly with internal towing bar and leveling supports. The 600-GPM hoseline pump has a discharge head of 350 feet and is rated at 2400 RPM. The 600-GPM hoseline pump is designed to--
THE 350-GPM TRANSFER PUMP
The 350-GPM transfer pump can be field transported with a tow vehicle for short distances. A long distance move has to be made with a transport vehicle. This pump unit is used in the contaminated fuel module with the TPT. The pump can also be easily moved and used as required in other locations and services. Figure 6-5, shows a 350-GPM pump. For more information on the 350-GPM pump see Chapter 20.
METER/STRAINER ASSEMBLY
The four meter/strainer assemblies are aluminum single-case, positive displacement meters with 6-inch double-groove connections. A meter/strainer assembly is shown in Figure 6-6. The maximum working pressure is 150 PSI. The maximum flow rate is 800 GPM. A large numeral reset counter mounted on the meter reads out in U.S. gallons. A 0 to 1500 GPM flow indicator is included as an integral part of the assembly. The strainers included in the skid-mounted assembly upstream of each meter have 6-inch cast steel strainers with 40-mesh stainless steel baskets with 6-inch double-groove connections. The strainers have a 150-PSI working pressure. An air release head is mounted on the strainer. The meters and strainers are mounted together on a skid for easy handling and a firm setting. Three of the four meters measure fuel into the fuel units. The other meter is supplied for installation in the hoseline return to the pipeline or to a user facility. The strainers are to protect the meter assemblies.
FILTER-SEPARATORS
There are twelve 350-GPM filter/separators in the system. The filter/separator is shown in Figure 6-7. For more information on the 350-GPM filter/separator see Chapter 21.
PRESSURE-REGULATING VALVE ASSEMBLY
There is one pressure-regulating valve assembly in the TPT. It consists of a steel skid-mounted, 7-inch pilot-operated, pressure-regulating valve. The valve is controlled so that it will not open unless the upstream pressure is 50 PSI or above. Downstream pressure is limited to a maximum of 125 PSI. The pressure-regulating valve assembly has a 7-inch flange to 6-inch IPDS single-groove adapters on each side. Pressure gages are installed in the control manifolding to show pressures on both the upstream and downstream sides of the valve. To protect the pressure-regulating valve from debris in the pipeline, a sleeve strainer is supplied to insert into the scraper receiver at the end of the pipeline supplying fuel to the TPT. The pressure-regulating valve limits pressure into the TPT switching manifold to below 125 PSI and maintains a pipeline pressure of 50 PSI or above in operation and 50 PSI on shutdown. The pressure-regulating valves are supplied as part of the switching manifold supply.
THE 6-INCH PRESSURE CONTROL VALVE ASSEMBLY
There are three 6-inch pressure control valve assemblies in the TPT. These pressure control valves are back pressure relief/back pressure regulators set at 30 PSI. The unit is skid-mounted and fitted with double-groove adapters. These back pressure controllers are installed in the recirculating hoselines from the fuel-dispensing assembly back to the tankage to maintain dispensing pressure at a maximum of 30 PSI. These control valves are supplied as part of the dispensing assembly.
THE 1 1/2-INCH PRESSURE CONTROL VALVE
There are six 1 1/2-inch pressure control valves in the system, each set at 5 PSI. The end fittings are 1 1/2-inch with cam-lock couplings. These valves are part of the two 1 1/2- inch dispensing points at each dispensing assembly, designated primarily for filling nonvented 500-gallon collapsible drums. They limit the loading pressure of the drums to 5 PSI. The valves are supplied as part of the dispensing assembly.
FUEL SAMPLING ASSEMBLY
There is one fuel sampling assembly in the TPT as shown in Figure 6-8. It consists of a pipe section with double-groove ends, a 1/2-inch tap into the line, a 1/2-inch ball valve, a 1/2-inch needle valve, a goose-neck spigot, and a catch basin. A set of hydrometers is supplied with the fuel sampling assembly. This assembly is located on the inlet line to the switching manifold for each TPT to permit periodic sampling and quality control.
RANGE POLES
The TPT is supplied with 36 range poles Range poles are used to roughly estimate the quantity of fuel in the fabric collapsible tanks in the TPT. Each pole is made of two sections of steel tubing of nominal 1 1/8-inch outside diameter and of nominal 0.032-inch wall thickness. The pole is 6½ feet long with a hardened steel point permanently fastened to the lower end. The two pole sections are locked together with a spring catch. Both sections are fitted in a two-pocket cotton duck carrying case. Two poles are supplied for each BFTA. They are driven in the berms on opposite sides of the tank and a cord is stretched across the tank. The cord should be set at 6 feet 8 inches up from the base of the tank, which is the full level. Attaching a readily visible object, such as a ball, to the cord over the center of the tank makes estimating tank height easier.
NESTABLE CULVERTS
Nestable culverts are 12-inch corrugated culvert pipe. Hose can be routed through these nestable culverts for protection from traffic weight and any other effects which might cause hose damage. Nestable culverts can also be used to protect the hose from rock or from ballast and cinders under a railway spur. The culverts are part of the TPT support assembly.
FLOODLIGHT SETS
There are six floodlight sets in the TPT. A floodlight set is a wheel-mounted diesel engine-driven generator with an integrally mounted telescoping tower carrying four high intensity lamps. One set can light 7.5 acres. It has a generator set that is powered by a 7-cycle, air-cooled, multifuel engine. It carries a fuel capacity for 18 hours. The setup locations for the six sets are determined by the requirements for the particular TPT site. Particular attention should be given to the lighting of fuel-dispensing areas, fuel receipt areas, and heavy operating areas around the pumps and the switching manifold. There is one portable petroleum aviation fuel contamination kit supplied with the TPT.
FIRE-SUPPRESSION EQUIPMENT
Each TPT is furnished with 19 sets of fire-suppression equipment. Each set contains a skid-mounted dry chemical and AFFF fire extinguisher with a remote wheel-mounted hose cart; Purple K dry chemicals; liquid foam; Kevlar hoods, gloves, coats, boots and trousers. The particular TPT layout determines where fire-suppression equipment is placed. Whatever locations are selected, they should be readily accessible to the operators and the fire suppression crew and. These locations should be clearly flagged with prominent signs. Clothing should be stored in a dry, readily accessible building or container.
HOSE, FITTINGS, AND VALVE ASSEMBLIES
For the most part, the hose, fittings, and valves are used to interconnect the equipment described in Table 6-1, pages 6-33 and 6-34, and Table 6-2. They are preassembled into convenient units that make installation more efficient. There are 12 of these assemblies in the TPT system.
STORAGE AND TRANSFER SYSTEMS
The equipment described previously in this section make up the storage and transfer systems described below. Installation of these components is covered in Section III of this chapter.
Tank Farm Units
The tank farm units are the primary storage units for fuel in the TPT. Fuel is pumped directly to the fuel-dispensing assembly from the storage tanks of any tank farm unit assembly. Fuel can be pumped from the tank farm unit assembly to another tank farm assembly in the fuel unit or to an associated pipeline or hoseline system if required in the particular operating area. A tank farm unit consists of two BFTAs, one 600-GPM hoseline pump, three 6-inch aluminum Ts, seven 6-inch gate valves, coupling adapters, and enough 6-inch hose assemblies (suction and discharge) to connect the components. Range poles are provided to estimate the amount of fuel in the collapsible tanks. The maximum distances in the fuel tank spacing is depends on the available hoseline and the minimum distances by safety considerations. The hoseline arrangements shown are examples. Other arrangements may be more suitable for certain situations.
Contaminated Fuel Unit
The contaminated fuel unit is used to store fuel that has become mixed or contaminated during transport to the TPT. This includes the interface which occurs in the pipeline batching and the fuel/water interface at the time of the initial purge and fill operation. Tank vehicle connections are provided so the contaminated product can be transported for blending or disposal. The contaminated fuel unit consists of two 50,000-gallon fabric collapsible tanks, a 6-inch aluminum T, a 350-GPM pump, a 3-inch ball valve assembly for loading tank vehicles, two 6-inch aluminum gate valve assemblies, and hoses and fittings to connect the components. Road access is required to allow the unloading of the 50,000-gallon tanks with tank vehicles.
Transfer Hoseline Assemblies
Three transfer hoseline assemblies are provided with the TPT. Each assembly provides the connection between the switching manifold, the tank farm units, and the return manifold to the pipeline system. Valve assemblies in the transfer hoseline allow the switching of fuel between the tank farm assemblies. Each transfer hoseline assembly has about--
The hoseline is provided in flaking boxes with two 250-foot lengths per box. Four flaking boxes can be stacked on the bed of a 5-ton cargo truck and flaked out continuously.
Fuel-dispensing Assemblies
Three fuel-dispensing assemblies come with each TPT. The fuel-dispensing assembly is used to issue fuels from a TPT. There is one fuel-dispensing assembly for each of the three fuel units. Using a tank farm unit as its pumping source and bulk holding point, the fuel-dispensing assembly allows fuel loading to tanker trucks and 500-gallon collapsible drums. The major components of the fuel-dispensing assembly include three 350-GPM filter/separators, three probe adapters for the portable fuel contamination testing kit, six loading points for loading tank trucks, and two 500-gallon collapsible drum loading points. About 900 feet of hoseline and valves of various sizes are used to connect the components of the dispensing assembly.
Tank Vehicle Receipt Manifold
The three tank vehicle receipt manifolds provide the TPT with the valves, hoselines, and fittings necessary to allow the offloading of petroleum products from tank vehicles if required. A bypass line around the pump is provided, allowing the manifold to be used to load tank vehicles to supplement the fuel-dispensing set, if required. Depending on system requirements, the manifold can be installed fully or partially. Each of the manifolds has four tank vehicle unloading stations using 7-inch butterfly valves with 3-inch quick-disconnect couplings. A 600-GPM hoseline pump from the TPT support assembly is used with each manifold. The truck unloading valves are connected to 7-inch suction hose which is connected to a 6-inch suction hose leading to the pump. The bypass around the pump is made up of 6-inch discharge hose. Three 6-inch aluminum T assemblies and four 6- x 6- by 7-inch aluminum Ts provide the necessary connection for the manifold. To connect the receipt manifold to the TPT and maintain a safe separation between the components, 250-foot long 6-inch hoseline sections from the transfer hoseline kit can be used as needed.
Switching Manifold
The switching manifold controls the flow from the associated pipeline to the tank farm units and the contaminated fuel unit. It also controls the flow from the tank farm units to a pipeline or a user facility. The manifold is made up of two parts; the receipt manifold and the return manifold. The receipt manifold receives fuel from the associated pipeline and tank vehicle receipt manifold and distributes the fuel to the tank farm unit. The valves in the switching manifold allows cuts between batches of different fuels arriving at the TPT from the associated pipeline, and, if necessary, from the tank vehicle receipt manifolds. The interface goes to the contaminated fuel unit. The return manifold receives fuel from the tank farm units and directs it to the associated pipeline or hoseline user facility. The switching manifold consists of--
Only two of the 6-inch single-groove to double-groove adapters are used in the switching manifold, one in the receipt manifold and the other in the return manifold. The other adapters are available for use in modifications that may be required in certain operating areas. Ideally, the switching manifold should be as compact as possible; however, certain situations may require extra length. The switching manifold setup may vary with site conditions and service requirements.
Optional Tank Configuration
The optional tank configuration can be used to replace or supplement the normal BFT's in the tank farm units or provide for special storage as required. There is one optional tank configuration supplied with each TPT. Each tank configuration contains up to six BFTAs, six 7-inch aluminum Y-assemblies, six 7-inch aluminum gate valve assemblies, and four 7-inch aluminum tee assemblies. Connections between components are made with 7-inch hoseline assemblies, both suction and discharge. Note that each BFTA comes with a 10-foot section of 7-inch suction hose and a 7-inch aluminum gate valve which are incorporated into the hoseline layout. Each tank is also supplied with a 4- to 6-inch adapter and a 6-inch cam lock to double-groove adapter to allow the tank to be used separately. Two 6-inch Ts are provided to be used as required.

Figure 6-3. The 5,000 barrel fabric collapsible tank

Figure 6-4. The 50,000 gallon fabric collapsible tank

Figure 6-5. The 350 GPM pump

Figure 6-6. The meter/strainer assembly

Figure 6-7. Filters separator, liquid fuel

Figure 6-8. Fuel sampling assembly
Section III. Tank Farm Installation
LAYOUTS
The layout requirements for a TPT must be flexible to fit the particular site and service. These arrangements may be modified for practicality at a particular site. The objective in any equipment arrangement is to provide for efficient and safety in operations. As a general rule, the TPT should be arranged for maximum spacing between tank farm units and fuel units to the extent the particular operating site requirements and hoseline availability permit. This will provide for the highest level of safety for the equipment and the operating personnel without adversely affecting operating efficiency. Specific area service requirements may also affect layout and spacing. For detailed information on TPT layout, refer to FM 5-482.
Typical TPT Layouts
A typical TPT layout is shown in Figure 6-9. This layout is an example of a TPT which has been arranged to make full use of the transfer hoseline provided for wide spacing between fuel modules. The layout assumes that adequately sized property is available and the equipment is wide spaced for security reasons. In many locations, due to terrain or operational situations, the layout may have to differ substantially from that shown. In a relatively secure area or when property available is limited, it will be appropriate to arrange the system with much closer spacing between fuel units and equipment. A typical close-spaced TPT layout is shown in Figure 6-10. It is not imperative to lay out tankage in a straight line. Security demands or terrain may dictate otherwise. Road access should always be considered when planning a TPT site. Ideally, there should be a limited number of entry points into the TPT area, with each entry point having a control or checkpoint to monitor and route traffic in and out of the area. A road that can support two-way tank vehicle traffic should run along the perimeter of the TPT site. This road would give access to each fuel unit's fuel-dispensing assembly. In the fuel-dispensing areas, the roadway should be widened to at least 40 feet. Through traffic should be routed away from the fuel-dispensing area. Similar fuel handling areas are needed for the contaminated fuel module and the tanker truck receipt manifolds. Secondary roads should be made for MHE, pumps, fire-suppression equipment, and maintenance equipment to be moved. Under-road culverts through which hoselines pass allow vehicles to cross over the hoselines without damaging them. These culverts are installed as necessary. The hoseline suspension kit may also be used to provide for crossing under the hoseline. Access must be provided to the pumps and near each tank berm. An important point shown on the general TPT layout is the location of the fire-suppression equipment. A wheel-mounted fire extinguisher should be located near each tank berm, at each fuel-dispensing assembly, at each tank vehicle receipt assembly, and at the contaminated fuel module. Extra units should be stationed at a central point ready for use anywhere in the TPT. Covered shelters or containers for housing the Kevlar fire-fighting clothing and extra fire fighting supplies should be provided at central, easily accessible locations around the TPT. The 20-pound hand-held fire extinguishers should be distributed and located at each pump, each floodlight set, each fuel-dispensing area, and other operating areas at the discretion of the operating supervision. Personnel must know where all fire-fighting equipment is located at all times to prevent confusion in an emergency. Readily visible signs flagging the locations of fire extinguishers would be helpful. The floodlight sets should be placed to give light to the fuel-dispensing areas, fuel receipt areas, and heavy operating areas around the pumps and the switching manifold.

Figure 6-9. Typical wide-spaced TPT layout

Figure 6-10. Typical closed spaced TPT layout
SITE SELECTION
Using both aerial and ground reconnaissance, the Army will probably preselect a specific site or at least a desired area in which to set up the TPT. (Refer to FM 5-482 for detailed information on site selection). There is not a completely ideal site. When picking a site, a decision must be made. When evaluating the site, these factors must be considered in site selection.
SITE PREPARATION AND EARTHWORK
Final site selection and subsequently site preparation and earthwork must be based on the layout discussed in the previous paragraph. The site will probably not be ideal; therefore, there must be some give and take between the layout and site preparation results. Site preparation work should be based on a grading plan that reduces cut and fill operations even if the plan is roughly prepared in the field. The plan should be based on actual on-site elevations and survey, observation of obstructions, and knowledge of the types of soils that appear to be present. The first step to prepare the site is to cut an access road to the site unless one already exists. Stake out the area that must be cleared. Mark where the major components will be located. Cut, grub, doze, or if necessary, blast major obstructions; for example, trees, boulders, or buildings. Clear and grade the areas where a fuel unit will be located, transfer systems installed, roadways built, and loading and unloading facilities installed. There must be good drainage from the site. Plan cuts and fills so that the volume of cut soils roughly equals the required fill for low spots, tank berms, and roadways. If the area is fairly flat and requires only minimal grading, the materials for roadways and tank berms can come from a borrow pit near the site which can, if desired, be converted to a reserve water storage basin. Keep in mind that the major equipment, most particularly the BFTAs, should be set on virgin or cut soils, if possible, rather than on fill. If tankage must be located on a filled area, the fill must be compacted as it is placed. Compaction after a deep fill has little effect. When extensive fill is required, the slopes must be such as to prevent slides and reduce erosion. As a general rule, there should be no slopes greater than 2:1 (approximately 25° ) in sandy or loamy soils.
Road
Road must be fully compacted and have good drainage. If possible, they must have at least a surface of gravel or crushed rock. Each side of the road should have an adequate swale or ditch for good drainage. Drainage culverts should be placed as required. The road, swale, ditch, and drain culvert requirements will depend on the site and anticipated rainfall. Roads must be constructed to permit ready access to all areas for installation, operation, fuel loading and unloading, and fire fighting.
Tank Pad and Berm Construction
Proper tank pad and berm construction is most important to provide for tank operation and protection from spill or a fire resulting from the spill. Tank pads are preferably constructed of a loamy or clay soil containing some sand so that a smooth area can be graded and hold its shape. The longest slope should be approximately 1° (degree) from horizontal. The low point should be where the tank drain will end up when the tank is unrolled. A small ditch and a basin for the tank drain line and drain valve can be excavated by hand at the time the tank is unrolled. The low point permits maximum pump out of the tank and drainage through the drain line. The base of the tank pad area must be virgin, cut, or well compacted soil. To avoid damage to the tank bottom, sticks, stones, or sharp objects must be removed before the tank is installed. Berms may be constructed before, after, or simultaneously with tank pad construction, depending on job conditions. The tank must be cleared on any rocks or clumps, that roll on to the tank pads during berm construction. Tank pad rough grading should be completed before berm construction and should be finished after berm construction. The preferred materials are soils containing a fairly high clay content to hold shape and sealing. The berm should be compacted as it is constructed. An alternate to graded berms are sandbag berms as described earlier. If a berm drain is installed, as recommended, it should be laid in a hand-cut trough after the first layer of berm is placed and before the second layer is placed. Care must be taken to avoid damage by the equipment constructing the berm. This can best be handled by not installing the valve until after the berm is completed and giving the berm drain pipe plenty of cover. When the drain valve is installed, it should be left closed, or the integrity of the berm has been compromised. Berm liners should be installed after the pad and berm are completed. A light layer of soil (without rocks) may be spread over the liner to protect and hold it in place.
Pads for Other Equipment
To the extent possible, all operating equipment should be set on virgin or cut soils rather than fill. If a filled area cannot be avoided, it must be well compacted. This is particularly important for the pumps and floodlight sets. If available, it is recommended that the areas on which equipment is placed be covered with a 6 to 7-inch layer of coarse gravel or crushed rock. The gravel or crushed rock should extend out and around the equipment for several feet. This will provide a high and dry area from which to operate and maintain the equipment. If coarse gravel or crushed rock is available, place it around often-operated valve stations.
EQUIPMENT INSTALLATION
This section lists the equipment in the recommended installation sequence. Major equipment is installed first, followed by major fittings and valve assemblies, and then by the interconnecting hoselines. The transfer hoselines can be laid as soon as the location of the switching manifold is Setup. When equipment, valves, fittings and hoses are being installed, internal cleanliness is very important. Sand, rocks, rags, tools, or clothing left inside will block the fuel flow or damage equipment. Leave protective caps and plugs in place until actually ready to make a connection. Before closing a joint, inspect the parts being assembled and remove any foreign material.
FLOODLIGHT SETS
Install the six floodlight sets that come with the TPT as soon as possible. Sufficient light must be available for night TPT installation. Install the floodlight set according to the manufacturer's manual. The location of the sets will depend on characteristics of the field site.
BFTA
Make sure that the tank pads are free of sharp objects and smooth before rolling out the tanks. The drain on the tank should be located over the low spot in the pad and the top fitting intended for pump suction is the one closest to this drain. Cut a small trench for the drain hose before unrolling that end of the tank under which the drain hose will pass. After cutting the trench, install the drain hose and valve assembly. Service, install on assigned pads, and assemble all components of the BFTAs as described in the TM overpacked with the tanks. Six BFTAs are supplied per fuel unit and 18 per TPT.
The 50,000-Gallon Fabric Collapsible Tanks
Install the 50,000-gallon tanks the same as for the BFTAs.. Service, install on assigned pads, and assemble all components IAW TM 5-5430-210-12. Up to six tanks are in the optional tank configuration and two per contaminated fuel unit.
The 600-GPM Hoseline Pumps
Three 600-GPM pumps come with each fuel unit and nine per TPT. One 600-GPM pump come with the tank vehicle receipt manifold and three per TPT. The TPT comes with three spare 600-GPM pumps for use as needed. Ground the pumps when they are installed. Install the 600-GPM pumps as far from the collapsible tanks as possible without deforming the tank top or causing long unsupported lengths of suction hose. The suction hose should lay on the ground without strain on the tank or pump. Pump engines and exhaust fumes are hot. For safety reasons, keep them as far as practical and distance from the tank will enhance safety. Install, service, and prepare the 600-GPM hoseline pumps for operation IAW the technical manual overpacked with each pump.
The 350-GPM Transfer Pump
Install the one 350-GPM transfer pump with the contaminated fuel unit. The same preparation procedures are used as with the 600-GPM pump. Install, service, and prepare the 350-GPM transfer pump IAW TM 5-4320-226-14.
Meter Skid Assemblies
Install the meter skid assemblies. Three are supplied per fuel unit supply hoseline and one per common header to associated pipeline or hoseline system. Service and prepare the assemblies IAW the manufacturer's manuals overpacked with the equipment. Ground the meter skid assemblies when they are installed.
Filter Separators
Install, service, and prepare the filter/separators IAW TM 5-4330-211-12. Ground the filter/separators when they are installed. Three filter/separators are installed with each fuel-dispensing assembly and nine per TPT.
Tank Farm Unit Assembly Hoselines, Valves, and Fittings
The following installation and assembly procedures are based on the shared berm layout shown in Figure 6-11.
|
NOTE: When installing coupling clamps and gaskets, liberally apply grease to the gasket and the inside surface of coupling clamp to prevent pinching during installation. Then, pull the coupling gasket over one grooved end of each mating joint. Ensure the gasket is properly positioned over the full circumference of the sealing surfaces. Position the coupling clamp over the gasket. While maintaining alignment of mating parts, lock the coupling clamp securely. Make sure all hoselines, fittings and valves are clean internally. Foreign materials may stop operations and damage equipment. |

Figure 6-11. Tank farm (Module) assembly layout, typical layout with separate berm constuction, hose, valve, and fitting installation
Check the position of the 600-GPM hoseline pump
CONTAMINATED FUEL UNIT HOSELINES, VALVES, AND FITTINGS
The following assembly and installation procedures are based on the contaminated fuel module layout. Make sure all hoselines, fittings, and valves are clean internally. Foreign materials may stop operations and damage equipment.
TRANSFER HOSELINE ASSEMBLY, VALVES, AND FITTINGS
One transfer hoseline assembly is supplied with each fuel unit; three assemblies per TPT. The transfer hoseline set assemblies are crated in a partially assembled condition to ease packaging and shipping. Some assembly is required to place the Ts and gate valve assemblies in operating condition before installation. The following installation procedures are based on the transfer hoseline assembly layout. Make sure all hoselines, fittings, and valves are clean internally. Foreign materials may stop operations and damage equipment.
Fuel-Dispensing Assemblies
One fuel-dispensing assembly is supplied with each fuel unit; three per TPT. Make sure all hoselines, fittings, and valves are clean internally. Foreign materials may stop operations and damage equipment.
Installation of Coupling Clamp and Gasket
|
NOTE Liberally apply grease to the gasket and the inside surface of the coupling clamp to prevent pinching during installation. Then pull the coupling gasket over one grooved end of each mating joint. Ensure the gasket is properly positioned over the full circumference of the sealing surfaces. Position the coupling clamp over the gasket. While maintaining alignment of mating parts, lock the coupling clamp securely. |
TANK VEHICLE RECEIPT MANIFOLD HOSELINES, VALVES, AND FITTINGS
The tee assembly used in the tank vehicle receipt manifold is crated in a partially assembled condition to facilitate packaging and shipping. Some assembly is required to place the unit in operating condition prior to installation. Make sure all hoselines, fittings, and valves are clean internally. Foreign materials may disrupt operations and damage equipment. The following installation procedures are based on the tank vehicle receipt manifold shown in FM 5-482.
SWITCHING MANIFOLD
The following assembly and installation procedures are based on the switching manifold shown in FM 5-482. Make sure all hoselines, fittings, and valves are clean internally. Foreign materials may disrupt operations and damage equipment.
|
CAUTION Upstream (back pressure) and downstream (reduced pressure) pressures are preset as intended to 50 PSI upstream minimum and 125 PSI downstream maximum. DO NOT bypass upstream or downstream pilots without supervisory instructions. Bypassing the downstream pilot can result in pressure or reduced pressure control settings without operating authority approval. |
OPTIONAL TANK CONFIGURATION HOSELINES, VALVES, AND FITTINGS
The following assembly and installation procedures are based on the optional tank configuration. Make sure all hoselines, fittings, and valves are clean internally. Foreign materials may disrupt operations and damage equipment.
FIRE SUPPRESSION EQUIPMENT
Check out, service, and install the fire suppression equipment in accordance with the overpacked instructional manuals and specific instruction of operating management. The wheel-mounted dry chemical/AFFF units should be located such that they can be readily put into service at the fuel storage units, fuel-dispensing sets, the switching manifold, the contaminated fuel module, and the tank vehicle offloading area. U.S. Marine Technical Manual 07661B-14/1 contains instructions on the dry chemical/AFFF unit. The 20-pound fire extinguishers should be placed according to the direct operating authority. It is recommended that one be placed near all pumps, floodlights, and loading spots. Placement of the extra extinguishers not specifically located should be just outside the immediate operating area in a highly visible location.
|
CAUTION Thoroughly check out all fire suppression equipment at the time of locating in the unit. Extinguishing equipment must be charged and in working order. Clothing must be clean and in good condition. Clearly mark storage areas for fire suppression equipment and educate all personnel on its location and use prior to bringing flammable fuels to any part of the system. |
SAFETY AND NO SMOKING SIGNS
Prepare and install appropriate safety and no smoking signs at designated locations for the specific site. No smoking is allowed within 50 feet of any system or equipment containing flammable fuels. Set up "No Smoking" signs just outside of this boundary area. Set up "No Smoking" signs around fuel-dispensing and fuel receipt areas. To minimize the threat of smokers, create a well- marked "Smoking Permitted" area well away from the facilities and make that the only area in which smoking is permitted. This area should not be lower than or down wind of the fuel handling area. Set up "Shut Engine Off" signs at fuel-dispensing and receiving areas. Set up "Disconnect Hose Before Moving Vehicle" signs at dispensing and receiving areas. Place the following safety signs at appropriate locations:
PRESSURE TEST SYSTEM
The TPT system, particularly the hose systems, should be pressure tested before it is placed in operation. The purpose of the test is to prove the integrity of the system, by locating leaks, blockages, and installation faults. The test is not to prove the strength of the materials; therefore, test pressures are limited to the maximum design operating pressures. A complete test is recommended; however, it is understood that some deviation may be required due to specific site conditions and immediate operating needs. The extent of pressure testing and the test media used is up the operating authority.
Test Medium.
Tests can be conducted with air, water, or fuel. The medium used is dependent on the conditions at the specific site and installation/operations management decision. From a safety standpoint, a water test is the safest medium. However, it has certain disadvantages, such as the difficulty of removing all water from the system. Air tests should not be conducted at pressures in excess of 50 PSI and, therefore, cannot be used to locate leaks that occur at higher pressures. A fuel test can be handled safely if care is taken and the method will save time and is considered adequate. If a fuel pressure test is conducted, it can be handled in conjunction with the purge and commissioning program. After the test medium has been decided and the line to be tested is filled, bring the test pressures up and hold them long enough to thoroughly inspect the system for leaks and faults. The test pressure is then taken off the system and the leaks and faults corrected. The system must be retested after these corrections are made. A longer period of holding the system at test pressures may be opted for at the discretion of the operation/installation authority.
Maximum Test Pressures.
Testing is for locating leaks, loose connections, blockage in the system, and flaws in construction. Testing will prove the integrity of the facility prior to regular operation. The test pressures listed below are less than maximum pressures. The operating authority may designate lower pressures at their option. When testing fabric collapsible tanks, no pressure is allowed other than static liquid head plus .10 PSI. Make sure the tank vent is open and clear. The tanks may be filled to approximately 85 percent of their design capacity with fuel. All inlet and outlet valves must be closed and blanked off. Inspect for leaks. If any leaks develop, the tank must be emptied and repaired, tank refilled, and inspected for leaks. If sections of pipeline, connected with a suction hose, are being tested to higher pressures, the suction hose must be blanked off and tested separately. Pressure tests may be performed using water, fuel or air. The maximum test pressures for 7-inch pumps and smaller discharge hoses, valves and fittings are 150 PSI when testing with water or fuel. The maximum test pressure for suction hose are 150 PSI when testing with water or fuel. The maximum test pressure when testing with air is 50 PSI for 7-inch pumps, smaller discharge hoses, valves and fittings, and suction hoses.
Maximum test pressures for 6-inch pump discharge and transfer hose, valves, and fittings are:
|
NOTE Certain fittings are rated at 75 PSI maximum. These items are not to be exposed to test pressure above 75 PSI. They can be isolated or removed during the test. |
Test Pressure Source.
Test pressure can be supplied from any source capable of holding the test pressures. The 600-GPM hoseline pump is suitable for testing with water or fuel. An air compressor must be available to proceed with an air pressure test. All test media, water or fuel, if incompatible with the particular fuel service for which the system is intended, must be drained from the system before it is placed in service.
|
CAUTION Under no conditions are air pressure tests to be used on fabric collapsible tanks. Remove all connecting hoses to tanks to prevent this. Pumping air into fabric tanks can exceed the tanks venting capacity, inflate, and possibly rupture the tanks. |
Preparation for Testing.
Before the test is begun, actions should be taken to ensure that the test runs smoothly. Be certain that there are sufficient gaskets, repair equipment, etc. available. Locate fire suppression equipment near the testing area and be sure that it is in operating condition (when testing with fuel). Make sure to have a tank vehicle and drums available, in case a section has to be drained and have shovels amd materials available to dig and line a pit in case there is a break and spill (when testing with fuel). Have caps and plugs available to blank off the section under test. Valves in the system may be used to isolate hose sections as necessary. After all the TPT equipment, hose, valves, and fittings are physically connected, there should be a meeting of all responsible personnel connected with the testing program. Each phase of the test plan including a communication plan shall be discussed and reviewed. Prior to filling a section for test, a final check should be made to verify:
Fuel Test Procedure.
Adjust valves so that fuel can be pumped through the section under test, exhausting air. Slowly pump fuel into the system, not to exceed a flowrate of 200 GPM. When all air is evacuated, close the discharge valves, fill the section with fuel, and stop the pump. Check all connections for leaks. If no leaks are found, start the pump and raise the pressure to 25 PSI, stop the pump, and check the gages. If no leaks are found and gages are okay, start the pump and raise the pressure to the selected test pressure. Stop the pump, check for leaks, and hold the test pressure for a period long enough to inspect the entire system under test. If leaks are found, relieve the pressure, drain the leaking section, and make repairs, adjustments, or replacements as necessary. At that point, pressure up the section again to test the repairs made.
CULVERTS
Install culverts at road crossings where hoselines cross under an area where vehicle traffic is planned. Erect signs advising drivers that there is a crossing at that point. Place "Danger, Hoseline Crossing" signs where they are needed. Hoselines can be easily damaged by vehicles crossing them. Be sure well covered culverts are installed where traffic is expected. Permit no vehicles to cross unprotected hose.
HOSELINE SUSPENSION SETS
Install suspension sets at road crossings, small streams, and other areas where a nestable culvert may not be used.
RANGE POLES
Each BFTA is supplied with two range poles, 36 per TPT. Install the range poles and cords at all BFTA sites.
PAINT SYSTEM
Paint all metal parts that have not been previously painted or anodized to acceptable standards or that have deteriorated in shipment and storage. Prepare the surfaces and apply primer in accordance with MIL T-704, Type A and finish coat per MIL-E-52798, Type I, sand color.
EQUIPMENT AND LINE IDENTIFICATION MARKING
Mark all major equipment, tanks, pumps, meter-strainers, filter- separators, operating valves, and pump pressure gages with the equipment identification numbers. for efficiency and safety in operations. Equipment that has large enough surfaces should be stencil painted using a color that contrasts well with the background. Small valves and other small equipment can be marked with metal strips bearing the equipment number and wired in place. This should be done after installation to make sure numbering is correct. Consider marking hoselines and pipelines with color-coded bands and direction of flow arrows as described in MIL STD 161. Care must be taken to correct the marking if the service of a marked section of hose is changed.
AREA CLEANUP
The installation personnel must clean up the area prior to starting operations. They must remove all construction dregs, obstructions, and boxes. Unused materials, hose, fittings, and the like should be stored in a specific area for future use. All dust caps and plugs should be boxed and marked for use in the event the system is disassembled for shipment. The ISO container supplied with the TPT for ISIL parts may be used for this purpose.
FINAL INSPECTION
It is important to make a final inspection using a checklist arranged essentially in the order of this installation procedure. This should be done by supervisory and management personnel from both the installation and operating groups. The following inspection points should be emphasized:
Correct the faults found in the inspection and then reinspect. Do not proceed with the operations until all points affecting the integrity and safety of the system are corrected.
Section IV. Terminal Operations
OPERATIONS ORDER
Each terminal prepares its own operation order. It is based on the daily pumping order issued by the chief dispatcher. The daily pumping order is covered in Chapter 9. The contents and format of the terminal operation order are described below.
|
NOTE With the introduction of JP-8 as the single fuel on the battlefield, batching and scheduling may not be needed in military pipelines and hoselines. However, for purposes of this manual, batching and scheduling procedures and fixed tankage will be discussed in the event multifuel pipelines are required or commercial facilities are operated by Army personnel. Motor gasoline and diesel fuel will also be discussed in the event commercial facilities are operated by Army personnel. |
Contents.
The written operation should include the following for each operation:
Format.
An operation order should include standard procedures, general orders, and special orders. These are discussed below.
GENERAL OPERATING RULES AND PROCEDURES
Terminal design, product demands, and the nature of each receipt or issue of product determine specific operating procedures. However, there are certain rules and procedures that must be followed at any terminal for efficient operation and safety. They are described below.
Personnel Assignments and Training.
All personnel must be trained to know the entire system so that each person will be familiar with what the others are doing. Only experienced and qualified personnel should be assigned to independent work. Each person must receive complete operational instructions and must understand them. Personnel should be trained to anticipate emergencies so that they can cope with various situations.
Operating Rules.
There are general operating rules that must be followed. They are listed below.
Receipt of Product.
There are a number of general procedures that need to be followed when product is pumped into tanks. These procedures are described below.
Issue of Product.
The first in, first out policy (the issue of oldest stocks first) should be followed, and products should not be mixed. Follow the general procedures below for issuing fuel.
Intraterminal Transfers
Product may be transferred between tanks in a terminal when the terminal is not receiving product from the main pipeline. Product may be circulated to end stratification. All free bottom water should be drawn off before such operations. Pipelines should be checked periodically during intraterminal transfers.
REMOVAL OF WATER FROM STORAGE TANKS
Water must be periodically removed from both fixed and collapsible storage tanks.
Remove water from fixed tanks as follows:
LINE DISPLACEMENT
Lines should be kept filled with product. However, lines that are shutdown are sometimes drained to prevent pilferage or sabotage. Temperature changes, pressure loss, or air release may cause inaccurate issues or receipts. Therefore, lines must be filled or packed before each operation. Where there is a loop or double line system, lines may be filled by circulating product in them with or without booster pumps. A line may be filled by allowing air to escape through one or more vents at the high points and at the end of the line. This process is much slower, and it may leave air pockets in the line and cause gaging errors. However, this may be the only means available. Water may be used to displace product only if specifically authorized by a technical authority. This process is used as a last resort because it is difficult to remove and dispose of the water completely.
PIPELINE METERS
Pipeline meters may reduce loss of product caused by leaks by allowing more reliable, continuous checks of pipelines. Also, they may reduce losses from terminal operations by providing a means of checking product receipts and deliveries. Meters may not stay accurate when they are in constant use. They should be verified periodically or when their accuracy is in doubt.
RECORDS AND REPORTS
DD Form 250 (Material Inspection and Receiving Report). DD Form 250 is a multipurpose form. It is used for reporting shipments and receipts of packaged petroleum and related products from contractors and government-owned or consigned pipeline deliveries. This form also is used to report shipments and receipts by tank vehicle and tank car from contractors. Instructions for preparing DD Form 250 are contained in DOD 4140.25-M.
DD Form 250-1 (Tanker/Barge Material Inspection and Receiving Report). DD Form 250-1 is used when bulk petroleum and related products are moved by tanker or barge. It is used mainly to report origin acceptance of the cargo, shipments and receipts of government-owned product, and destination acceptance of tanker and barge cargo. Instructions for preparing the form are in DOD 4140.25-M.
DA Form 5467-R (Petroleum Products Pipeline Leakage Report). DA Form 5467-R is used to report a leak found anywhere along the pipeline.
Class III Status Report. A Class III status report must be kept for each terminal in the pipeline system on a daily basis. Although there is no prescribed form for this report. The report shows the stock status of the terminal for the past 24 hours. It is sent to higher headquarters or to the chief dispatcher. File copies are kept at the terminal and at higher headquarters. These copies are a permanent record of terminal activities. They are part of the total record for the pipeline system. Minimum information needed in the report is as follows:
Daily Terminal Inventory Report.
The daily terminal inventory report is used only by coastal terminals that receive products by tanker. The report shows levels of marine terminal bulk fuel stock and permits tanker cargo adjustments before loading. Amounts are reported in thousands of barrels to the nearest hundred barrels (for example, 17.2). The report is telephoned daily to the subarea petroleum office (SAPO). It gives the location of the terminal and the following information for each product:
DA Form 4786 (Petroleum Products Tank Farm Intake Record)
DA Form 4786 is used to record the flow of petroleum products to the storage tank area from the dock area or other point of entry..
DA Form 5463-R (Petroleum Products Tank Farm Outturn Record).
DA Form 5463-R is used to record the flow of petroleum products from the storage tank area to tank cars, tank vehicles, and pipelines. It is used when shipments from the tank farm are consigned to outgoing vessels, tank cars, or tank vehicles. The form is also used if product is transferred from the dock area to the loading rack, bypassing terminal storage in emergencies.
Weekly Bulk Petroleum Terminal Message Report.
The bulk petroleum terminal message report (RCS:DLA(W)1884(DFSC-MIN)) is an operational report for Defense Fuel Supply Center (DFSC) commodity management and for tanker cargo scheduling review. The report is also used to answer inquiries from all levels of the federal government. Reports are prepared as of 0800 (local time) on Friday of each week. They are to arrive at DFSC no later than the following Monday. Information copies are sent to the proper joint petroleum office (JPO) and DFSC fuel region. Instructions for preparing the report are given in DOD 4140.25-M.
DD Form 1788 (Bulk Petroleum Terminal Report)
DD Form 1788 (RCS DLA(M)-1883 (DFSC)) is prepared by each terminal, terminal complex, or tanker serving as floating storage that has custody of products owned by the Defense Logistics Agency (DLA). Reports are prepared monthly. Instructions for preparing and forwarding the report are given in DOD 4140.25-M.
Annual Bulk Petroleum Storage Facilities Report
This report (RCS:DD-M(A)506) gives data on all bulk petroleum storage facilities of 500-barrel capacity or more, either singly or in manifold systems. The report, in a machine produced format, is provided annually by the DFSC. It is based on annual review and updates from the military departments and DFSC activities. All storage capacity changes, including product allocation changes, in excess of 10,000 barrels at any activity must be reported to the DFSC as changes occur. Instructions for preparing the report are given in DOD 4140.25-M
Section V. Maintenance
This manual covers lubrication, preventive maintenance, and corrective maintenance of the materials and equipment in a typical TPT. On major items of equipment, such as hoseline pumps, collapsible tanks, and filter separators, refer to the appropriate technical publication for detailed repair and maintenance procedures.
LUBRICATION PRACTICES
Mechanical equipment requires lubrication to overcome friction and minimize wear, damage, or corrosion. A firm lubrication procedure and schedule should be established. When the U.S. Army Lube Order is available, lubricate equipment in accordance with the instructions in it. In this section, application of preservative compounds is included with lubrication where appropriate. Pivot points on various pieces of equipment should be lubricated regularly. Closure surfaces are lubricated to prevent corrosion. Unpainted surfaces should be coated with lubricant to prevent corrosion. Generally, if a part pivots, rotates, or slides and is subject to friction, it requires lubrication. Lubrication work can generally be handled in conjunction with the preventive maintenance program.
Table 6-1. Hose assemblies
|
Assemblies |
Quantity |
Length (ft) |
Location |
PSI 1/PSI 2 |
Notes |
|||||
|
6-Inch Lightweight Collapsible Discharge Hose |
96 |
250 |
Packed 2 to a flaking box |
NA |
The flaking box dimensions are 92 ¼ by 81 1/2 by 8 ¼ inches. The hose is used in the transfer hose assembly. |
|||||
|
6-Inch Collapsible Discharge Hose |
163 |
50 |
NA |
150-1 |
These hose sections are used in the tank farm assemblies, contaminated fuel module, tank vehicle receipt manifold, fuel-dispensing assembly, and the switching manifold |
|||||
|
6-Inch Noncollapsible Suction Hose |
225 |
12 |
NA |
100-2 |
These hose section are used in the tank farm assemblies and the tank vehicle receipt manifold. |
|||||
|
7-Inch Collapsible Discharage Hose |
13 |
12 |
NA |
150-2 |
These hose sections are used in the contaminated fuel module and the optional tank configuration. |
|||||
|
7-Inch Collapsible Dispensing Hose |
4-6 or 4 |
25 or 50 |
NA |
150-2 |
These hoses are used in the fuel-dispensing assembly and the 50,000-gallon TPT optional tank configuration |
|||||
|
7-Inch Noncollapsible Suction Hose |
90 |
12 |
NA |
100-2 |
They are used in the vehicle receipt manifold, contaminated fuel module, and the 50,000-gallon TPT optional tank configuration. |
|||||
|
1½-Inch Collapsible Dispensing Hose |
6 |
25 |
NA |
100-2 |
These hoses are used in the fuel-dispensing assembly. |
|||||
|
6-Inch Double Groove Coupling Clamp |
42 |
NA |
25 clamps to a box |
NA |
These clamps are used with the 6-inch hoselines and the 6-inch fittings and valves. Each camp comes with a prelubricated gasket in its own plastic bag. Packed also are a hammer drift pin and two removable assembly tools. Although similar in appearance, these double-groove clamps and gaskets must not be confused with the IPDS and single-groove clamps supplied for the pipelines. They are not interchangeable. See Figure 6-14. |
|||||
|
1-Inch Collapsible Dispensing Hose |
4 |
25 |
NA |
100-2 |
The meter skid assembly uses this hose for operation. |
|||||
|
6-Inch Single-Groove Coupling Clamp |
NA |
NA |
NA |
NA |
Used throughout TPTs if available. The single-groove clamps are compatible with double grooving. They fit into only the firs groove of the coupled components. The gasket is similar to that in the double-groove coupling; for example, prelubricated, synthetic rubber, and a C-shaped cross section. The gasket is compressed when the clamp is closed. |
|||||
|
7-Inch Single-Groove Coupling Clamp |
18 |
NA |
NA |
NA |
The 7-inch single-groove coupling clamps have the same design characteristics as the 6-inch single-groove coupling clamp. |
|||||
Table 6-2. Fitting and valve assemblies
|
Assemblies |
Quantity |
PSI 1/PSI 2 |
Notes |
|
|
6-Inch Gate Valve Assembly |
122 |
150-2 |
Gate valve assembly is a part of the tank farm assembly, contaminated fuel module, transfer hoseline assembly, tank vehicle receipt manifold, and the switching manifold. |
|
|
6-Inch Double-Groove Ball Valve Assembly |
13 |
NA |
Values are a part of the fuel-dispensing assembly and the switching manifold. |
|
|
7-Inch Quick-Disconnect T-Assembly |
4 |
NA |
1 male x 2 female—Two each. 3 male T—one each. 3 female T—one each. All gaskets and bolts are supplied with the Ts. These four 7-Inch T-assemblies are part of the 50,000-gallon TPT optional tank configuration. |
|
|
7-Inch Quick-Disconnect Gate Valve Assembly |
24 |
NA |
These gate valves are part of the fuel-dispensing assembly and the 50,000-gallon TPT optional tank configuration. |
|
|
7-Inch Quick-Disconnect Y-Assembly |
NA |
NA |
Two version of this Y-assembly are in the TPT. There are three units of the two female and one male version and three units of the two male and one female version. This Y-assembly is a part of the 50-gallon optional tank configuration. |
|
|
7-Inch Quick Disconnect Butterfly Valve Assembly |
30 |
NA |
The 7-Inch quick-disconnect butterfly valve is part of the fuel-dispensing assembly and the tank vehicle receipt manifold. |
|
|
3-Inch Quick-Disconnect Ball Valve Assembly |
1 |
NA |
This ball valve assembly is in the contaminated fuel module. |
|
|
1½ -Inch Quick Disconnect Ball Valve Assembly |
12 |
NA |
These ball valve assemblies are a part of the fuel-dispensing assembly. |
|