Higher Level Index Index   Search our Site



CHAPTER 5

OFFSHORE PETROLEUM DISCHARGE SYSTEM

Section I. OPDS Tankers

RESPONSIBILITIES

The Offshore Petroleum Discharge System was designed by and for the U.S. Navy, for use with the Army, and Marine Corps, Inland Petroleum Distribution System (IPDS), component parts of the Southwest Asia Petroleum Distribution Operational Project (SWAPDOP). The OPDS is stored on board a selected RRF tanker. It is transported to a theater of operations by the tanker. The U.S. Navy is responsible for installing the OPDS and ship-to-shore pipeline to the high-water mark. The OPDS provides 1.2 million gallons per 20-hour day of refined petroleum to the beach, from a tanker moored four miles offshore. The petroleum products are delivered from the offshore tanker to forces onshore where ports or terminal facilities are damaged, inadequate, or nonexistent. Each tanker is manned by a civilian merchant crew. The crew is train to operate, deploy, and recover the of the OPDS. Military personnel plan, direct, and control all the OPDS operations. The OPDS tanker must be able to begin pumping fuel within 48 hours of arrival. Where required, a permanent SPM will be operating by the seventh day after the tanker arrives in the objective area. The OPDS will also provide fuel for aircraft operating from field sites in the objective area. Table 5-1 gives the current commercial (OPDS) special tankers in the MSC inventory and their statistics. Table 5-2 shows the maximum working conditions for the OPDS.

Table 5-1. OPDS tanker statistics

TANKERS

LENGTH

(feet)

BEAM

(feet)

DRAFT

(feet)

LONG TONS

FUEL CAPACITY

(BBL)

S.S. Potomac

620

84

34

27,467

168,000

S.S. American Osprey

661

90

36

34,723

235,000

S.S. Chesapeake

736

102

40

50,023

255,000

S.S. Petersburg

736

102

40

50,063

225,000

S.S. Mount Washington

736

102

40

49,471

269,000

Table 5-2. Maximum conditions for the OPDS

OPERATIONS

CURRENT
(knot)

WIND
(knot)

WAVES
(feet/height)

Installation

1

9-12

3

SALM

4

27-40

12

Maximum

4

48-55

22-35

OPDS TANKER SITE SURVEY

Prior to positioning the OPDS tanker, a site survey must be conducted. The general requirements for the tanker site are:

RESUPPLY OF THE OPDS TANKER

There may be a need for the OPDS tanker to dock in a specific location longer than expected due to the amount of fuel supplies needed at that undeveloped theater of operation. Depending on the water depth, prevailing currents, and the judgment of the tanker’s commander, resupply of the OPDS tanker can be resupplied in one of three ways:

OPDS SYSTEM DESCRIPTION

The OPDS was designed to be installed and carried to the operating area on a medium-sized tanker. The tanker will be manned by a civilian merchant crew. The crew will be trained to operate, deploy, retrieve the OPDS. Other trained OPDS personnel may direct or assist in the tanker operations. Army or Navy personnel are trained install the components as they are deployed from the tanker. The OPDS consists of five principal subsystems. They are listed below:

Section II. Major Components (OPDS) Tanker

SINGLE ANCHOR LEG MOORING

The SALM is a large, steel, compartmented barge (Figure 5-1). It can be carried to the deployment site on the tanker skid beams. The SALM can be towed if needed. Like its commercial counterparts, it provides a SPM for the OPDS tanker that permits the tanker to weathervane around the mooring buoy and continue pumping. The hard piping on the mooring base and the attached hoses provide the capabilities to pump two products simultaneously with its dual product swivel from the tanker to the beach. Within seven days, and with diver SLWT assistance, the SALM can be installed to provide uninterrupted, all weather product delivery. The SALM permits a tanker to remain on station and pump in much higher sea states than otherwise is possible in a spread moor. Figure 5-2, shows the 48-hour and seven-day OPDS configurations. Some characteristics of the SALM subsystem are listed below:

Figure 5-1. Single anchor leg mooring

Figure 5-2. OPDS configurations

The SLWTs (Figure 5-3) are provided by other forces assigned to the amphibious operation. They provide OPDS with tanker carrier utility boats to make OPDS a stand-alone system. Four SLWTs are required for deployment of the OPDS. They must be modified for OPDS use with equipment and tools carried on the OPDS tanker. Three SLWTs are modified to act as tow tugs and the fourth unit is modified to act as the LRB. As soon as the tanker arrives, the equipment stored in its hold is offloaded onto the SLWTs and taken to a support area where the equipment can be installed by the Navy Amphibious Construction Battalion PHIBCB support personnel. Welding and removal of designated tie plates on each of the craft is required.

Figure 5-3. Side loadable warping tug

BEACH TERMINATION UNITS AND EQUIPMENT SET

Two BTUs are carried aboard the OPDS tanker to the deployment site. Depending on the requirement, one or both BTUs may be installed. The BTU has many functions for the OPDS (Figure 5-4,* see glossary); it is the high water mark termination of the OPDS. It is the anchor for the shoreward end of the conduit. It controls the pressure and fuel flow distribution through the hoseline from the SALM. It acts as an interface between the hoseline and IPDS. The following is a description of the BTU.

Figure 5-4. Beach termination unit

BTU Equipment Set

A BTU equipment set consists of two BTUs and component items. The OPDS beach termination equipment consists of the following:

CONDUIT AND COUPLINGS

There are two types of sea floor conduit manufactured for the OPDS; each has a 6 inch inside diameter and about an 8-inch outside diameter. They have different handling characteristics and end fittings. Special fittings are provided to connect one type with the other. Most OPDS conduit is flexible, steel-reinforced elastomer hose. It is designed in a float-sink configuration. When filled with air, the conduit has a positive buoyancy of about 1.9 pounds per foot. When filled with water or petroleum products, it sinks to the sea floor. On the seafloor, it has a negative buoyancy of about 8 pounds per foot. The conduit couplings consist of male and female fittings. The couplings are bolted together with six cap screws. The male fitting has a swivel flange that ensures ease of alignment with the female coupling. Each of the different hoses is listed below.

Dual Product Submarine Hoseline

The submarine hose conduit system (Figure 5-5) supplied aboard the mooring base tanker consists of eight hose assemblies and one hose support buoy assembly. Each hose section consists of two independent flow paths of 6-inch. inside diameters (Table 5-3, page 5-13.) encased by a semirigid carcass of 28-inch outside diameter with an air-filled annulus. The submarine hose provides a flow path to the product swivel on the base of the SALM from the floating hose string on the surface. The eight hose sections are sufficient for water depths up to 200 feet at the SALM site. The rigidity of the submarine hose string makes it function like a lever arm. It is enough to rotate the product swivel as tanker weathervanes around the SALM. The hoses (Figure 5-6) are marked with a white band running their entire length and are to be identified as types, AP, A, B, and C.

Figure 5-5. Dual product submarine hoseline

Figure 5-6. Submarine hoses

PigTail Hoses or Jumper Hoses

The two SALM pigtail hoses transfer the tanker’s petroleum products from the mooring base to the flexible conduit. Each of the two SALM (Figure 5-7, page 5-9) pigtail hoses is 320 feet long and similar to the conduit in construction. It can be connected to the floating conduit end on the sea’s surface by the SLWT crew after the SALM base is on the seafloor. Both pigtail hoses are capped with a blank towing flange to keep the hoses afloat during deployment. The hoses are stored on all the tanker’s tenth reel except the S.S. Potomac.

Figure 5-7. Pig tail hoses

Floating Hoses

The floating hoses transfer the product from the tanker’s manifold to the submarine hoses. This hose system is comprised of mainline floating hoses and tanker rail hoses. The mainline floating hose system consists of two 6-inch inside diameter hose assemblies, each 560 feet. long. Each assembly contains 14-hose sections of 40 feet lengths (floating mainline hose sections and 1 tanker rail hose section). The floating mainline hose are electrically continuous and the tanker rail hoses are electrically discontinuous. All floating hoses are marked by two longitudinal white stripes spaced 180 degrees apart along their entire length (Figure 5-8).

Figure 5-8. Floating hoses

Flexible Conduit Pipeline

There are 4 nautical miles of 6-inch hoseline included with the OPDS. The system uses high-pressure hoses on ship-mounted reels. Each reel holds 0.5 mile of collapsible hoses; eight reels make up the 4-mile kit. The hoses, which are not subject to corroding are made out of a smooth high-grade fuel-resistant synthetic-type rubber. They can be damaged and should be routinely inspected. The hoses can be stretched to 33 percent under normal conditions of use. Hose-to-hose and hose-to-fitting connections are made with 6- and 12-bolt flange connections that are designed for a burst pressure of 2,200 PSI. The 6-inch diameter and 1-inch thick hose has a maximum operating pressure of 740 PSI. The hoses weighs about 19 ½ pounds per foot. The U.S. Coast Guard hydrostatic pressure test is 1,014 feet per section with 24,336 feet per shipset. Petroleum is pumped using two positive displacement pumps in parallel (500 GPM each at 700 PSI). High pressure is required by the high head losses that result from delivery of 1,000 GPM in the 6-inch hose over the 4-mile (maximum) distance to shore.

Section III. BTU Procedures

DEPLOYMENT

The BTU is deployed from the OPDS tanker. The following procedures are used for deployment:

BTU SITES

The site of the BTU for each beach terminus of the OPDS must be determined early in planning. The location should be suitable for connecting to the IPDS. Below is a list of the preparation rules to follow:

BEACH PREPARATION

Preparing the beach area for receiving the OPDS conduit requires equipment and personnel to set up the BTU site(s), range markers, lighting, and other items to support the installation of BTUs. Bulldozers help in bringing the conduit ashore and connecting it to the BTU hookup hose. Specific actions for each of the areas of support are given below.

Installing Beach Terminal Unit Bermed Area With Spill Catchment

Before performing any POL operation, consult the local environmental coordinator to check for the possible existence of special permit requirements. The BTU will be installed in a bermed site with a berm liner (Figure 5-9, page 5-11) to contain any fuel or contaminated water spills from the pig catcher. The berm area should be not less than 10 by 16 feet to permit personnel to move around inside the enclosure while operating/maintaining the BTU. If the berm floor is sloped, the high side should be seaward. Prepare an 8- by 8- by 3-foot hole 100 feet inland from the BTU site for the BTU anchor. Clear the area between the BTU and the sea to help connect the 40-foot hook-up hose and 6-inch ball valve to the BTU.

Installing Range Markers/Lights

Install range markers inland from the BTU site if room permits. Markers must be large enough and high enough for SLWT pilot to see the markers a minimum of 1 mile away. They must be at least 100 feet apart.

Setting up the Maintenance/Support Pier

If no harbor or other pier space is available, set up an administrative pier within a mile of the BTU/conduit site for the OPDS service craft. The pier should be at least 500 yards from the BTU so that it does not interfere with the SLWTs bringing the conduit to the beach.

Figure 5-9. BTU with berm liner

Anchoring the BTU

Dig a hole for the 1,500-pound lightweight BTU anchor which is buried about 100 feet inland of the BTU. Dimensions of the hole are about 8 by 8 by 3 feet. Lower the anchor in the hole with the shank toward the BTU. Bury the anchor, covering it up to the jew’s harp. Attach the 100-foot wire to the jew’s harp and to the inland end of the BTU.

BTU OPERATIONS

After the BTU is installed and tested by the Navy personnel and flowing fuel, the remaining operations consist of monitoring the flow, correct operation of the flow control valve, and routine maintenance of the BTU. The BTU operators must maintain continuous communications with the tanker and with the onshore unit. Radio checks will be conducted regularly by net control. Any failure of radio communications is cause for immediate shutdown by the tanker. Operations at the BTU continue until fuel requirements are met. There will be interruptions in pumping during refueling of the tanker and when the SALM is being connected to the conduit string. All other procedures of the BTU are listed below.

Controlling the BTU

The BTU is operated by a Navy crewman for the benefit of the Army or Marine Corps onshore. The BTU crewman takes their orders from the onshore command unless other arrangements are worked out and reflected in the OPORD. The BTU crewman is trained to operate the BTU valves to perform certain functions during pigging, flowing product, and hydro testing the lines. The Army and Marine Corps should be sufficiently familiar with the operation of the BTU so they can check valve alignment for the ordered function. Depending on the downstream arrangement of hoses, valves, and bladders, a misaligned valve in the BTU could divert the wrong fluid into a storage bag and contaminate the bag.

Disconnecting The BTU

The method used for conduit retrieval determines when the BTU hookup hose is disconnected from the conduit. Onshore fuel connections BIU will be disconnected first and cleared from the immediate area. Uncover the hook up hose and conduit down to the surf area before disconnecting them. When ready to disconnect the BTU hookup hose from the conduit, secure the restraining collar and bridle to the seafloor conduit end fitting. Shackle a bulldozer’s winch wire to a pelican hook to the bridle and take a strain on the winch wire. The pelican hook provides a positive control for release of the conduit. The hose and conduit are then unbolted and a female pulling cap attached to the male end of the conduit.

Flushing The BTU

Before the BTU can be returned to the tanker, it must be flushed, drained, and dried. The Navy PHIBCB or Army personnel need a freshwater supply air pump for this procedure. Use a forklift or crane to tilt the BTU casing once the flushing is completed. Unbolt the BTU hook up hose from the inlet valve flange and prepare for retrieval to tanker.

Retrieving The BTU

The BTU is prepared for recovery by PHIBCB or Army personnel. A designated tow rigged SLWT proceeds to the BTU site. If a pier is available, forces ashore transport the BTU there and load it onto the SLWT. They also load the anchor, pendants, hook-up hose, and other fittings. In the absence of a pier, the BTU, anchor, pendants, and fittings are moved to the shoreline. The SLWT passes its forward winch wire to the beach by small craft. The anchor, fittings, and pendant are then pulled out and lifted on deck with the A-frame. At the tanker, the forward boom of the tanker lifts the BTU and all its equipment from the SLWT to the forward deck.

Table 5-3. Conduit and hose characteristics

Items

Bore
Size
(inch)

Outside
Diameter
Normal
(inch)
Body/Ends

Maximum
Allowable
Working
Pressure
(psig)

Burst
Pressure
(psig)

Electrical
Continuity

Conduit

6.00

7.85/8.85

714

2220

No Requirement

Tanker Rail Hose

6.00

10.0/17.5

714

2220

Discontinuous

Floating Hose

6.00

12.0/13.0

714

2220

Continuous

Submarine                         A

6.00

28.0/30.0

714

2220

Continuous

Hose                                   B

6.00

27.7/29.7

714

2220

Continuous

C

6.00

26.7/29.5

714

2220

Continuous

Pigtail Hose

6.00

7.85/8.85

714

2220

No Requirement

BTU Hook-up Hose

6.00

7.85/8.85

714

2220

Discontinuous

Section IV. Planning and Administrative Considerations

OPDS DEPLOYMENT CONSIDERATIONS

When the OPDS tanker arrives, the JLOTS commander holds an OPDS deployment conference on board the tanker. The meeting is to coordinate efforts of the OIC OPDS and all participating OPDS deployment elements. Attendees review the OPDS deployment plan. They refine it for the existing scenario and work out last-minute details. The meeting considers all facets of OPDS installation to include:

PRODUCT DISCHARGE CONFERENCE

Before the initial pumping of product, the JLOTS commander will hold a PDC. This PDC will ensure safe pumping operations and mutual (ship and shore) understanding of procedures. A review and initialing of the OPDS POL communications checklist will also be done. The checklist must be signed whether the deployment is exercise or wartime. The meeting includes the Army Petroleum Operations Officer, the ship’s master, and pumping master. Fuel quality, quantity, and product delivery schedule will be agreed upon before any product discharge. The OPDS deployment conference may be combined with the PDC. Also with the PDC, the Army or Marine Corps quality control specialists will inspect the ship’s product tanks and take fuel samples. They will test product samples IAW MIL-HDBK-200 to ensure the products to be pumped ashore meet specifications.

ENVIRONMENTAL CONSIDERATIONS

The JLOTS commander is responsible for monitoring and keeping the OPDS OIC and ship’s master informed of weather conditions. During deployment and recovery operations, the OPDS OIC will determine when to suspend operations due to weather. During pumping operations, the ship’s master makes this determination and will notify the Army or Marine Corps of intent to discontinue operations.

Section V. Communications and Installation

COMMUNICATIONS EQUIPMENT

The OPDS-installed tanker transceivers include as a minimum one each HF, VHF, and SSB or UHF transmitters and receivers. These units are used for general communications, OPDS deployment/recovery, and for pumping operations. There are 20 portable hand-held 5-watt transceivers (30-75 MHZ) that are part of the TOE. The PHIBCB personnel on the tanker, support craft, and ashore will use those or similar radios in addition to standard military VHF radios. During deployment and recovery, the Army onshore will use PRC-77 or equivalent. The hand-held VHF radios have a range of about 4 miles at tanker deck level and an operating life of six to eight hours.

OPDS OPERATIONS REQUIREMENTS

During OPDS deployment and recovery, long-range and secure tactical voice communications are not usually required. Operational communications require sufficient range to reach from the IPDS onshore and the tanker, which may be in excess of 20 miles. Also, for tactical reasons, secure voice communications may be required. The Army petroleum distribution commander ensures communications equipment is compatible with the OPDS tanker. If the communications equipment is not compatible for product scheduling or off-load operations, the Army unit onshore will provide the necessary equipment.

WARNING

Any person who notices an unsafe condition is authorized to radio to the tanker to stop pumping.

ONSHORE COMMUNICATION PLAN

Good communications are needed throughout all phases of OPDS planning, deployment, recovery and operation. Most OPDS installation and recovery operations are controlled by soldiers using VHF walkie-talkie, hand-held radios with at least six-channels. The onshore fuels distribution system delivers fuels from the BTU to locations ashore. It consists of one or more conduits, storage facilities, and pumping stations, as well as related monitoring and control systems.

WARNING

The tanker will stop pumping whenever communications with the beach is list for one minute.

PUMPING COMMUNICATIONS AND CONTROL

There must be a dedicated communications pumping network and a backup network that are manned and operable every second so that the tanker can be advised to stop the pumps in an emergency. The tanker has pump shut down buttons in three locations, any one of which can be used to shut down the pumps under emergency conditions (loss of lubrication, possible pump damage). There is always a tankerman close to at least one of the buttons, usually to two buttons during pumping operations. However, they will not react until so directed by the beach. Any person along the flow path is authorized to give a stop pumping order to the tanker if he notices an unsafe condition. The tanker may shut down pumping operations because of equipment or other problems on board the ship, but will always advise the beach as soon as possible. The Army or Marine Corps must anticipate all problems.

OPERATIONAL PROCEDURES

The sequence of events for the OPDS deployment is as follows: