|
|
|
CHAPTER 4 WATERFRONT OPERATIONS |
Section I. Loading and Unloading Facilities
PIERS AND WHARVES
Piers and wharves are permanent structures built in protected harbors. They are built using timber, concrete, or steel. Petroleum base terminals in developed theaters have piers (Figure 4-1) or wharves equipped to load and unload tankers and barges. Piers or wharves may have single-length berths or multiple-length berths. A single-length berth (Figure 4-2) is 60 to 80 feet longer than the largest tanker that uses it. A multiple-length berth (Figure 4-3) should be 110 to 130 feet longer than the combined lengths of the largest tankers that use it. No vessel should be allowed to dock or moor within 50 feet of a vessel that is unloading bulk cargo, unless the depot officer or supervisor and the master of the vessel transferring cargo agree.

Figure 4-1. Pier at petroleum based terminal

Figure 4-2. Single-length berth

Figure 4-3. Multiple-length berth
EQUIPMENT ON PIERS AND WHARVES
Piers and wharves at base terminals are equipped with ship-to-shore hoselines; standard 4-, 6-, 8-, or 12-inch pipelines; a loading and unloading manifold; valves; and fittings. Booster pump stations are installed where needed. Each facility should have at least one ballast tank with separate pipelines to receive and discharge water and an oil and water separator to remove product from ballast water during a transfer. A supply of water (preferably fresh water) and fire-fighting equipment must be available at all times. The equipment should include fire hoses, foam generators, and foam and carbon dioxide fire extinguishers. If there is a source of steam, it can be used to fight a fire in a confined space, such as a tanker compartment. Also, all piers and wharves must have the proper grounding connections for fuel transfer operations.
TEMPORARY STRUCTURES
Existing loading and unloading facilities in a developed theater may also require self-elevating piers and pipeline jetties. These are available through the Army Facilities Components System described in TMs 5-301-1, 5-301-2, 5-301- 3, and 5-301-4. The self-elevating pier and pipeline jetty are described below.
Self-Elevating Pier
A self-elevating pier (Figure 4-4) is a steel barge which must be towed into place. It has jacks, caissons, and machinery that raise the pier above the water to form a working platform. Depending upon navigable conditions at the erection site, self-elevating pier may be employed as single piers butted against a beach or as finger, marginal, T-head, or L-head piers. TM 55-500 discusses this pier in detail.

Figure 4-4. Self-elevating pier
Pipeline Jetty
A pipeline jetty (Figure 4-5) is a structure made of pilings and timber that extends as far as 1,000 feet from the shore. It is only wide enough to support pipelines and to provide a walkway with a 40- by 70-foot working platform at the tanker end. The pipeline jetties are used in protected harbors to transfer fuel.

Figure 4-5. Pipeline jetty
TACTICAL PETROLEUM TERMINAL
The TPT is the Army’s bulk-fuel storage facility. It is a fuel-handling system designed to receive, store, and issue bulk petroleum fuels, specifically diesel fuel and jet fuels. The TPT serves as a base terminal in an undeveloped theater and can be used in the developed theater to supplement existing facilities that are inadequate or damaged. For more information see Chapter 6.
OFFSHORE PETROLEUM DISCHARGE SYSTEM
A Navy system that uses a tanker, which is anchored up to 4 miles offshore, and underwater hoselines to off-load commercial tankers and deliver fuel to the high-water mark in an undeveloped theater. For more information see Chapter 5.
Section II. Tank Vessels
TANKERS
Tankers move large bulk petroleum cargo with speed and safety. Petroleum base terminals should be able to receive tankers that are at least 600 feet long with a draft of 35 feet. Tankers and their equipment are described below.
Cargo Space
Most of a tanker hull is used to carry liquid cargo. Cargo space varies among different types of tankers. Cargo space is divided into tank compartments by bulkheads which run the length and width of the tanker. The tank compartment is usually separated from fore and aft sections of the tanker by narrow, empty, liquid-tight compartments called cofferdams. Each tank compartment has a hatch and liquid-tight hatch cover. An-ullage sounding hole with a hinged cover is usually in each hatch cover. Tank compartments may have heating coils for heating cargo of heavy oil to viscosities suitable for pumping.
Vent Lines
Vent lines are usually between each tank and hatch. At the hatch, the vent lines connect to headers. The headers extend up the masts and have flame arresters at the top. Vapors caused by agitation or high temperature of product are vented through these lines. Each vent line is fitted with a vacuum relief valve. When vapors condense in the tank because of low temperature, the relief valve permits intake of air to relieve any vacuum created.
Pipeline and Pumping Systems
A complex cargo line system controls product flow during loading and discharging and while the vessel is under way. Tank farm pumps or booster pumps are normally used to load tankers. Tankers usually have cargo pumps for pumping cargo ashore through the pipeline. Some tankers also have stripping systems used to strip the tanks dry of ballast.
Fire-Fighting Equipment
Tanker fire-fighting equipment for the deck includes fire hoses, axes, buckets, and hand fire extinguishers. There may be a carbon dioxide fire extinguisher system for protecting fireroom bilges and electrical machinery. Most tankers also have a steam smothering system that can be used to fight fires. The main line of this system connects to the ship’s auxiliary steam line through the master valve in the boiler room. It runs forward along the deck with a branch for each fuel and cargo tank and cofferdam. Branch lines also run to the forward holds, the pump room, and other areas.
LIQUID-CARGO BARGES
Military liquid-cargo barges are steel watercraft. They move bulk petroleum products. Some are made for short distance hauls in harbor, coastal, or inland waters. Others are made for self delivery to an overseas destination and are self-sustaining for extended periods of operation. Barges have no propelling machinery; therefore, they require the services of a tug to move. A small tug is used for harbors and inland waterways while a large tug is used for coastal and intertheater missions.
Pumps and Piping Systems
Some barges require off-vessel equipment for discharging cargo, while other have their own equipment. Self-discharging vessels generally use electrically powered rotary pumps. The pumps are usually below the deck in the aft section or midship section. As a fire precaution, the pump room is completely insulated from the cargo and its gases. The piping systems on barges vary widely. There may be several pipelines, depending on the number of products carried. Vessels carrying light oils usually have pipelines with bellmouthed fittings. These fittings extend almost to the tank bottom. A stripper line, extending until it is almost flush with the tank bottom, is used to pump any oil left at the bottom of the tank. Vessels carrying heavy fuel oils and asphalts are usually equipped with 12- to 16- inch pumps and suitable pipelines.
Types of Barges
The military has 225-barrel-capacity and 4,160-barrel-capacity steel hull barges in its inventory. They are described below.
The 225-barrel Steel Barge
The barge (Figure 4-6) can carry limited quantities of liquid (225 barrels) or dry cargo (21 long tons) about harbors or inland waterways. Although this barge can carry limited quantities of liquid cargo, it does not have integral liquid-cargo pumps. It has an overall length of 45 feet 6 inches, an 18-foot 6-inch beam, and a molded depth of 3 feet. It has a displacement of 33 long tons loaded and a maximum draft of 1 foot 8 inches loaded. This barge consists of two sections joined end-to-end. The military has limited quantities of this barge remaining in its inventory. It is not considered a bulk transporter because of the limited capacity and the lack of integral pumping capability.

Figure 4-6. Steel barge with a 225-barrel or 21-ton capacity
The 4,160-Barrel Steel Barge
This barge (Figure 4-7) can carry 4,160 barrels of bulk liquid cargo or 578 long tons of dry cargo. The barge has an overall length of 120 feet, a 33-foot beam, and a molded depth of 10 feet 6 inches. It has an integral diesel-engine driven, liquid-cargo pump to receive and discharge liquid cargo.

Figure 4-7. Steel barge with a 4,160-barrel or 578-ton capacity
Uses
Sometimes tank barges are used for temporary storage of bulk petroleum products. However, the main uses for barges include the following:
Fire-Fighting Equipment
Fire-fighting equipment for the deck includes fire hoses, axes, buckets, and hand fire extinguishers. Most vessels have fire pumps and carbon dioxide for fires below deck. Pressure and flow are controlled by a master valve. In case of fire, carbon dioxide is fed into the cargo tank to smother the flames. Some modern vessels have an inert gas system fitted to the liquid-cargo tanks. This system provides a positive gas pressure to the cargo tank. The gas is so deficient in oxygen that it renders the atmosphere in the liquid cargo tanks incapable of supporting combustion.
Section III. Loading and Unloading Operations
RESPONSIBILITIES
Commanders of commercial tank vessels and commanding officers of military tank vessels are responsible for the loading plans for their vessels. Their decisions are final concerning the cargo layout. Petroleum shore inspectors inspect all vessel tanks and pipeline systems before loading. Their decisions on quality control of product are final. The inspectors review the loading plans and consider bulkheads, lines, tank capacities, and trim. In the case of split cargo, the inspectors must ensure that the vessel is physically able to carry two or more grades of products without contamination. The inspectors make sure that bulkheads are secure and that there are double valves or line blanks to separate and to protect each system. If valves are used they must be lashed and sealed in the proper position and the seal numbers must be placed on the shipping document. Shore operators must make sure that precautions are taken against fire, product contamination, and safety hazards. All loading plans must be coordinated between the ship’s officer and the responsible shore authority. Shore attendants should know loading terms and factors governing vessel loading and unloading.
LOADING INFORMATION
Below are the various types of data used to describe the loading capacity of a vessel.

Figure 4-8. Load-line markings

Figure 4-9. Sagging and hogging of vessels
LOADING FACTORS
A number of factors need to be considered by personnel loading a vessel. Some of these factors are given below.
Ballast Layout
The amount and distribution of ballast contribute to the seaworthiness, control, and trim of a tanker. Ballast also controls stress vibration in the hull caused by poor weight distribution. The master of a vessel must select ballast tanks that will distribute weight evenly through the hull. At the same time, the tank cleaning and inspection schedules and the effects of tank corrosion must be considered. If different ballast tanks are used on each voyage, tank corrosion is slowed down and tank life is increased.
Maximum Tonnage
Loading above load lines is a safety hazard. Therefore, load weights must be calculated accurately. The steps for calculating maximum tonnage are as follows:
Cargo Layout
The master of a vessel and the shore petroleum inspector consider weight distribution factors when they plan the cargo layout so that the cargo is not contaminated by the mixing of one product with another. There is little chance of this problem on a tanker carrying only one product.
PRELIMINARY PROCEDURES
There are many steps that must be taken before a ship is loaded or unloaded. They are described below.
Preparing Orders
Before a tank vessel docks, the shore terminal command posts written operation orders so that the shore operators can prepare for loading or unloading the vessel. The information that must be shown on the orders includes the following:
Notifying Customs and Health Authorities
If a vessel is arriving from a foreign port, customs authorities must be notified so that the cargo can be declared and the vessel can be inspected. The Public Health Service must be notified so that the crew can be examined.
Arranging for Dock Personnel, Tugboats, and Pilots
There should be enough shore personnel at their stations to help moor or undock and load or unload the vessel. The vessel’s personnel are responsible for the safe docking of the vessel, but the shore personnel must help. Arrangements must be made for tugboats and required pilots, when necessary. All personnel concerned with the operation should be told of the grade of product and the tanks being used.
Inspecting Hose
Shore personnel must inspect all connecting hoses for condition and suitability. Cargo hoses should be inspected and maintained according to Chapter 10. Any cracked, worn, or frayed hose must be replaced. A contaminated hose should be cleaned or replaced, depending on the contamination and the product to be handled. There should be enough hose to allow for slack to take care of tide changes, weather, or layout. Too much hose may cut down product flow.
Providing Sufficient Product, Tankage, and Ballast
When the vessel takes on products, there must be enough product in the shore tanks. If the vessel must unload products, there must be enough shore tankage to handle them. Shore tanks must be gaged by shore personnel. A ship’s representative may witness the gaging. Enough ballast water tankage also should be provided.
Preparing Dock
All needed tools and equipment should be readily available before the vessel arrives. Items that should be included are listed below:
Preparing for Safety
Safety equipment should also be available. These include the following:
Preparing to Deal With Spills
Plans for preventing, controlling, and cleaning up spills are required. The SPCC plan is a federally required document. It covers all aspects of facility-wide spill response. The ISCP is the site-specific plan for responding to a spill. It must be included in the facility-wide SPCCP to meet legal requirements. All personnel involved in loading and unloading operations must have had all spill response training in accordance with these plans. Specific personnel must perform certain specialized functions including command and control, as well as all other spill response team functions. All spill team personnel must take part in periodic spill response team drills, in accordance with these plans. A spill of oil is reportable if it creates a sheen on the navigable waters of the United States, or if it otherwise meets certain local quantity criteria. The term navigable waters is quite broad. It may include whether it will create a sheen in storm-water runoff into a nearby stream the next time it rains. If a spill is confined so that it may reasonably be expected not to affect the navigable waters of the United States, it may still be reportable dependent upon the amount involved in accordance with specific permit provisions, and other local, state, and federal requirements. Failure to report oil spills in a proper and timely manner is a criminal offense. It is important that all oil spills be reported immediately up the chain of command. It must be done without any delay whatsoever except for those required for personnel safety. At the appropriate level in the chain of command, the environmental compliance officer shall be notified so that proper, timely notification of the Coast Guard National Spill Response Center, the Environmental Protection Agency, and other local, state, or host-nation regulatory officials may take place. The following information will be required in all spill reports.
Designating and Inspecting Facilities
Shore tanks, pump stations, and pumps should be marked order in which they are to be used. All valves, except dock valves, to be used during loading or unloading operations must be opened until the lines are filled. After the lines are packed, the valves must be closed. Then, tanks should be inspected, gaged, and checked for water. All valves must work and must not leak. If blinds are needed, their location should be in the written order.
Sampling Product
Product in shore tanks scheduled to receive product must be sampled and tested as prescribed in the updated MIL-HDBK-200. Product carried by the vessel also must be sampled and tested. It may be possible to board the vessel and take product samples before it is docked to speed unloading.
Preparing Pier Pipelines
Before the vessel is docked, the pier pipelines should be filled, when and where possible, with the same grade of product that is going to be moved. Unless the pipelines are completely filled or empty, there is no way to get an accurate measurement of product issued or received.
Checking Mooring Lines
When the vessel is moored, mooring lines should be taut enough to hold it steady. The lines should also be slack enough to allow for the rise and fall of the tide and the change in the vessel’s draft during product transfer. Lines must be watched and adjusted as product is moved and tides rise and fall.
Preparing Gangway and Testing Signal System
As soon as the vessel is docked, vessel personnel should rig a gangway with a safety net underneath so that inspectors and other personnel may board safely. Special equipment may be used if vessel movement makes rigging a gangway difficult. Vessel access must be according to Coast Guard regulations. The need for access applies mainly to large tank vessels where shore personnel witness sampling and gaging. The signal used at the dock to regulate product transfer should be tested.
Notifying the Vessel Master of Fire Protection Services
The master of the vessel must be told of fire protection services available at the pier. These services include power, water, and steam which may be needed to put out fires in the boiler and galley.
PREPARING WATERFRONT OPERATIONS LOG SHEET
Information on the loading or unloading operations must be recorded on a waterfront operations log sheet. This information is used to prepare DD Form 250-1. The log sheet should be kept at the waterfront terminal. Discrepancies between the shore log and the ship’s log should be identified. The information that the log sheet should include is given below:
FIRE AND SAFETY PRECAUTIONS
When a tank vessel has docked, responsible persons must make sure there are no fires, open flames, or open lights on deck or anywhere near the part of the deck at which the cargo hose is to be connected. Although it is sometimes necessary to keep fires in the boiler room when cargo is being loaded or unloaded, the potential hazard should be weighed. Extreme care should be taken when tugs or other vessels that may have open flames come alongside. Smokestacks of coal burning tugboats, dredges, or pile-driving equipment should have spark arresters. These precautions are very important during the transfer operation when large amounts of explosive vapors may form. Smoking or flame-spark-producing devices should not be allowed on the vessel or at the terminal, except in special places. Fire fighters must not be allowed to clean out stacks while vessels are docked. No garbage or waste of any kind should be thrown overboard while the vessel is docked. Additional measures are described below.
Caution Signs
Caution signs must be posted. They include NO SMOKING and NO LOITERING signs and traffic direction markers. A warning sign stating DANGER: THIS VESSEL HANDLING PETROLEUM must be posted. A sign stating NO FIRES, NO SMOKING, NO VISITORS should be posted in clear view on the gangway while product is being loaded or unloaded. The sign must be lettered in red on a white background. When a petroleum cargo is transferred at a mooring or dock, the vessel must display a red flag by day and an all-round red light by night.
Grounding Cable
A grounding cable must be connected between the dock grounding system and the hull of the vessel before the cargo hose is connected. This cable must not be removed until after the cargo hose is removed.
Cleanup of Spills
All spills must be cleaned up as soon as possible. Sources of vapor ignition must be eliminated.
Mooring Limitations
No vessel should be allowed to dock or moor within 50 feet of a vessel that is unloading bulk cargo, unless the depot officer or supervisor and the master of the vessel transferring cargo agree.
Mooring Line
At the end of each mooring line, at the bollard or belay pile, there should be a manila or synthetic fiber line that can be cut in an emergency. It is used if there is no other emergency release.
Relief Valves on Suction Lines
A shutdown of the booster pumps, either through error or power failure, will stop the flow and cause the full delivery head from the vessel’s pumps to back up at the dock. There may also be a surge of pressure that could burst the hose. Precautions should be taken against these hazards. A battery of relief valves may be connected to the pump station suction line. The valves will relieve pressure until vessel personnel can be told to shut down the vessel’s pumps.
Inspections
To ensure safe operating procedures, the depot supervisor must inspect conditions both on shore and on the vessel before loading or unloading operations are started. There will usually be at least one deck officer and one engineer officer on duty aboard a tanker during such operations. This rule may be changed to suit transfer operations to and from small vessels.
Deck Watch and Hose Watch
During the entire loading or unloading operation, the vessel personnel usually provide a deck watch and the shore organization provides a hose watch. The hose watch observes ship/dock operations, looks for straining or chafing of the cargo hose, stands by at all times to close the dock valves, and coordinates with the deck watch to start and stop the operations.
SPILLS
All spills are subject to strict reporting requirements, with potential criminal liability for violations. In case of spill, in any amount, see section on "Preparing to Deal with Spill." All spills must be minimized. Personnel can limit a spill by closing a valve that was accidentally opened, stopping any pumping through a ruptured line, or plugging a leak. Various methods, equipment, and materials are used to clean up spills. The type of cleanup used is determined by the type of product, where the spill occurs, weather conditions, and special considerations. Special considerations include closeness to drinking water sources, fishing grounds, wildlife habitats, bathing beaches, and recreational areas.
Spills on Dock or Ship
If there is a spill on the dock or ship, transfer operations must be stopped. If possible, the spill should be bailed into the cargo tank or bulkhead. Remaining product should be absorbed with absorbent material. Care should be taken to remove possible sources of vapor ignition.
Spills on Water
A number of steps must be followed when handling product spilled on water. These steps are given below.
· · Transfers of nonpersistent fuels such as JP-8 and gasoline must not be boomed, unless ordered by the Coast Guard.
· · Fixed boom will not be required in areas of swift current (1.5 knots or greater) when fuel will be deflected over the top or under the boom.
· · Do not boom in situations deemed unsafe.
NOTE: Chemical dispersants must be approved by the EPA.
Spills on Shore
Spilled product that comes ashore may be removed mechanically or by detergents. The quicker the cleanup, the less the spread of contaminants.
NOTE: All detergents used must be approved by the EPA.
SAFE HANDLING OF JET FUEL AND KEROSENE
The handling of jet fuel (JP-4 or JP-8) and kerosene creates special hazards. The safety precautions that must be followed when jet fuel and kerosene are loaded into tankers, barges, or storage facilities are given below.
WARNING These hazards involve the discharge of static electricity, which is caused by turbulence, low flashpoint, fast rate of flow, and water in the product. |
LOADING PROCEDURES
As soon as the vessel is docked, the terminal chief should review the loading plans with the master of the vessel. They should agree on any changes. The procedures for loading are described below:
Grounding
After the vessel is moored and all safety precautions are taken, and before cargo hoses are connected, the vessel must be grounded to the dock. To ground a vessel, personnel must--
Deballasting
Often, quantities of ballast water, needed to maintain proper vessel trim, are delivered to a terminal. The ballast must be removed from the vessel before it is loaded. It is against regulations to dump water containing petroleum products overboard. The best way to deballast at the terminal is to pump the ballast through a separate pipeline and oil and water separator to shore ballast tanks. Sometimes tank barges are used as ballast tanks. The terminal may not have a separate pipeline to handle ballast or the vessel may not have a stripping system. In these cases, cargo lines and pumps may be used if ballast water is clean and if lines and pumps are drained well after they have been used for ballast. Deballasting procedures must be followed carefully because product contamination may result from improper handling of ballast water. When pumping ballast ashore, personnel must--
Inspecting Vessel
Before product is loaded aboard a vessel, each tank compartment and all pumping and cargo lines must be inspected by the shore petroleum inspector. To certify that they are suitable to receive product, the inspector must-
Connecting Cargo Hose
The terminal furnishes hoses for loading and unloading vessels that are operated by non-DOD personnel. These hoses are usually connected and disconnected by shore operators. However, if the master of the vessel desires, the hoses may be connected or disconnected by vessel personnel at the risk of the vessel. When vessels have military operators, the vessel personnel normally connect and disconnect hoses on the vessel and the shore personnel connect and disconnect hoses on the shore. Military tank ships, fuel barges, and other vessels usually carry hoses; however shore hoses should be used when possible to save time. Most tankers have American standard 4-, 6-, or 8-inch flanges for hose attachment. They will cause no problem. Some tankers may have foreign made flanges or flanges with irregular spacing between the holes that need adapters or C-clamps. Older tankers may use the same spacing between holes for both 4- and 6-inch flanges. The terminal should have a set of straight and reducing adapter spools on hand to cover all normal requirements. It should have several sets of bolts, preferably of alloy steel. In all cases, at least four bolts will be used per coupling unless a camlock flange or C-clamp is used. If C-clamps are used, their strength must be verified by test or calculation. To prevent sliding or twisting, at least two bolts must be inserted through the vessel flange and hose flange when C-clamps are used. Although it is hazardous to do so, C-clamps may be knocked off in an emergency. Quick-acting clamping devices should be used instead of C-clamps, when possible. To connect a cargo hose, personnel must--
Connecting Loading Arms
At some tanker loading facilities, marine loading arms (Figure 4-10) are used instead of cargo hose. The arms are operated by cables and hydraulics. Most marine loading arms have hydraulic connections instead of flange connections. To connect loading arms, use the following procedures:

Figure 4-10. Marine loading arm
Heating Cargoes
When tanks have heater coils, viscous products in the tanks should be heated to prescribed temperatures before transfer operations begin. Prescribed temperatures must not be exceeded. Very high temperatures deteriorate products and can cause vapor lock in pumps. Navy special burner fuel oil and heavy lubricating oils should be heated to above 100° F, but not over 120° F.
Pumping Product
Shore pumps usually are used to load vessels. If possible, the pier lines should be filled with product and samples should be tested before the vessel arrives. All valves to be used on the shore lines should be opened, except those used to prevent cross transfer and the valve at the pier hose connection. Special procedures should be followed when jet fuels or kerosene is pumped. Procedures to pump product are as follows:
Performing Follow-Up Procedures
Certain follow-up procedures must be performed after a vessel is loaded. These procedures are as follows:
Refueling and Bunkering Tankers
Tankers may be refueled at the port terminal. The same procedures are used to issue fuel as those used to load fuel in the tanker. All bunkering operations should be recorded on DD Form 250-1. Samples must be taken to detect contamination. All safety precautions must be followed. After refueling, disconnect the refueling hose, open the grounding switch, and disconnect the bonding cable from the ship, in that order.
UNLOADING PROCEDURES
There are a number of procedures that must be followed to properly unload a vessel. These procedures are described below.
Grounding
After the vessel is moored and all safety precautions are taken, the vessel must be grounded to the dock before cargo hoses are connected. To ground a vessel, take the following steps:
Inspecting Vessel
The master of the vessel and the shore petroleum inspector must review the loading plan of the vessel for grades and amount of products carried. Also, they must review the layout of the cargo and the order in which products should be unloaded. Before unloading operations begin, the shore petroleum inspector must check the manifest and DD Form 250-1 for serial numbers of valve seals. The inspector must verify that each seal is intact on isolation valves and sea suction valves. He must document reasons for missing or broken seals. Ullages, temperatures, and water soundings must be taken on each compartment by ship personnel and witnessed by shore personnel. These readings are recorded on DA Form 3853-3. Great differences in compartment gages after loading and before discharging must be checked promptly. The vessel’s master must explain these differences in a written statement attached to the ullage report.
Sampling and Testing Product
If the product aboard the vessel has been inspected on procurement by the government, unloading operations may begin after a type C test of an all-levels sample of product from each compartment shows no contamination. Multiple tank composite samples must then be sent to the laboratory for type B-1 tests. If the product aboard the vessel has not been inspected on procurement by the government, the laboratory must run a type A test on samples from the upper, middle, and lower portions of each tank or an all-levels composite sample from each tank before discharge. If no testing facilities are readily available, any product in question should be placed in isolated storage until laboratory tests confirm quality.
Connecting Cargo Hose
The steps for connecting the cargo hose to unload a vessel are the same as those used to connect it to load a vessel. See page 4-18 for these steps.
Connecting Loading Arms
The steps for connecting loading arms to unload a vessel are the same as those used to connect them to load a vessel. See page 4-19 for these steps.
Heating Cargoes
The cargo may need to be heated before it is unloaded. See the information on heating cargoes given on page 4-20.
Pumping Product
There are certain procedures that must be followed to unload product from vessel to shore. These procedures are as follows:
Performing Follow-Up Procedures
Certain follow-up procedures must be performed after a vessel is loaded. These procedures are as follows: